This is a comprehensive set of construction contract specifications for the American River Common Features (ARCF) Lower American River Contract 3B North and South Erosion Protection project located in Sacramento, California. The United States Army Corps of Engineers (USACE) Sacramento District is seeking construction services for erosion control and levee strengthening along the north and south banks of the Lower American River, with an anticipated two-contract award approach.

The project involves extensive environmental protection, erosion control, and infrastructure improvements, including stream bank protection, levee stabilization, and habitat restoration. Key technical requirements include installing rock protection, constructing planting benches, implementing storm water pollution controls, managing biological resources (with specific protections for species like Valley Elderberry Longhorn Beetle and various fish species), and conducting archaeological and tribal cultural resource monitoring. The contract includes multiple construction phases spanning two years, with specific work windows, environmental restrictions, and detailed monitoring requirements. Contractors must comply with complex environmental regulations, obtain necessary permits, and implement comprehensive storm water and erosion control management plans. The project is expected to use design-bid-build procurement with awards based on lowest price to the government.

View the file

Other files

File Type Posted
B08 - Section 00 21 13 Draft Instructions to Bidders.docx DOCX document
LAR_C3BN_RTA_Erosion_22x34_v2.pdf PDF
LAR_C3BS_RTA_Erosion_22x34_v2.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INVITATION FOR BID IFB NO: W9123826BA003

DISTRIBUTION STATEMENT A

Not approved for public release; distribution is limited

AMERICAN RIVER COMMON FEATURES LOWER

AMERICAN RIVER CONTRACT 3B NORTH & SOUTH

SACRAMENTO COUNTY

SACRAMENTO, CA

PROJECT NO. 456852

SPECIFICATION NO. 2454

DESIGN FILE NO. 1-04-0583 (C3B North), 1-04-0662 (C3B South)

ARCF LAR Contract 3B North & South 2454 Sacramento County, CA

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 20 00 PRICE AND PAYMENT PROCEDURES

01 31 20 PROJECT TECHNICAL DATA MANAGEMENT AND VISUALIZATION

01 32 01 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 56 39 TREE AND PLANT PROTECTION

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL

01 71 10 MOBILIZATION AND DEMOBILIZATION

01 71 23 CONTRACTOR SURVEYS

01 78 00 CLOSEOUT SUBMITTALS

DIVISION 02 - EXISTING CONDITIONS

02 22 13 MOVEMENT AND VIBRATION ASSESSMENT

02 41 00 DEMOLITION AND DECONSTRUCTION

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 09 13 GEOTECHNICAL INSTRUMENTATION AND MONITORING

31 09 14 AUTOMATED DATA ACQUISITION SYSTEM (ADAS)

31 11 00 CLEARING AND GRUBBING

31 32 39 BIOENGINEERING PRACTICES FOR STREAM BANK AND SHORELINE

STABILIZATION

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 01 13 ASPHALT SURFACE TREATMENT

32 11 23 AGGREGATE BASE COURSE FOR FLEXIBLE PAVING

32 12 13 BITUMINOUS TACK COATS

32 12 16 ROAD-MIX ASPHALT PAVING

32 15 00 AGGREGATE SURFACING

32 92 33 GRASS SEEDING AND EROSION CONTROL

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 42 38 STONE PROTECTION

PROJECT TABLE OF CONTENTS Page 1 October 2025 RTA

APPENDIX A - GENERAL REEVALUATION REPORT HISTORIC PROPERTIES MANAGEMENT PLAN

APPENDIX B - LARCHMONT COMMUNITY PARK IMPROVEMENT AS BUILTS

-- End of Project Table of Contents --

ARCF LAR Contract 3B North & South 2453

The sections and paragraphs in the table below were provided by HDR:

Spec Section Paragraph 01 50 00 2.2.1.1 01 50 00 3.3.3 01 50 00 3.3.4 31 09 13* 31 09 14* *entire section was provided by HDR

