Appendix C - Electrical Testing - Proposed Scheduled Outages.pdf

PDF 49 KB Posted

Attached to
H261--Triennial Electrical Distribution System Testing Federal contract opportunity
Solicitation number
36C25021Q1081
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10

About this file

This document outlines requirements for a federal contract to provide triennial electrical distribution system testing and maintenance services at the Department of Veterans Affairs LTC Charles S. Kettles VA Medical Center in Ann Arbor, Michigan. The contractor must be an experienced electrical contractor certified in electrical testing and safety standards. Services include inspecting, testing, and maintaining transformers; switchgears; switchboards; distribution panels; and related components. The contractor must clean, inspect for defects, test circuit breakers, calibrate relays, identify hotspots, and tighten connections. The contractor will also participate in a 4-hour power outage test, provide electrical safety training, and inspect and maintain automatic transfer switches. The contractor must submit written reports within 7 days of completing the work. The report must include test data, equipment conditions, deficiencies found, and corrective recommendations. The contractor schedule is due within 14 days of award and must avoid disruption to medical center operations.

View the file

Other files for this federal contract opportunity

Other files attached to H261--Triennial Electrical Distribution System Testing, newest first.
File Type Posted
36C25021Q1081 0001.docx DOCX document
Electrical Testing_VA Map.pdf PDF
Appendix E - Campus Electrical one line drawings.pdf PDF
Appendix E - Campus Electrical one line drawings MAP.pdf PDF
Appendix D - Equipment summary by drawing.xlsx XLSX spreadsheet
36C25021Q1081.docx DOCX document
Appendix F - All breaker summary section 4.2.1.1.pdf PDF
Appendix F - All relay table section 4.2.2.2.pdf PDF
Appendix D - Inventory of Items Tested_Previous Ks.xlsx XLSX spreadsheet
Appendix F - All fuse table section 4.2.3.2.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date Optional Revised Dates Equipment Name Area(s) Affected Description

TBD

B1W Substation #6

(Lighting)

B1W (Old Hospital) Commencement: 7:00AM

Projected duration: 8 Hours

This work will shutdown most lighting in the building. Only emergency lighting will remain in operation.

TBD

B32 Chiller Substation #1 N/A This work will be performed during normal hours. Outages will not be noticable.

TBD

B32 Chiller Substation #2 N/A This work will be performed during normal hours. Outages will not be noticable.

TBD

B1W Substation #4 B1W (Old Hospital) Commencement: 7:00PM

Projected duration: 8 Hours

Work will shut down a number of air handlers. All other loads will be powered by the building's emergency generator.

TBD

B1W Substation #5 B1W (Old Hospital) Commencement: 7:00PM

Projected duration: 8 Hours

Work will shut down a number of air handlers. All other loads will be powered by the building's emergency generator.

TBD

B1W Switchboard #3 B1W (Old Hospital) Commencement: 7:00PM

Projected duration: 8 Hours

Portions of the building will have loss of power for normal receptacles and select

HVAC systems and pumps.

TBD

B1W Switchboard #2 B1W (Old Hospital) Inspection only?

TBD

B1W Switchboard #1 B1W (Old Hospital) Commencement: 7:00PM

Projected duration: 8 Hours

Portions of the building will have loss of power for normal receptacles and select

HVAC systems and pumps.

TBD

B1W Emergency

Switchboard 1-Bi-1

Campus Emergency

Power System

Commencement: 7:00PM

Projected duration: 8 Hours

Emergency power to the Clinical Addition will not be immediately available in the event of a major utility power disruption.

TBD

Fire Pump Sub. 1-B-01

B1E Substation 1-1-04

Campus Fire Pump

Service & MEP Systems in Clinical Addition

Commencement: 7:00PM

Projected duration: 8 Hours

Fire pump will be down during this time. The fire alarm system will be closely monitored. In the event of a fire, power will be restored to the fire pump ASAP.

HVAC systems and miscellaneous pumps will be shut down in the west half of the

Clinical Addition.

TBD

B1E Substation 1-1-02

B1E Substation 1-1-03

Clinical Addition (East), Clinical Addition (X-Ray)

Commencement: 7:00PM

Projected duration: 8 Hours

Multiple components of the HVAC system (exhaust and supply) will be shut down.

Loading dock door operators will be off. Cart wash system will be shut off. X-ray

TBD

Isolation Bank A & B

Primary Switches &

Transformers & B31

Substations

B1W, B22, B28, & B31 Commencement: 7:00PM

Projected duration: 8 Hours

Both of these buildings will be reduced to emergency power only.

TBD

B1E Substation 1-1-01

B1E Substation 1-1-05

B1E (Entire Clinical

Addition)

Commencement: 7:00PM

Projected duration: 8 Hours

Receptacles and lights will be reduced to emergency power only.

TBD

B31/15 Transformer T-1

B31/15 Transformer T-2

B31/15 Transformer T-3

B31 (Research Building) Commencement: 7:00PM

Projected duration: 8 Hours

The entire building will be reduced to emergency power only.

TBD

Isolation Bank A & B

Secondary Selector

Switches

B1W (Old Hospital) Commencement: 7:00PM

These buildings will be reduced to emergency power only.

TBD

13.2kV Primary

Switchgear

Entire Campus Commencement: 7:00AM

Projected duration: 8 Hours

The entire building will be reduced to emergency and standby power only.

TBD

B32 Substation #1

B32 Substation #2

B32 (Energy Center) Commencement: 7:00AM

Projected duration: 10-12 Hours

Energy Center will be on emergency power only.

TBD

B28 Switchboards 28SBD-

28SWBD-2

28ESWBD-1

B28 (Nursing Home &

Med ECC)

Commencement: 10:00AM

Projected duration: 8-12 Hours

The building will be reduced to emergency power only. Computer network (VISTA, CPRS, BCMA) will be down. Omitted previously due to UPS battery reliability.

Upgrades since should be reviewed for impact on potential testing.

11/12/2014

General Notes:

1. Descriptions of services to be interrupted have been provided by hospital personnel based on previous testing procedures.

2. Each scheduled day is a block of work. For scheduling, days of work can be switched or moved around to accommodate hospital activites provided 72 hours advanced notice.

3. Switching and de-energizing of equipment will be by site personnel.

Keyed Notes:

a. Campus primary switchboard.

b. Includes switchboards 28SWBD-1, 28SWBD-2, & 28ESWBD-1.

c. Includes enclosed circuit breakers in rooms FG07 & FB07 serving automatic transfer switches (ATS').

Appendix C - Electrical Testing - Proposed Scheduled Outages