About this file

This document provides details on base support equipment and facilities available to support a federal contract for the Selection, Screening, Discovery and Design of Alloys and Advanced Metals Processing Technologies (SDAMPT). The contract will take place at various buildings at Wright Patterson Air Force Base in Ohio from August 2021 through August 2028. Equipment available includes metalworking machines such as a 1000-ton vertical forge press, a 700-ton extrusion press, a 75-ton rolling mill, and a 250g vacuum arc melter. Additional equipment includes a Gleeble thermomechanical testing machine, mechanical testing load frames with induction heating capabilities, a torsion testing unit, heat treatment furnaces, a hot isostatic press, EDM machines, thermal analysis instruments, and machining equipment. The contractor will work with Air Force and Space Force scientists and engineers to conduct research and development, assist with operation of laboratories, perform modeling and analysis, evaluate material properties, conduct characterization, and advance manufacturing approaches for metallic materials. The end goal is to assess new metals technologies and transition advancements to the defense supply chain.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA8650‐21‐S‐5002

Attachment 8

3/31/2021

Base Support Equipment List & Available Base Facilities for

Certification of On-Site Contractor Support for Contract/Delivery Order “Selection, Screening, Discovery and Design of Alloys and Advanced Metals Processing

Technologies” (SDAMPT)

The following base support equipment and facilities at Wright Patterson AFB, OH will be available beginning 1 August 2021 through 1 August 2028:

Building 655, Rooms 048, 049, 047, 047A, 130, 133, 135, 138, 140

Description Quantity Erie vertical forge press, 1000‐ton 1 Lombard extrusion press, 700‐ton 1 Rolling mill, 75‐ton separation load 1 Vacuum arc melter, 250 g maximum charge size 1 Gleeble 3800 thermomechanical testing machine with torsion unit 1 Mechanical testing load frames (55 kip and 200 kip) with induction heating up to 1200degC and 1600degC in vacuum, digital image correlation system, extensometry 2 Torsion testing unit, 500 in‐lb torque, up to 1200degC 1 Heat treatment furnaces, max temperatures from 425‐1700degC; air, argon, and vacuum atmospheres 11 Hot isostatic press (up to 45 ksi and 2100degC) 1 Makino U6 Wire EDM 1 Differential scanning calorimeter and thermogravimetric analyzer unit 1 Dilatometer for up to 1100degC 1 Thermogravimetric analyzer with mass spectrometry 1 Plunge EDM 1 Machining equipment (lathes, drill presses) 2 Vacuum encapsulation apparatus 1 Centorr oil quench furnace 1 Rapid solidification melt caster 1 Crystalox single crystal growth apparatus 1 High performance computer workstations 2