October 2025 RTA

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

1.2 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS

1.3 SUBMITTALS

1.4 LIMITS ON HOURS OF OPERATION

1.4.1 City of Sacramento (Downstream Portion of Site 3-1)

1.4.2 County of Sacramento

1.5 GENERAL SAFETY REQUIREMENTS

1.6 PRIORITY SUBMITTALS FOR MOBILIZATION ONTO SITE

1.7 ANTITERRORISM (AT) - OPERATION SECURITY (OPSEC)

1.8 UTILITIES

1.8.1 Potholing of Underground Utilities

1.9 PLANNED UTILITY OUTAGES AND STREET CLOSURES

1.10 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

1.11 HAZARDOUS NOISE AREA

1.12 BID ITEM OVERRUN

1.13 NON CONTRACT WORK

1.14 DAMAGE TO ACCESS ROADS AND STAGING AREAS

1.14.1 Removal and Replacement of Bicycle and Pedestrian Pathways

1.14.2 Documentation Regarding Potential Damage

1.14.2.1 Preconstruction Quantity Survey Plan

1.14.2.2 Preconstruction Access Road and Staging Area Survey

1.14.2.3 Construction Access Road Monitoring Survey

1.14.2.4 Post Construction Access Road and Staging Area Survey

1.15 UNHOUSED POPULATION

1.16 ENVIRONMENTAL LITIGATION

1.17 WORK IN THE ACTIVE CHANNEL AND FLOODPLAIN

1.18 REGULATORY FLOOD SEASON REQUIREMENT

PART 2 PRODUCTS

2.1 GOVERNMENT FURNISHED MATERIALS

PART 3 EXECUTION

3.1 AFTER AWARD DOCUMENTS

-- End of Section Table of Contents --

SECTION 01 00 00 Page 1

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this Section to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 415-1-15 (1989) Construction Time Extensions for Weather

1.2 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS

Promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:

Federal Veteran employment information at http://www.fedshirevets.gov/index.aspx

Department of Labor Veterans Employment Assistance http://www.dol.gov/vets/

Department of Veterans Affairs-VOW to Hire Heroes Act http://benefits.va.gov/vow/

Army Wounded Warrior Program http://wct.army.mil/modules/employers/e1-hireOurSoldiers.html

U.S. Chamber of Commerce Foundation-Hiring Our Heroes http://www.hiringourheroes.org/

Guide to Hiring Veterans - Reference Material https://www.dol.gov/veterans/Employer-Guide-to-Hire-Veterans-DEC-2017.pdf

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

After Award Documents

High Water Risk Management Plan ; G

SECTION 01 00 00 Page 2

Potholing Records

Preconstruction Quantity Survey Plan ; G

Preconstruction Access Road And Staging Area Survey ; G

Transient Population Safety Plan ; G

SD-05 Design Data

Construction Access Road Monitoring Survey

SD-11 Closeout Submittals

Post Construction Access Road And Staging Area Survey ; G

Post Construction Quantity Survey Plan ; G

1.4 LIMITS ON HOURS OF OPERATION

Work hours must not vary unless otherwise approved by the Contracting Officer. No work or hauling is to take place on holidays without permission given by the Contracting Officer. Staging and access areas may have limited access beyond these hours of operation. Refer also to paragraph TEMPORARY ACCESS AND STAGING in Section 01 50 00 TEMPORARY

CONSTRUCTION FACILITIES AND CONTROLS.

1.4.1 City of Sacramento (Downstream Portion of S ite 3-1)

Monday through Saturday, Contractor's hours of operation, including equipment warm-up, must be limited to daylight hours but not earlier than 7:00 A.M. and not later than 6:00 P.M. On Sunday, Contractor's hours of operation must be limited to daylight hours but not earlier than 9:00 AM and not later than 6:00 PM.

1.4.2 County of Sacramento

Monday through Friday, Contractor's hours of operation, including equipment warm-up, must be limited to the hours of 6:00 A.M. and not later than 8:00 P.M. On Saturday and Sunday, Contractor's hours of operation must be limited to the hours of 7:00 AM and not later than 8:00 PM.

1.5 GENERAL SAFETY REQUIREMENTS

See Section 01 35 26 GOVERNMENTAL SAFTEY REQUIREMENTS.

1.6 PRIORITY SUBMITTALS FOR MOBILIZATION ONTO SITE

A partial list of priority submittals for this Contract is provided below for the Contractor's convenience. It is recommended that the Contractor prioritize these submittals prior to mobilization at their own discretion.

The parent specification section and paragraph for each submittal is given in the table; submittal requirements for each submittal can be found at its corresponding parent section and paragraph.

SECTION 01 00 00 Page 3

PRIORITY SUBMITTALS LIST

Submittal Name Parent Section No.

Preconstruction Quantity Survey Plan 01 00 00

Transient Population Safety Plan 01 00 00

High Water Risk Management Plan 01 00 00

Potholing Records 01 00 00

Preconstruction Access Road and Staging Area Survey 01 00 00

Permits 01 11 00

Data Management Plan 01 31 20

Project Scheduler Qualifications 01 32 01

Preliminary Project Schedule 01 32 01

Initial Project Schedule 01 32 01

Submittal Register 01 33 00

Accident Prevention Plan (APP) 01 35 26

Hot Work Permit 01 35 26

Certificate of Compliance 01 35 26

Contractor Quality Control Plan 01 45 00

Construction Site Plan 01 50 00

Haul Route Plan 01 50 00

Sign Legend Orders 01 50 00

Temporary Access Ramp Plan 01 50 00

Competent Person Qualifications 01 50 00

Load Distribution Platform (LDP) Plan 01 50 00

Traffic Control Plan 01 50 00

Bike Path Detour Plan 01 50 00

Certified Arborist 01 56 39

Photo Documentation of Each Tree 01 56 39

SECTION 01 00 00 Page 4

PRIORITY SUBMITTALS LIST

Submittal Name Parent Section No.

