Appendix A - Price Sheet.xlsx
XLSX spreadsheet 35 KB Posted
- Attached to
- Nankin Mills Campus Improvements
- Solicitation number
- 37-25-049
- Issued by
- Wayne County, Michigan
About this file
The document is a Price Sheet (Appendix A) for the Wayne County Parks Nankin Mills Campus Improvements project, Control No. 37-25-049, soliciting bids for comprehensive campus renovations. The project encompasses improvements to multiple buildings including the Mill Building, Red Barn, Silo, Recreational Storage Building, Miller House, and Maintenance Administration and Storage Buildings. The bid requires detailed pricing across 33 construction divisions, with separate sections for each building and overall site work. The project timeline requires substantial completion within 700 calendar days of the Notice to Proceed, with an additional 30-day completion period and a two-year landscape establishment period.
The total project cost is estimated at $1,395,000, funded through the American Rescue Plan Act (ARPA) and Wayne County Parks millage. The pricing structure includes contingency percentages ranging from 5% to 20% for different building sections, and substantial allowances totaling $1,395,000 for items such as site security, winter conditions, hazardous material abatement, permits, surveys, testing, exhibits, furniture, appliances, and specialized equipment. Bidders are required to provide unit prices for various site work elements including specialty paving, concrete work, landscaping, parking lots, utilities, and infrastructure improvements. The bid emphasizes precise pricing documentation, with a warning that failure to complete the price sheet correctly could result in bid rejection.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table 1
| Appendix A - Price Sheet |
| Control No. 37-25-049 |
| Wayne County Parks Nankin Mills Campus Improvements |
Failure to complete and submit this form by the Bid Deadline shall result in your Bid being deemed nonresponsive and rejected without any further evaluation.
It Is the Bidders’ Responsibility to verify all work listed on the Price Sheet with the Specifications. The Totals must complete the intent of all the work identified in the Specifications. Quantities provided are not intended to be inclusive of all work. All quanties are provided as a courtesy only and construction must be completed per plans.
TYPE YOUR BID INTO THE APPROPRIATE CELLS BELOW - DO NOT HANDWRITE
DO NOT CHANGE FORMULAS OR ALTER PRICE SHEET
COMPANY NAME: ______________________________________________________________________________________
| Section A - Overall for Mill Building | |||
| NM | Mill Building | Total | |
| Div 1 | Project Requirements | ||
| Div 2 | Site Conditions | ||
| Div 3 | Concrete | ||
| Div 4 | Masonry | ||
| Div 5 | Metals | ||
| Div 6 | Woods & Plastics | ||
| Div 7 | Thermal & Moisture Protection | ||
| Div 8 | Opening | ||
| Div 9 | Finishes | ||
| Div 10 | Architectural Specialties | ||
| Div 11 | Equipment | ||
| Div 12 | Furnishings | ||
| Div 13 | Special Construction | ||
| Div 14 | Conveying Systems | ||
| Div 21 | Fire Protection | ||
| Div 22 | Plumbing | ||
| Div 23 | HVAC | ||
| Div 26 | Electrical | ||
| Div 27 | Communications | ||
| Div 28 | Electronic Safety & Security | ||
| Div 31 | Earthwork | ||
| Div 32 | Exterior Improvements | ||
| Div 33 | Utilities | ||
| Subtotal | $0.00 | ||
| Contingency (15%) | $0.00 | ||
| Section A Total: | $0.00 |
| Section B - Overall for Red Barn & Silo | |||
