S-10-0428_Section_B_-_M_.doc
DOC document 312 KB Posted
- Attached to
- RECOVERY - CARIBOU-CALLIHAN ROAD DECOMMISSIONING
- Solicitation number
- AG-82B1-S-10-0428
About this file
SECTIONS B THROUGH M
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S-10-0428 Standard Specifications.docx | DOCX document | |
| A-004 S-10-0428.pdf | ||
| A-003 S-10-0428.pdf | ||
| FP-03 A-003 S-10-0428.doc | DOC document | |
| A-002 S-10-0428.pdf | ||
| Attachment to Amendment A -002 S-10-0428.docx | DOCX document | |
| A-001 S-10-0428.pdf | ||
| A-001 - Part 2. S-10-0428 pdf.pdf | ||
| A-001 S-10-0428 Attachment.docx | DOCX document | |
| Plans - Part 4.pdf | ||
| MT SERVICE CONTRACT WAGES.htm | HTM file | |
| Plans - Part 2.pdf | ||
| sf-1447.pdf | ||
| Plans - Part 3.pdf | ||
| Plans - Part 1.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AG-82B1-S-10-0428
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS
CARIBOU-CALLAHAN ROAD DECOMMISSIONING
Kootenai National Forest Three Rivers Ranger District Lincoln County, MT
B-1 - SCHEDULE OF ITEMS.
| Item No. |
| Item Description |
| Method of Measure- ment |
| Pay Unit |
| Quantity |
| Unit Price |
| Total Price |
Bid Item 1: Caribou Road Decommissioning
| 15101 |
| Mobilization |
| LSQ |
| LS |
| All |
| 21159 |
| Roadway Clearing |
| CQ |
| MI |
| 5.23 |
| 21160 |
| Roadway Clearing |
| CQ |
| LF |
| 26,515 |
| 21161 |
| Stream Channel Excavation - Category I |
| AQ |
| EA |
| 5 |
| 21162 |
| Stream Channel Excavation - Category II |
| AQ |
| EA |
| 5 |
| 21166 |
| Partial Road Recontour, 3:1 Outslope |
| AQ |
| LF |
| 940 |
| 21168 |
| Road Scarification |
| AQ |
| LF |
| 6,035 |
| 21169 |
| Ditch Relief Culvert Removal |
| AQ |
| EA |
| 18 |
| 21170 |
| Cross Channel |
| AQ |
| EA |
| 15 |
| 21171 |
| Ditch Drainage Waterbar |
| AQ |
| EA |
| 47 |
| 21172 |
| Surface Waterbar |
| AQ |
| EA |
| 36 |
| 21174 |
| Double Earth Barrier |
| AQ |
| EA |
| 3 |
| 21175 |
| Grade Control Structure |
| AQ |
| EA |
| 24 |
| 62201 |
| Hydraulic Excavator with Thumb |
| AQ |
| HR |
| 57 |
TOTAL - Bid Item 1
XXXXXXX
| Item No. |
| Item Description |
| Method of Measure- ment |
| Pay Unit |
| Quantity |
| Unit Price |
| Total Price |
Bid Item 2: Callahan Road Decommissioning
| 15101 |
| Mobilization |
| LSQ |
| LS |
| All |
| 21160 |
| Roadway Clearing |
| CQ |
| LF |
| 45,970 |
| 21161 |
| Stream Channel Excavation - Category I |
| AQ |
| EA |
| 2 |
| 21162 |
| Stream Channel Excavation - Category II |
| AQ |
| EA |
| 3 |
| 21163 |
| Stream Channel Excavation - Category III |
| AQ |
| EA |
| 5 |
| 21164 |
| Stream Channel Excavation - Category IV |
| AQ |
| EA |
| 2 |
| 21166 |
| Partial Road Recontour, 3:1 Outslope |
| AQ |
| LF |
| 2,665 |
| 21168 |
| Road Scarification |
| AQ |
| LF |
| 34,945 |
| 21169 |
| Ditch Relief Culvert Removal |
| AQ |
| EA |
| 10 |
| 21170 |
| Cross Channel |
| AQ |
| EA |
| 5 |
| 21171 |
| Ditch Drainage Waterbar |
| AQ |
| EA |
| 54 |
| 21172 |
| Surface Waterbar |
| AQ |
| EA |
| 35 |
| 21174 |
| Double Earth Barrier |
| AQ |
| EA |
| 2 |
| 21175 |
| Grade Control Structure |
| AQ |
| EA |
| 29 |
| 25170 |
| 6" Rock, Produce and Deliver |
| CQ |
| CY |
| 8 |
| 25170 |
| 12" Rock, Produce and Deliver |
| CQ |
| CY |
| 41 |
| 25170 |
| 18" Rock, Produce and Deliver |
| CQ |
| CY |
| 45 |
| 25170 |
| 30" Rock, Commercial Source and Delivery |
| CQ |
| CY |
| 20 |
| 62201 |
| Hydraulic Excavator with Thumb |
| AQ |
| HR |
| 92 |
TOTAL: Bid Item 2
XXXXXXX
Abbreviations: AQ - Actual Quantity; LS – Lump Sum; HR – Hour; EA – Each;
CY – Cubic Yard; LF – Lineal Foot; MI – Mile; CQ – Contract Quantity; LSQ – Lump Sum Quantity
B – 2 EVALUATION OF OFFERS/BASIS OF AWARD, AND AWARD:
Offers will be evaluated based on the quantities indicated. Actual quantities (AQ) will be tabulated during contract performance and changes in quantities will be compensated via modification to the contract.