Temporary Root Protection Matting 01 56 39

All SD-01 Preconstruction Submtitals 01 57 19

SWPPP 01 57 23

BMP Product Data 01 57 23

Mobilization/Demobilization Work Plan 01 71 10

Construction Surveying Work Plan and Schedule 01 71 23

Quality Control Plan 01 71 23

Preliminary Survey 01 71 23

Professional Certification and Work Experience 01 71 23

All SD-01 Preconstruction Submittals 02 22 13

Televised Report 02 22 13

CCTV Technician Qualifications 02 22 13

Demolition/Deconstruction Plan 02 41 00

Earthwork Survey 31 00 00

Engineered Fill Survey 31 00 00

Plan of Operations 31 00 00

Borrow Site Soil Sampling 31 00 00

Laboratory Qualifications 31 00 00

Borrow Area Chemical Suitability Certification Report 31 00 00

All SD-01 Preconstruction Submittals 31 09 14

All SD-02 Shop Drawings 31 09 14

All SD-03 Product Data 31 09 14

Permission to Dispose of Cleared Materials 31 11 00

Certified Arborist Qualifications 31 11 00

SECTION 01 00 00 Page 5

PRIORITY SUBMITTALS LIST

Submittal Name Parent Section No.

Plant, Equipment, and Tools 32 11 23

All SD-01 Preconstruction Submittals 35 42 38

All SD-05 Design Data Surveys 35 42 38

All SD-06 Test Reports 35 42 38

Turbidity Curtain 35 42 38

1.7 ANTITERRORISM (AT) - OPERATION SECURITY (OPSEC)

a. General Security Requirements and Guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor ("Contractor") and all subcontractor employees) supporting the performance requirements of this contract.

The Contractor is responsible for compliance with these security requirements. Questions regarding security matters must be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel must complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor must provide written documentation (e.g., email or memorandum) to the Government representative. The documentation must include the names of contract personnel trained and which training they completed; the Contractor must maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel must comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as "RAMs"), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures --this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor must ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

b. Antiterrorism (AT) Level I Training: All contract personnel requiring

SECTION 01 00 00 Page 6 routine access to Army installations, facilities, and controlled access areas, or requiring network access must complete initial and annual refresher AT Level I awareness training. Online AT Level I awareness training is available at https://jko.jten.mil/ (website subject to change).

c. Physical Security and Access Control Requirements: All contract personnel requiring physical access to a federal installation or facility must comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US must be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as "NCIC-III") and Terrorist Screening Database (commonly referred to as "TSDB"). Contract personnel must comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities must coordinate escorted access with the Government representative, as needed.

Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property must comply with key and lock control procedures of the RA.

d. Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel must receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.

e. Pre-screen Candidates using E-Verify Program: Contractors must comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at ( https://www.e-verify.gov/ ) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates must be provided to the COR no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.

1.8 UTILITIES

Immediately notify the Contracting Officer in writing if utilities not shown on the Drawings and not visible as to the date of this contract are encountered within the construction limits of the entire project, and such utilities will interfere with construction operations, to enable a determination by the Contracting Officer as to the necessity for removal or relocation. If such utilities are removed or relocated as directed by the Contracting Officer, an equitable adjustment in the contract price must be made pursuant to the Contract Clause CHANGES to cover the cost of any additional pertinent work or delay.

SECTION 01 00 00 Page 7

Pumps may turn on automatically. Coordinate with the County and City of Sacramento, Department of Utilities for shutdown when performing work.

1.8.1 Potholing of Underground Utilities

Perform potholing and submit the potholing records to the Contracting Officer, prior to excavation or work near existing underground utilities.

Potholing information at each pothole location must contain:

a. Owner of utility

b. Horizontal and vertical location by coordinates and elevation on project datum

c. Depth of cover

d. Size, material, and description of pipe, conduit encasement, or facility

1.9 PLANNED UTILITY OUTAGES AND STREET CLOSURES

All utility outages and street closures to be of as short a duration as possible and to be scheduled as far in advance as possible with the Contracting Officer, in no case less than 7 days before the outage or closure. Obtain from the Contracting Officer in writing a statement or schedule giving the permissible times of outages or closures for particular installations and the maximum time allowed for each. Strictly observe such schedules and the Contractor will be held responsible for any violations.

1.10 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

This provision specifies the procedure for the determination of time extensions for unusually severe weather. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule will reflect these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

(07) (07) (06) (03) (02) (01) (00) (00) (01) (02) (04) (06)

Upon execution of the Notice to Proceed (NTP) and continuing throughout

SECTION 01 00 00 Page 8 the contract, the Contractor will record on the daily Contractor Quality Control (CQC) report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. Refer to ER 415-1-15 .

1.11 HAZARDOUS NOISE AREA

Provide adequate ear protection for Contractor's personnel at the job site.

