This is a Bid Pricing Form for a geotechnical drilling and sampling contract with the Oregon Department of Transportation (ODOT) for project S-73000-00016301. The project involves providing drilling, geotechnical sampling, and instrumentation services at three separate landslide locations along Highway 227 Tiller Trail Highway in Jackson County, Oregon. The work encompasses multiple drilling and sampling methodologies across the three sites, including auger drilling (4-inch ID HSA at 105 feet per site), mud rotary drilling, rock coring (HQ3 Wire-Line at 75 feet per site), thin-walled Shelby tube sampling, 2-inch Standard Penetration Tests (48 each per site), Slope Inclinometer and Vibrating Wire Transducer installation (varying quantities by site), concrete and asphalt coring, and cuttings management. Each site also includes provisions for administrative and mobilization costs, as well as standby hours for ODOT-induced delays and fire regulation compliance.
The bid pricing form requires bidders to submit unit prices and lump sum costs for all specified line items across the three sites, with costs currently shown as $0.00 pending bidder submission. The form structure allows bidders to provide detailed pricing for labor, materials, equipment, and services required to complete the geotechnical investigation work in accordance with ODOT specifications and the Invitation to Bid requirements. No pricing information, contract award amounts, funding sources, or contract term details are provided in this blank pricing form template.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00016301 Request for Competitive Quotes.docx | DOCX document | |
| Sample Contract~54.docx | DOCX document | |
| Draft Exploration Plan - Checklist Reference Document.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| ATTACHMENT C - BID PRICING FORM S-73000-00016301 |
| Bidder name: |
| City, State: |
The Bidder proposes to furnish all material, equipment and labor, and perform all work for ODOT, in strict accordance with the ITB and the Plans, Specifications and other provisions incorporated in the ITB, on the basis of the lump sum or unit prices, or both, as follows:
| Site 1: HWY 227 MP 43.1 Tiller Trail Highway | |||||
| Item | Description | Est Qty | Unit | Unit Price | Total |
| 1 | Administration | 1 | LS | $0.00 | |
| 2 | Mobilization | 1 | LS | $0.00 | |
| 3 | Auger Drilling 4-inch ID HSA | 105 | Foot | $0.00 | |
| 4 | Mud Rotary Drilling | 1 | Foot | $0.00 | |
| 5 | Rock Coring HQ3 Wire-Line | 75 | Foot | $0.00 | |
| 6 | Thin-Walled Shelby Tube Sample (casing supplied by ODOT) | 1 | Each | $0.00 | |
| 7 | 2-inch SPTs | 48 | Each | $0.00 | |
| 8 | SI + VWT Installation | 3 | Each | $0.00 | |
| 9 | Concrete / Asphalt Coring | 1 | Each | $0.00 | |
| 10 | Drums for Cuttings | 1 | Each | $0.00 | |
| 11 | Standby (ODOT Induced) | 8 | Hours | $0.00 | |
| 12 | Standby (Fire Regulations) | 8 | Hours | $0.00 | |
| BID TOTAL | $0.00 |
| Site 2: HWY 227 MP 44.1 Tiller Trail Highway | |||||
| Item | Description | Est Qty | Unit | Unit Price | Total |
| 12 | Administration | 1 | LS | $0.00 | |
| 14 | Mobilization | 1 | LS | $0.00 | |
| 15 | Auger Drilling 4-inch ID HSA | 105 | Foot | $0.00 | |
| 16 | Mud Rotary Drilling | 1 | Foot | $0.00 | |
| 17 | Rock Coring HQ3 Wire-Line | 75 | Foot | $0.00 | |
| 18 | Thin-Walled Shelby Tube Sample (casing supplied by ODOT) | 1 | Each | $0.00 | |
| 19 | 2-inch SPTs | 48 | Each | $0.00 | |
| 20 | SI + VWT Installation | 2 | Each | $0.00 | |
| 21 | Concrete / Asphalt Coring | 1 | Each | $0.00 | |
| 22 | Drums for Cuttings | 1 | Each | $0.00 | |
| 23 | Standby (ODOT Induced) | 8 | Hours | $0.00 | |
| 24 | Standby (Fire Regulations) | 8 | Hours | $0.00 | |
| BID TOTAL | $0.00 | ||||
| Site 3: HWY 227 MP 44.7 Tiller Trail Highway | |||||
| Item | Description | Est Qty | Unit | Unit Price | Total |
| 25 | Administration | 1 | LS | $0.00 | |
| 26 | Mobilization | 1 | LS | $0.00 | |
| 27 | Auger Drilling 4-inch ID HSA | 105 | Foot | $0.00 | |
| 28 | Mud Rotary Drilling | 1 | Foot | $0.00 | |
| 29 | Rock Coring HQ3 Wire-Line | 75 | Foot | $0.00 | |
| 30 | Thin-Walled Shelby Tube Sample (casing supplied by ODOT) | 1 | Each | $0.00 | |
| 31 | 2-inch SPTs | 48 | Each | $0.00 | |
| 32 | SI + VWT Installation | 3 | Each | $0.00 | |
| 33 | Concrete / Asphalt Coring | 1 | Each | $0.00 | |
| 34 | Drums for Cuttings | 1 | Each | $0.00 | |
| 35 | Standby (ODOT Induced) | 8 | Hours | $0.00 | |
| 36 | Standby (Fire Regulations) | 8 | Hours | $0.00 | |
| BID TOTAL | $0.00 |