| B | Red Barn and Silo | Total | |
| Div 1 | Project Requirements | ||
| Div 2 | Site Conditions | ||
| Div 3 | Concrete | ||
| Div 4 | Masonry | ||
| Div 5 | Metals | ||
| Div 6 | Woods & Plastics | ||
| Div 7 | Thermal & Moisture Protection | ||
| Div 8 | Opening | ||
| Div 9 | Finishes | ||
| Div 10 | Architectural Specialties | ||
| Div 11 | Equipment | ||
| Div 12 | Furnishings | ||
| Div 13 | Special Construction | ||
| Div 14 | Conveying Systems | ||
| Div 21 | Fire Protection | ||
| Div 22 | Plumbing | ||
| Div 23 | HVAC | ||
| Div 26 | Electrical | ||
| Div 27 | Communications | ||
| Div 28 | Electronic Safety & Security | ||
| Div 31 | Earthwork | ||
| Div 32 | Exterior Improvements | ||
| Div 33 | Utilities | ||
| Subtotal | $0.00 | ||
| Contingency (10%) | $0.00 | ||
| Section B Total: | $0.00 |
| Section C - Overall for Recreational Storage Building | |||
| RS | Recreational Storage Building | Total | |
| Div 1 | Project Requirements | ||
| Div 2 | Site Conditions | ||
| Div 3 | Concrete | ||
| Div 4 | Masonry | ||
| Div 5 | Metals | ||
| Div 6 | Woods & Plastics | ||
| Div 7 | Thermal & Moisture Protection | ||
| Div 8 | Opening | ||
| Div 9 | Finishes | ||
| Div 10 | Architectural Specialties | ||
| Div 11 | Equipment | ||
| Div 12 | Furnishings | ||
| Div 13 | Special Construction | ||
| Div 14 | Conveying Systems | ||
| Div 21 | Fire Protection | ||
| Div 22 | Plumbing | ||
| Div 23 | HVAC | ||
| Div 26 | Electrical | ||
| Div 27 | Communications | ||
| Div 28 | Electronic Safety & Security | ||
| Div 31 | Earthwork | ||
| Div 32 | Exterior Improvements | ||
| Div 33 | Utilities | ||
| Subtotal | $0.00 | ||
| Contingency (10%) | $0.00 | ||
| Section C Total: | $0.00 |
| Section D - Overall for Miller House | |||
| MH | Miller House | Total | |
| Div 1 | Project Requirements | ||
| Div 2 | Site Conditions | ||
| Div 3 | Concrete | ||
| Div 4 | Masonry | ||
| Div 5 | Metals | ||
| Div 6 | Woods & Plastics | ||
| Div 7 | Thermal & Moisture Protection | ||
| Div 8 | Opening | ||
| Div 9 | Finishes | ||
| Div 10 | Architectural Specialties | ||
| Div 11 | Equipment | ||
| Div 12 | Furnishings | ||
| Div 13 | Special Construction | ||
| Div 14 | Conveying Systems | ||
| Div 21 | Fire Protection | ||
| Div 22 | Plumbing | ||
| Div 23 | HVAC | ||
| Div 26 | Electrical | ||
| Div 27 | Communications | ||
| Div 28 | Electronic Safety & Security | ||
| Div 31 | Earthwork | ||
| Div 32 | Exterior Improvements | ||
| Div 33 | Utilities | ||
| Subtotal | $0.00 | ||
| Contingency (20%) | $0.00 | ||
| Section D Total: | $0.00 |
| Section E - Overall Maintenance Administration Building | |||
| MA | Maintenance Administration Building | Total | |
| Div 1 | Project Requirements | ||
| Div 2 | Site Conditions | ||
| Div 3 | Concrete | ||
| Div 4 | Masonry | ||
| Div 5 | Metals | ||
| Div 6 | Woods & Plastics | ||
| Div 7 | Thermal & Moisture Protection | ||
| Div 8 | Opening | ||
| Div 9 | Finishes | ||
| Div 10 | Architectural Specialties | ||
| Div 11 | Equipment | ||
| Div 12 | Furnishings | ||
| Div 13 | Special Construction | ||
| Div 14 | Conveying Systems | ||
| Div 21 | Fire Protection | ||
| Div 22 | Plumbing | ||
| Div 23 | HVAC | ||
| Div 26 | Electrical | ||
| Div 27 | Communications | ||
| Div 28 | Electronic Safety & Security | ||
| Div 31 | Earthwork | ||
| Div 32 | Exterior Improvements | ||
| Div 33 | Utilities | ||
| Subtotal | $0.00 | ||
| Contingency (5%) | $0.00 | ||
| Section E Total: | $0.00 |