1.12 BID ITEM OVERRUN

Throughout the contract (at a minimum, every two weeks), monitor placement or installation of unit price items (if any) with respect to the original estimated quantities shown in the contract. If placement or installation indicates a possible overrun with respect to the original estimated quantities shown in the contract, immediately provide written notification to the Contracting Officer with revised total estimated quantities.

1.13 NON CONTRACT WORK

Do not perform any work or erect any structure for third parties, landowners or otherwise, without prior approval of the Contracting Officer.

1.14 DAMAGE TO ACCESS ROADS AND STAGING AREAS

Preserve and protect all existing private or project access or right-of-way roads, off-site staging area (if applicable), and bicycle and pedestrian pathways. At the completion of work and prior to the Contractor leaving the project, restore to pre-project conditions all such access roads, staging areas, and pathways. Repairs include replacement of base rock and surface treatment as required and as approved by the County of Sacramento. Refer also to paragraph PROTECTION OF TRAFFIC in Section

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS.

1.14.1 Removal and Replacement of Bicycle and Pedestrian Pathways

Remove existing paved bicycle and pedestrian pathways within the work limits as shown on the Drawings before beginning levee improvements and material hauling activity. Construct temporary paved bicycle and pedestrian pathways as shown on the Drawings. After completion of levee improvements and material hauling activity, replace bicycle and pedestrian pathways on their original alignments to meet the requirements of the Drawings, Section 32 11 23 AGGREGATE BASE COURSE FOR FLEXIBLE PAVING, Section 32 12 16 HOT-MIX ASPHALT PAVING (HMA) FOR ROADS, and Sacramento County standards. Temporary and permanent bicycle and pedestrian pathway construction includesreplacement of base rock and surface treatment as required and as approved by the County of Sacramento.

Preconstruction and post-construction surveys must include all bicycle and pedestrian pathways used in the operations inside and at least 200 feet outside the defined work limits on the Drawings. The Contracting Officer and County of Sacramento will determine, based on review of surveys, if repair of bicycle and pedestrian pathways used by the Contractor is required. If repairs are deemed necessary, perform repairs as-directed at no additional cost to the Government to meet the standards of the Drawings, Section 32 11 23 AGGREGATE BASE COURSE FOR FLEXIBLE PAVING, Section 32 12 16 HOT-MIX ASPHALT PAVING (HMA) FOR ROADS, and Sacramento County standards.

SECTION 01 00 00 Page 9

1.14.2 Documentation Regarding Potential Damage

1.14.2.1 Preconstruction Quantity Survey Plan

Complete and submit a Preconstruction Quantity Survey Plan , at least 30 days prior to mobilization, stating the names of personnel and license number who will be performing the Preconstruction Survey and the Post-Construction Survey. Include the procedures to follow in conducting the surveys. Include all structures within 200 feet of construction limits.

1.14.2.2 Preconstruction Access Road and Staging Area Survey

Complete and submit a Preconstruction Access Road and Staging Area Survey including digital video and digital photographs of all public, private, and project access or right-of-way roads, and all bicycle and pedestrian pathways before construction begins. Submit the digital video and the digital photographs before the start of construction operations. The preconstruction access road survey must clearly identify all pavement markings to facilitate replacement of markings should replacement of pavement be required after construction.

For all portions of the access, haul routes, and work limits that encompass the top of levee, provide geotagged survey points at 10 foot increments in each wheel track on the levee crest, accurate to the nearest tenth of a foot. For areas with aggregate surface, fill and compact ruts of less than 6 inches with aggregate surface as specified in Section 32 15 00 . Contractor to immediately notify the Contracting Officer if ruts are greater than 6 inches deep or extending below the aggregate base layer are identified. The Contracting Officer will provide direction on method required to fix ruts greater than 6 inches . Blading is not allowed.

The preconstruction survey must also document the condition of the driveway, sidewalk, and discharge pipes at the Wilhaggin Pump Station and all other utilities within the work area limits that cross under the levee road. Refer to Section 02 22 13 MOVEMENT AND VIBRATION ASSESMENT for additional requirements.

1.14.2.3 Construction Access Road Monitoring Survey

During construction of the project, submit a Construction Access Road Monitoring Survey on a monthly basis. This includes digital video, digital photographs, and rutting dimensions/locations along the length of the Access Road that coincides with the top of levee. At the end of the project, all Construction Access Road Monitoring Surveys must be complied and submitted as part of project closeout. See paragraph DAMAGE TO ACCESS ROADS AND STAGING AREAS for more information.

1.14.2.4 Post Construction Access Road and Staging Area Survey

After completion of construction of the project, submit a Post Construction Access Road and Staging Area Survey as well as a Post Construction Quantity Survey Plan including digital video and digital photographs of the same locations where preconstruction digital video and digital photographs were taken. Include all structures within 200 feet of construction limits.

SECTION 01 00 00 Page 10

1.15 UNHOUSED POPULATION

Assist the Government's public outreach program during the Contract performance period and post notifications as determined by the Government.