Offers may be made on one or both bid items. Offers on each bid item will be evaluated separately. As a result one or two contracts may be awarded. Please round to the nearest dollar.
SECTION C—DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C-1 PROJECT DESCRIPTION AND LOCATION
a) Description of Work. Work includes clearing roads of brush and logs for equipment access, removing stream and ditch relief culverts, reconstructing stream channels, constructing cross drains and waterbars, recontouring road fills, scarifying roadbeds, spreading slash on decommissioned surfaces, and foot or ATV path excavation along the roadway.
This contract is composed of two bid items. Work associated with each item is described as follows:
1) Item 1: Caribou Road Decommissioning. Decommissioning of 5.13 miles of road plus clearing of an additional 5.23 miles of road for access in the Caribou Creek watershed.
2) Item 2: Callahan Road Decommissioning. Decommissioning of 8.71 miles of road in the Callahan Creek watershed.
b) Project Location. Both bid items are located on the Three Rivers Ranger District, Kootenai National Forest.
1) Item 1: Caribou Road Decommissioning. This work is located approximately 60 miles north of Troy, Montana in Lincoln County. Follow US Highway 2 north from Troy 10 miles to the junction with State Highway 508 (Yaak Highway). Follow the Yaak Highway (becomes County Road 92) approximately 48.3 miles to National Forest System (NFS) Road 5800, and 49.6 miles NFS to Road 5819. See project location map in the plans.
2) Item 2: Callahan Road Decommissioning. This work is located is located approximately 12 miles southwest of Troy. Follow NFS Road 427 (Callahan Creek Road) west from Troy approximately 7 miles to junction with NFS Road 414 (South Fork Callahan Road). Follow NFS Road 414 southwest approximately 5 miles to junction with NFS Roads 4541 and 4530. Decommissioning work on NSF Road 4541 begins approximately 0.6 miles beyond the junction. Follow NFS Road 4530 northwest from the junction approximately 2 miles to junction with NFS Road 4521. See project location map in the plans.
c) Pre-Bid Conference and Tour. A pre-bid conference/tour will not be conducted. However, prospective offerors are encouraged to visit the project site prior to submitting a bid. For questions, call Steve Tralles at 406-295-7415 or Kris Newgard at 406-295-7416.
d) Start Work. It is estimated that work will begin approximately July 12, 2010.
e) Period of Performance. The Contractor will be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) notify the Contracting Officer of intent to begin work at least 48 hours in advance of the anticipated start date, (c) prosecute the work diligently, and (d) complete all bid items by September 30, 2011.
In order to protect water quality and fisheries, work is limited to the following periods:
1) Item 1: Caribou Road Decommissioning. Complete work between July 15 and September 30.*
2) Item 2: Callahan Road Decommissioning. Complete work between July 15 and August 31.* *Work such as road clearing that poses no risk of sediment contribution to streams may occur outside this period with approval from the Contracting Officer’s Representative (COR).
NOTE: Work performed under Pay Item 62201-Rental Equipment must be performed between 7 AM and 5 PM Monday through Saturday, unless otherwise mutually agreed, so that the Contracting Officer’s Reresentative, or his/her appointee, can be present to direct the work.
C-2 GENERAL SPECIFICATIONS
a) Access. Project work on all roads except NSFR 4521 is located behind locked gates that restrict public access. The Contractor will be provided a lock and key for use during the contract which must be returned promptly at the end of the contract. Gates shall be kept closed and locked at all times. If the Government decides to use a temporary road barricade instead of a gate for closure, the barricade will be placed in the middle of the road at the location designated by the Contracting Officer. Only activities authorized under this contract are permitted. The Contractor is not allowed to use a vehicle to hunt or cut firewood on roads that are closed to the public.
b) Closure for Season. If work begun on any road is not completed in that season, the road will be winterized with shallow waterbars and the entrance blocked by an earth barrier or rocks as designated by the Contracting Officer’s Representative.
c) Traffic Control. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted to and approved by the Contracting Officer. Construction signing for traffic control will conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be place in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Expenses related to signing are incidental to other items of work listed in the Schedule of Items.
d) Pollution and Erosion Control. During all operations under this contract, the Contractor shall exercise reasonable measures to prevent or minimize soil erosion and pollution of water and other resources. All refuse, including garbage, rubbish, and solid or liquid wastes, from the Contractor's operations, including camps, parking areas, and equipment maintenance areas shall be stored, collected, and disposed of in a sanitary and nuisance-free manner.