| Section F - Overall Maintenance Storage Building | |||
| MS | Maintenance Storage Building | Total | |
| Div 1 | Project Requirements | ||
| Div 2 | Site Conditions | ||
| Div 3 | Concrete | ||
| Div 4 | Masonry | ||
| Div 5 | Metals | ||
| Div 6 | Woods & Plastics | ||
| Div 7 | Thermal & Moisture Protection | ||
| Div 8 | Opening | ||
| Div 9 | Finishes | ||
| Div 10 | Architectural Specialties | ||
| Div 11 | Equipment | ||
| Div 12 | Furnishings | ||
| Div 13 | Special Construction | ||
| Div 14 | Conveying Systems | ||
| Div 21 | Fire Protection | ||
| Div 22 | Plumbing | ||
| Div 23 | HVAC | ||
| Div 26 | Electrical | ||
| Div 27 | Communications | ||
| Div 28 | Electronic Safety & Security | ||
| Div 31 | Earthwork | ||
| Div 32 | Exterior Improvements | ||
| Div 33 | Utilities | ||
| Subtotal | $0.00 | ||
| Contingency (5%) | $0.00 | ||
| Section F Total: | $0.00 |
| Section G - Overall Site Work | ||||||
| SW | Site Work | |||||
| 1 | Mill Bldg - Entry Plaza and Amphitheater | Quantity | UOM | Unit Price | Total | |
| Specialty Paving | $0.00 | |||||
| Concrete Pavement | $0.00 | |||||
| Concrete Form Work | $0.00 | |||||
| Pergola | $0.00 | |||||
| Handrail | $0.00 | |||||
| Plantings | $0.00 | |||||
| Site Furnishings | $0.00 | |||||
| Mill Bldg - Entry Plaza and Amphitheater Total | $0.00 | |||||
| 2 | Mill Bldg - South Garden and Outdoor Nature Center | Quantity | UOM | Unit Price | Total | |
| Specialty Paving | $0.00 | |||||
| Concrete Pavement | $0.00 | |||||
| Concrete Form Work | $0.00 | |||||
| Masonry Piers and Walls | $0.00 | |||||
| Guardrail | $0.00 | |||||
| Stonework | $0.00 | |||||
| Plantings | $0.00 | |||||
| Site Furnishings | $0.00 | |||||
| Mill Bldg - South Garden and Outdoor Nature Center Total | $0.00 | |||||
| 3 | Mill Bldg East Garden | Quantity | UOM | Unit Price | Total | |
| Concrete Form Work | $0.00 | |||||
| Guardrail | $0.00 | |||||
| Stonework | $0.00 | |||||
| Plantings | $0.00 | |||||
| Rain Garden | $0.00 | |||||
| Mill Bldg East Garden Total | $0.00 | |||||
| 4 | Mill Bldg South Parking Lot (Along Hines) | Quantity | UOM | Unit Price | Total | |
| Concrete Curbs | $0.00 | |||||
| Concrete Pavement | $0.00 | |||||
| Asphalt Pavement | $0.00 | |||||
| Plantings | $0.00 | |||||
| Drainage Basin | $0.00 | |||||
| Masonry Sign Walls | $0.00 | |||||
| Mill Bldg South Parking Lot (Along Hines) Total | $0.00 | |||||
| 5 | Mill Bldg North Parking Lot (Ann Arbor Trail) | Quantity | UOM | Unit Price | Total | |
| Concrete Curbs | $0.00 | |||||
| Concrete Pavement | $0.00 | |||||
| Asphalt Pavement | $0.00 | |||||
| Site Furnishings | $0.00 | |||||
| Dumpster Enclosure | $0.00 | |||||
| Mill Bldg North Parking Lot (Ann Arbor Trail) Total | $0.00 | |||||
| 6 | Miller House | Quantity | UOM | Unit Price | Total | |
| Concrete Pavement | $0.00 | |||||
| Concrete Form Work | $0.00 | |||||
| Pergola | $0.00 | |||||
| Handrails and Guardrails | $0.00 | |||||
| Plantings | $0.00 | |||||
| Site Furnishings | $0.00 | |||||
| Miller House Total | $0.00 | |||||
| 7 | Miller House Parking Lot and Drive | Quantity | UOM | Unit Price | Total | |
| Specialty Paving | $0.00 | |||||
| Concrete Curbs | $0.00 | |||||
| Concrete Pavement | $0.00 | |||||
| Asphalt Pavement | $0.00 | |||||
| Miller House Parking Lot and Drive Total | $0.00 | |||||
| 8 | Red Barn and Recreational Storge Building - Plaza | Quantity | UOM | Unit Price | Total | |
| Concrete Pavement | $0.00 | |||||