The City of Sacramento Police Department Impact Team will relocate the transient persons. Enforcement requests must be made to the Contracting Officer at the end of the notice period if the excluded phase work area is repopulated. Do not attempt to move members of the transient population remaining in or returning to work areas, which is the responsibility of local law enforcement or other authorized agencies or services.

Be responsible for the safety of the public within the limits of construction during the course of construction. In particular, the project site is a known location of transient persons. Prior to the commencement of construction activities, submit a Transient Population Safety Plan depicting proposed phasing, signage, fencing, and other protective measures to provide for the safety of the public and transient community.

At a minimum the plan must include the following:

a. Work zones from which the public and transient population must be excluded during the various phases of construction.

b. Safety fencing locations.

c. Proposed signage to be placed, including frequency of signage.

d. Locations within the project limits that remain open to the public during periods of non-construction activity based on various phases of construction.

e. Identification of public access and public path of travel during various phases of construction.

f. Locations and duties of flagmen at Wilhaggin Access and Watt Avenue bridge haul route.

1.16 ENVIRONMENTAL LITIGATION

a. If the performance of all or any part of the work is suspended, delayed, or interrupted due to an order of a court of competent jurisdiction as a result of environmental litigation, as defined below, the Contracting Officer, at the request of the Contractor, is to determine whether the order is due in any part to the acts or omissions of the Contractor or a subcontractor at any tier not required by the terms of this contract. If it is determined that the order is not due in any part to acts or omissions of the Contractor or a subcontractor at any tier other than as required by the terms of this contract, such suspension, delay, or interruption is to be considered as if ordered by the Contracting Officer in the administration of this contract under the terms of the SUSPENSION OF WORK clause of this contract. If the period of such suspension, delay or interruption is unreasonable, and an adjustment is to be made for any increase in the cost of performance of this contract (excluding profit) as provided in that clause, subject to all the provisions thereof.

b. The term "environmental litigations" as used herein, means a lawsuit alleging that the work will have an adverse effect on the environment or that the Government has not duly considered, either substantively

SECTION 01 00 00 Page 11 or procedurally, the effect of the work on the environment.

1.17 WORK IN THE ACTIVE CHANNEL AND FLOODPLAIN

The proposed work is located within the floodplain of the Lower American River. The site is subject to seasonal flooding by elevated-flow events.

Some elevations shown in the Drawings including the finish grade of sections of the planting benches are below water levels typically exceeded during the summer months and will be constructed in the active channel.

Existing ground, subgrade, and finish grade elevations along the buried rock toe may also be below the instream water levels. The table below provides 95% non-exceedance monthly water surface elevation (stage) computed from hourly stage data recorded at the H-Street stream gage between July 1995 and July 2020. It is the Contractor's responsibility to determine schedule, control of water, and dewatering needs at the project site. Make no claim for costs or damages incurred as a result of having to conduct construction activities during inundated or saturated site conditions for water levels below the monthly 95% non-exceedance values identified in the table below.

Lower American River Monthly Non-Exceedance Data

Month 95% Non-Exceedance (Stage)

January 28.9

February 29.7

March 26.3

April 26.4

May 22.4

June 21.1

July 18.7

August 18.3

September 18.3

October 17.9

November 17.9

December 25.3

1.18 REGULATORY FLOOD SEASON REQUIREMENT

No work within the floodway or excavation into the existing levee section is permitted during the Regulatory Flood Season for the Lower American River, which extends from November 1 to April 15.

Submit an High Water Risk Management Plan for Government approval that outlines all features of work needed to strip and grub the site, prepare

SECTION 01 00 00 Page 12 the subgrade, and complete erosion protection placement. Include in the plan placement schedule and rates required for each feature of work in order to complete the erosion protection work by October 31st. For additional restrictions on work below the ordinary high water mark refer to section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS.

PART 2 PRODUCTS

2.1 GOVERNMENT FURNISHED MATERIALS

The Government will provide digital media at the preconstruction conference that contains the materials specified in SECTION 01 78 00

CLOSEOUT SUBMITTALS.

PART 3 EXECUTION

3.1 AFTER AWARD DOCUMENTS

Provide conformed hard copy sets reproduced from the PDF Contract Documents provided by the Contracting Officer at the time of award. The hard copy drawings must be sets of ANSI D (22" x 34") and sets of half size (11" x 17") 3-hole punched and bound with metal posts. The sets of specifications must be standard letter (8-1/2" x 11") 3-hole punched and bound with metal posts. Provide two (2) sets of each. Submit these documents within 5 work days of the receipt of the AWARD documents from the Government.