1) Equipment fueling areas will be situated at least 150 feet from stream channels or other water bodies. Stationary fuel tanks will not be allowed. Contractor shall have petroleum absorbent pads on site at all times during the construction period.
2) During all of the work, the Contractor shall make every reasonable effort to direct surface runoff water to stabilized waterways and to keep the drainage systems functioning effectively to minimize soil erosion and water pollution.
e) Permitting. The Government is responsible for securing any necessary water quality permits required for the project. The Contractor will be provided copies of all permit requirements at the prework meeting and is responsible for complying with the terms of the permits in the prosecution of the work.
f) Camping. Contractor will present any anticipated camping requests at the prework meeting. The Contractor will be required to obtain a Commercial Camping Permit (Form FS-R1-2460-10). Camping will be allowed only at locations approved by the District Ranger. Camping is not allowed at designated recreation sites. The Contractor will abide by all conditions of the permit as well as any rules applicable to the general public. A camp includes any location occupied by the Contractor or Contractor’s agents for the purpose of overnight occupancy. This includes any tent sites, use of camp trailers, and occupancy of campsites or campgrounds that are open to the public.
SECTION D PACKAGING AND MARKING
INTENTIONALLY BLANK
SECTION E - INSPECTION AND ACCEPTANCE
E – 1 - FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (Feb 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): http://www.arnet.gov/far
FAR 52.246-4 Inspection of Services
SECTION F – DELIVERIES OR PERFORMANCE
FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
F – 1 The contractor shall commence work under this contract within 10 calendar days after receiving the Notice to Proceed and complete the work no later than September 30, 2011.
F -2 Contract time will start (1) on the date specified on the Notice to Proceed, if the notice is hand-delivered; Or (2) on the third-day after the post office has issued a Notice of Certified Mail to the Contractor; Or (3) when flexible netting maintenance and/or other work commences, whichever is sooner. Failure of the Contractor to pick-up Certified Mail will not be considered excusable.
F.2.2. Unfavorable Conditions. It is estimated that adverse weather and/or road conditions may prevent access to the work sites or performance to specification. When such conditions make work impracticable, or other conditions create extreme conditions that are unsafe for contract work, and with written request by the Contractor, the Contracting Officer may suspend work with no charge against contract time. When conditions are again favorable, the Contracting Officer will issue a verbal resume work order and confirm that order in writing. The count of contract time will resume on the day indicated by the Contracting Officer. If the Contractor cannot be reached at the phone number provided or the Contractor fails to contact the Contracting Officer a written Resume Work Order will be mailed and count of contract time will resume on the date specified in the order.
F – 3 - FAR 52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984). At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor.
SECTION G - CONTRACT ADMINISTRATION DATA
G-1 - INCIDENTAL PAYMENT ITEMS Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.
G-2 - FINAL PAYMENT The amount of the final payment will be calculated as described above and approved for payment after--
(a) Completion and acceptance of all work in each Item;
(b) Presentation of a properly executed invoice; and
Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor's claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of 1940 (31 U.S.C. 3727 and 41 U.S.C. 15).
SECTION H - SPECIAL CONTRACT REQUIREMENTS
H – 1 - KEY PERSONNEL
H.1.1. The Contractor shall assign to this contract the key personnel identified in their technical proposal (experience questionnaire) and that list may include the following:
· CONTRACTOR REPRESENTATIVE
· FOREMAN/FOREWOMAN
· INSPECTOR
H.1.2. The Contractor shall make no substitutions of key personnel without notifying the Contracting Officer within a reasonable timeframe and in advance, and shall submit justification (including proposed substitutions) in sufficient detail to permit evaluation of the impact on the contract. Proposed substitutes should have comparable qualifications to those of the persons being replaced.
H.1.3. The Contractor shall make no diversion of personnel without the written consent of the Contracting Officer.
H.1.4. The contract will be modified to reflect any approved changes of key personnel.
H – 2 - FIRE CONTROL
H.2.1. Contractor's Responsibility for Contractor-Caused Fires. The Contractor, whether or not directed by the Forest Service, shall immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by Contractor's employees, whether set directly or indirectly as a result of Contractor operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or resulting from contract operations.
H.2.2. Other Fires. For the purpose of fighting forest fires on or in the vicinity of the project which are not caused by the Contractor or his employees, the Contractor when requested by the Contracting Officer shall place his employees and equipment temporarily at the disposal of the Forest Service. Payment for such services will be made by the Government at not less than the current rate for fire-fighting services established by the Forest Service in the area concerned.