| Concrete Form Work | $0.00 | |||||
| Plantings | $0.00 | |||||
| Red Barn and Recreational Storge Building - Plaza Total | $0.00 | |||||
| 9 | Maintenance Yard | Quantity | UOM | Unit Price | Total | |
| Concrete Curbs | $0.00 | |||||
| Concrete Pavement | $0.00 | |||||
| Asphalt Pavement | $0.00 | |||||
| Fence and Gate | $0.00 | |||||
| Dumpster Enclosure | $0.00 | |||||
| Storage Bin | $0.00 | |||||
| Retaining Wall | $0.00 | |||||
| Plantings | $0.00 | |||||
| Maintenance Yard Total | $0.00 | |||||
| 10 | Parking Lot (Ellsworth) | Quantity | UOM | Unit Price | Total | |
| Concrete Curbs | $0.00 | |||||
| Concrete Pavement | $0.00 | |||||
| Asphalt Pavement | $0.00 | |||||
| Drainage Basin | $0.00 | |||||
| Parking Lot (Ellsworth) Total | $0.00 | |||||
| 11 | Overall Site Work | Quantity | UOM | Unit Price | Total | |
| Demolition | $0.00 | |||||
| Earthwork | $0.00 | |||||
| Underground Utilities | $0.00 | |||||
| Remaining Concrete Pavement | $0.00 | |||||
| Remaining Drainage Basins | $0.00 | |||||
| Overflow Parking | $0.00 | |||||
| Remaining Plantings | $0.00 | |||||
| Trees | $0.00 | |||||
| Sidewalk Snowmelt | $0.00 | |||||
| Overall Site Work Total | $0.00 | |||||
| Site Work Contingency (15%) | $0.00 | |||||
| Section G Subtotal: | $0.00 |
Sections Total (A + B + C + D + E + F + G) $0.00
| Miscellaneous | Amount |
| General Conditions | $0.00 |
| Insurance | $0.00 |
| Fees | $0.00 |
| Profit & OH | $0.00 |
| Total Miscellaneous | $0.00 |
| Allowances | Amount |
| Site security during construction (General) | $100,000.00 |
| Winter conditions (General) | $100,000.00 |
| Hazardous material abatement (General) | $50,000.00 |
| Permits (General) | $50,000.00 |
| Surveys (General) | $30,000.00 |
| Testing (General) | $50,000.00 |
| Exhibits (NM) | $500,000.00 |
| Furniture- FFE (General) | $250,000.00 |
| Appliances (General) | $10,000.00 |
| Kitchen Equipment (MH) | $100,000.00 |
| Café/Gift Shop Millwork & Kitchen equipment (MH) | $25,000.00 |
| Low Voltage/Security Cameras (General) | $50,000.00 |
| Generator room equipment restoration (NM) | $25,000.00 |
| Fountain (MH) | $50,000.00 |
| Fire Feature (MH) | $5,000.00 |
| Total Allowances | $1,395,000.00 |
Total Project Cost $1,395,000.00
The undersigned Bidder having carefully examined the procurement and contracting requirements of the contract documents, including plans and specifications, and any and all addenda, having visited the sites, and being familiar with all conditions and requirements of the Work, hereby agrees to furnish all material, labor, equipment and services necessary to fully complete the construction of the Project, meeting the intent of the drawings and specifications for the stipulated sum above.
The Bidder hereby agrees to have the work completed within the following schedule:
1. Substantial completion within 700 calendar days of receipt of the Notice to Proceed.
2. Completion within 30 days of Substantial Completion.
3. Two (2) year landscape establishment period.
| Additional Price Information |
| Price Clause: Price is Firm |
| Terms: Discount of % for payment of invoice within 30 days from date of delivery and acceptance of materials or services and vendor’s invoice. |
| County Based Enterprise (and Other) Certificates: Attach Bidder’s County Based Enterprise certificate and/or other program certificates if one exists; otherwise it will not be considered during price evaluation. |
File details come from the government source that posted it. Updated .