-- End of Section --

SECTION 01 00 00 Page 13

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 WORK COVERED BY CONTRACT DOCUMENTS

1.3.1 Project Description

1.3.2 Location

1.3.2.1 C3B-North

1.3.2.2 C3B-South

1.3.3 Phasing of Work (C3B - North and South)

1.3.3.1 Phase 1 - Tree Clearing and Transplant

1.3.3.2 Phase 2 - Erosion Protection (Year 1)

1.3.3.2.1 Restrictions

1.3.3.3 Phase 3 - Erosion Protection (Year 2)

1.3.3.3.1 Restrictions

1.3.3.4 Phase 4 - Greening

1.4 EXISTING WORK

1.5 DOCUMENTS PROVIDED BY THE GOVERNMENT

1.5.1 Documents Provided For Information Only

1.5.1.1 Historic Properties Management Plan

1.6 SUPERVISION BY THE CONTRACTOR

1.6.1 Contract Authority

1.6.2 Minimum Communication Requirements

1.6.3 Superintendent Qualifications

1.6.4 Non-Compliance Actions

1.6.5 Preconstruction Meeting

1.6.6 Electronic Mail (e-mail) Addresses

1.7 LOCATION OF UNDERGROUND UTILITIES

1.7.1 Notification Prior to Excavation

1.7.2 Damage of Existing Facilities

1.8 PARTNERING

1.9 COORDINATION

1.9.1 Coordination with Others

1.9.1.1 List of Other Contracts

1.9.2 Government Work

1.10 NOTICES

1.11 PERMITS

1.11.1 General

1.11.2 Permits Obtained By The Contractor

1.11.2.1 Encroachment Permit

1.11.2.2 Haul Route Permit

1.11.2.3 Permits for Road Closures and Traffic Control

1.11.2.4 Utility Connection Permit

1.11.2.5 Dewatering/Discharge Permit

PART 2 PRODUCTS

SECTION 01 11 00 Page 1

PART 3 EXECUTION

ATTACHMENTS:

Haul Route Ingress/Egress and Direction Traffic Flow

DE-304-App

-- End of Section Table of Contents --

SECTION 01 11 00 Page 2

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety -- Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Permits

Excavation And Placement Quantity Tracker ; G

1.3 WORK COVERED BY CONTRACT DOCUMENTS

1.3.1 Project Description

The work includes stream bank protection and stabilization of the existing Lower American River (LAR) levee system to protect critical infrastructure against the effects of erosion during large flood events. Refer to Drawings for project location and limits.

The work involves, but is not limited to: clearing, grubbing, and stripping within the construction limits and areas designated in the Drawings and by the Contracting Officer; protecting-in-place vegetation, existing facilities, and structures not scheduled for removal; earthwork, including import of earthen and rock materials, construction of stone protection structures shown on the Drawings, construction of a temporary haul route beneath the Watt Avenue bridge on the north bank of the LAR, construction of temporary and permanent bicycle and pedestrian pathway and public access improvements, installation of planting benches, instream wood structures and live cuttings; grass seeding and erosion control;

maintenance of seeding to meet performance requirements through the Establishment Period as defined in these Specifications; replacement of existing infrastructure disturbed or relocated by construction, and all incidental related work.

SECTION 01 11 00 Page 3

1.3.2 Location

The work is located on the LAR within the American River Parkway in Sacramento, California and consists of specific sections of riverbank on both the north and south banks. The exact Site locations are shown on the Drawings.

1.3.2.1 C3B-North

Includes two project sites: Site 3-1 is located along the north bank of the LAR from the Howe Avenue Bridge at River Mile (RM) 7.7 extending upstream to RM 8.8, approximately as indicated; and Site 4-2 is also on the north bank of LAR from RM 9.8 upstream to RM 10.3, approximately as indicated.

1.3.2.2 C3B-South

Includes one project site: Site 4-1 is located along the south bank of the LAR from the Watt Avenue Bridge at RM 9.1 extending upstream to RM 10.5, approximately as indicated.

1.3.3 Phasing of Work (C3B - North and South)

The year listed in this section are defined as the construction year for the Erosion Protection Contract with Year 1 anticipated to be the year of the Contract Award.

Haul route traffic is defined as the routing of haul trucks, loaded or unloaded, through points of ingress/egress on the site. For the purposes of this Section, haul trucks are trucks that are used to carry material from outside the work limits to inside the work limits. Refer to Section 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS for definition of haul trucks and the Haul Route Ingress/Egress and Direction Traffic Flow map attached at the end of this section.

See table below for ingress/egress locations referenced in Paragraph Restrictions under Paragraph Phase 2 - Erosion Protection (Year 1) and in Paragraph Restrictions under Paragraph Phase 3 - Erosion Protection (Year 2):

Ingress/Egress Name Nearby Stationing Sheet ID

University Park NB 455+80 C3B North, GC101

Kadema NB 497+40 C3B North, GC102

Wilhaggin NB 558+20 C3B North, GC105

Harrington Way NB 656+60 C3B North, GC108

Watt Avenue SB 487+60 C3B South, GC101

Mayhew Drain N/A* C3B South, GC104

SECTION 01 11 00 Page 4

Ingress/Egress Name Nearby Stationing Sheet ID

*Intersection of haul route along Mayhew Drain at Folsom Blvd does not have stationing nearby but is shown in plan view H1 on GC104 with the text "Stablized Vehicle Entrance" near points WL 390 and WL 392.

No other haul route traffic points of ingress/egress can be used or created unless approved by the Contracting Officer. Additionally, haul route traffic direction is restricted by year to minimize damage to the buried cut-off-wall beneath the levee crown. No other haul route traffic points of ingress/egress can be used or created unless approved by the Contrcting Officer. Loaded trucks could create more damage than unloaded trucks generally, but the cut-off-wall’s strength varies beneath the levee crown, making optimization difficult. These restrictions were developed with the assumption that haul route traffic is minimized over particularly vulnerable areas of the cut-off-wall.

If the Contractor recognizes that changes to the restrictions listed below could minimize loaded trucks on the levee crown, discuss with the Contracting Officer. Restrictions may be able to be adjusted to accommodate theoretical haul route plans.

Small personal vehicles and trailers carrying equipment are not required to follow these haul route traffic restrictions in paragraph PHASE 2 - EROSION PROTECTION (YEAR 1) and paragraph PHASE 3 - EROSION PROTECTION

(YEAR 2).

1.3.3.1 Phase 1 - Tree Clearing and Transplant

Work to be completed under a separate service contract. Clearing work for the first construction season will occur between September 1 of Year 0 and February 1 of Year 1. Clearing work for the second construction season will occur between September 1 Year 1 and February 1 Year 2. Elderberry transplanting will occur between November 1 Year 0 and February 15 Year 1.

1.3.3.2 Phase 2 - Erosion Protection (Year 1)

Commence work after the regulatory flood season restriction of November 1 Year 0 to April 15 Year 1. Work on levee embankment rock slope protection for Sites 3-1 and 4-2 may commence before in-water work is permitted in Year 1. The in-water work window is between July 1 and October 31.

Additionally, it is anticipated that the downstream portion of Site 3-1 (Segment 3-9), Site 4-2, and the downstream portion of Site 4-1 (Segments 3-5 and 3-6) will be completed in Year 1.

1.3.3.2.1 Restrictions

Haul route ingress/egress points and direction provided for Year 1 cannot be changed due to risk reduction measures for the buried cut-off wall. See Attachment 1 - Haul Route Ingress/Egress and Direction Traffic Flow.

a. Haul route traffic for construction of C3B-North, Site 3-1, downstream of Watt Avenue Bridge, must pass from the ingress point of University Park to the egress point of Kadema.

b. Haul route traffic for construction of C3B-North, Site 4-2, upstream of Watt Avenue Bridge, must pass from the ingress point of Wilhaggin

SECTION 01 11 00 Page 5 to the egress point of Harrington Way.

c. Haul route traffic for C3-B North may not cross under Watt Avenue Bridge.

d. Haul route traffic for construction of C3B-South, Site 4-1, must pass from the ingress point of Watt Avenue to the egress point at Mayhew Drain.

1.3.3.3 Phase 3 - Erosion Protection (Year 2)

This phase will continue the erosion protection improvements for the upstream portions of Site 3-1, C3B-North haul route operations and site improvements under Watt Avenue, and Site 4-1 which will be completed in construction Year 2. Work is also subject to the regulatory flood season restriction.

1.3.3.3.1 Restrictions

Haul route ingress/egress points and direction provided for Year 2 cannot be changed due to risk reduction measures for the buried cut-off wall. See Attachment 1 - Haul Route Ingress/Egress and Direction Traffic Flow.

a. Haul route traffic for construction of C3B-North, Site 3-1, downstream of Watt Avenue Bridge, must pass from the ingress point of Wilhaggin to the egress point of University Park.

b. Haul route traffic for construction of C3B-South, Site 4-1, must pass from the ingress point of Mayhew Drain to the egress point of Watt Avenue.

1.3.3.4 Phase 4 - Greening

Work to be completed under a separate service contract. This phase includes the revegetation of the erosion features and surrounding areas impacted by construction which will commence following the completion of construction of any given area. Planting will start after the second and third phases are complete in the Spring of Year 2 and Year 3, respectively. This phase also includes a 3 to 5 year long plant establishment period consisting of irrigation, weed control, and browse control.

1.4 EXISTING WORK

Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.5 DOCUMENTS PROVIDED BY THE GOVERNMENT

An electronic copy of the plans and specifications, including all amendments, revisions, and modifications will be provided to the Contractor. These documents must be kept at the job site during the Contract performance period and be accessible to the Contracting Officer.

SECTION 01 11 00 Page 6

In addition, the following documents are provided and may be downloaded from System for Award Management (SAM): https://sam.gov/content/home .

1.5.1 Documents Provided For Information Only

1.5.1.1 Historic Properties Management Plan

a. Appendix A - American River Common Features Project General Reevaluation Report - Historic Properties Management Plan.

b. Appendix B - Larchmont Community Park As Builts

Updated information may be available at the time of Contract award.

Coordinate directly with Cordova Recreation and Park District (CRPD) for updated information post award.

1.6 SUPERVISION BY THE CONTRACTOR

1.6.1 Contract Authority

Appoint a site representative, satisfactory to the Contracting Officer, who has the authority to negotiate and execute supplemental agreements to the Contract. Contracting authority must include agreements up to $500,000.

1.6.2 Minimum Communication Requirements

Provide a minimum of one qualified superintendent, and one competent alternate, capable of reading, writing, and conversing fluently in the English language. The superintendent or alternate must be on the job-site at all times during the Contract performance period. In addition, the safety representative and Quality Control (QC) representative must also be capable of reading, writing, and conversing in the English language.

1.6.3 Superintendent Qualifications

The project superintendent must have a minimum of 10 years' experience in construction with at least 5 of those years as a superintendent on projects similar in scope (e.g. in-water construction), size, and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any time during the project.

1.6.4 Non-Compliance Actions

The project superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the Contract and for failure to manage the project to ensure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

SECTION 01 11 00 Page 7

1.6.5 Preconstruction Meeting

After issuance of notice to proceed but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the Contract including value engineering, safety program, preparation of the schedule of prices, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" submittal. Major subcontractors who will engage in the work must also attend.

1.6.6 Electronic Mail (e-mail) Addresses

Establish and maintain electronic mail (e-mail) capability along with the capability to open electronic attachments including text files, pdf files, and other similar formats. Within 10 days after issuance of notice to proceed, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this Contract including, but not limited to Contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use e-mail to notify the Contractor of site access conditions when emergency conditions warrant, such as high wind warnings or terrorist threats. Multiple e-mail addresses are not allowed.

Promptly notify the Contracting Officer, in writing, of any changes to this e-mail address.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail within its own organization including subcontractors, suppliers, and field offices.

1.7 LOCATION OF UNDERGROUND UTILITIES

Obtain utility encroachment permits prior to start of potholing or any otherexcavation, and comply with State and local requirements for locating and marking underground utilities. Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday.

Verify existing utility locations indicated on contract drawings, within area of work.

Identify and mark all other utilities not managed and located by the local utility companies. Scan within the construction limits with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated, or specified to be removed or relocated, that is indicated or discovered during scanning, in locations to be traversed by piping, excavations, and other work to be conducted or installed. Verify elevations as specified in Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS before installing new work closer than nearest manhole, valve, or other structure at which an adjustment in grade can be made.

Prior to relocating or modifying any utilities, coordinate temporary service outages with utility owners and the Contracting Officer.

1.7.1 Notification Prior to Excavation

Notify the Contracting Officer at least 48 hours prior to starting

SECTION 01 11 00 Page 8 excavation work. Submit a monthly Excavation and Placement Quantity Tracker .

For each new excavation, provide station-to-station numbering and offset of the excavations, the expected volumes of each type of material required, and the expected date of completion. Maintain this information in a spreadsheet and provide a completed copy with actual volumes for each material required and the actual date of completion.

1.7.2 Damage of Existing Facilities

Report damage to utility lines or subsurface construction immediately to the Contracting Officer. Contractor is responsible for the repair of damage to existing utility lines and any associated costs for repairs.

1.8 PARTNERING

To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the non-Federal Sponsors, the Government Design and Construction team and Subject Matter Experts, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.

1.9 COORDINATION

Refer to paragraph NOTICES for agency contact information.

1.9.1 Coordination with Others

Coordinate operations with the operations of other Contractors, other Government agencies, and others that may perform work in and around the jobsite or require access through the jobsite. In particular, Sacramento County will require access for the LAR Parkway operations and maintenance throughout construction. Maintain access on haul routes at all times for other contractors.

Coordinate work with the other Contractors to prevent delays to this project and interferences with those contracts. Expect minor delays and rescheduling due to these other contracts and work. Document coordination efforts in the project schedule and notify the Contracting Officer of coordination efforts, schedule accommodations and impacts.

Coordinate jobsite safety with each Contractor's respective safety officer and ensure safety requirements for all personnel occupying the jobsite are adhered to. The other contracts and work in the area of this project are listed below. These contracts will be considered in accordance with Contract Clause: 52.236-8 OTHER CONTRACTS.

1.9.1.1 List of Other Contracts

The following contracts have been awarded:

Contract 3A - W9123824C0014, ARCF Lower American River Erosion Contract 3A.

SECTION 01 11 00 Page 9

Contract 1 - W9123822C0007, ARCF Lower American River Erosion Contract Site 2-1.

Contract 2 - W9123822C0012, ARCF Lower American River Erosion Contract 2 Site 2-2 and Site 2-3.

Site 3-1, 4-1, 4-2; Tree Clearing and Transplanting. Coordinate with the Contractor performing this work for turnover of the NOI as specified in Section 01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL.

1.9.2 Government Work

The Government may perform work during the contract performance period;

the Contractor must coordinate and make allowances for:

a. Field Surveying

b. Environmental Monitoring

c. Geotechnical Sampling and Testing

d. Other work as directed by the…