H.2.3. Any employees and equipment furnished will be relieved from fire fighting as soon as the Forest Service finds that it is practicable to employ other labor and equipment adequate for the protection of the area.
H.2.4. An equitable adjustment in contract time may be made for this period.
H.2.5. Fire Protection Requirements - Fire Plan. At all times during closed fire season period, as specified by State law, the Contractor shall comply with each of the following provisions to the extent applicable to his operation under the contract.
H.2.5.1. Fire Tools. The Contractor will provide for each employee in the contract area at least one approved handtool of a type appropriate in the contract area, such as shovel, pulaski, or ax. Tools required and furnished under H.2.5.2. and H.2.5.4. below, shall count toward fulfillment of the above requirement. Where additional tools, beyond those required below, are to be provided, the Contractor shall seal such tools in one or more boxes painted red and marked "Tools for Fire Only." All tools required herein shall be kept sharp and in good serviceable condition and maintained at locations to be designated by the Forest Service.
H.2.5.2. Fire Extinguishers and Tools on Mobile or Stationary Equipment. Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:
a. One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with 4 BC or higher rating.
b. One - shovel, round point #0 lady or equal.
c. One - ax, 2 pounds or over, 26-inch minimum length, or one pulaski.
d. One - water container (at least 1-gallon capacity), not required with stationary equipment.
H.2.5.3. Spark Arresters. Each internal combustion engine shall be provided with a spark arrester or spark arresting device approved by the Forest Service. Exceptions where the Forest Service may approve mufflers, or other equipment in lieu of spark arresters qualified and rated under Forest Service Standard 5100-1a, are: (a) small multiposition engines, such as chain saws, shall meet Society of Automotive Engineers J335b standards; (b) passenger-carrying vehicles and light trucks may have baffle-type mufflers with tail pipe; (c) heavy-duty trucks may have a vertical stack exhaust system and muffler, provided the exhaust stack extends above the cab of the vehicle. An exhaust-driven turbocharger is considered to be a satisfactory spark arrester. Internal combustion engine exhaust systems, arresters, and other devices must be properly installed and maintained.
H.2.5.4. Powersaws. For each powersaw used in connection with this contract, the following will be provided:
a. One - shovel, round point #0 lady or equal. Shovel must be immediately available for use.
b. One - Fire extinguisher, containing not less than 8 ounces of extinguisher fluid, or a dry chemical powder-type of not less than 1-pound capacity. The extinguisher must be immediately accessible to the saw operator at all times.
H.2.5.4.1. Any fueling or refueling of a powersaw shall only be done in an area which has first been cleared or is free of all material capable of carrying fire; powersaw shall be moved at least 10 feet from place of fueling before starting.
H.2.5.5. Blasting. Fuse or prima cord shall not be used unless authorized in writing by the COR with special precautions stated.
H.2.5.6. Smoking. Smoking shall not be permitted within the contract area except on surfaced or dirt roads, at landings, within closed vehicles, in camps, or at other posted places, and shall never be allowed while working or traveling on foot.
H.2.5.7. Storage of Petroleum and Other Highly Flammable Products. Gasoline, oil, grease, or other highly flammable material will be stored either in a separate building used exclusively for such storage, or at a site where all combustible debris and vegetation is cleared away within a radius of 25 feet. Fire extinguishers and/or sand barrels may be required at such locations specified by the Forest Service when unusually hazardous conditions exist.
H.2.5.8. Debris Burning and Warming Fires. Burning permits will be required for all debris burning fires. Lunch and warming fires may be allowed in fireproofed areas during periods of low fire danger if and as specified in the fire plan. Such fires must not be left burning unattended.
H.2.5.9. Precautions for Stoves. Stovepipes on all temporary buildings, trailers, and tents using wood burning stoves, will be equipped with roof jacks and serviceable spark arresters of mesh with openings no larger than 5/8 inch.
All stovepipes, inside and out, will not be closer than 2 feet from any wood or other flammable material or 1 foot if the combustible material is protected by a metal or asbestos shield.
H.2.5.10. Welding. Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all material capable of carrying fire. Flammable debris and vegetation must be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon standard backpack water container, (filled) with handpump attached, shall be immediately available for use in the event of a fire start.
H.2.5.11. Fire Plan. Prior to initiating work on the contract area, during the closed fire season period, a fire prevention and suppression plan will usually be prepared. The Contractor and the Forest Service will jointly prepare this plan. Such plan shall include a detailed list of men and equipment at the Contractor's disposal for implementing the plan. The fire plan shall also specify additional measures and/or special requirements, such as Hoot Owl restrictions, necessary during periods of critical fire weather conditions.
H.2.5.11.1 When Hoot Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:
a. All high fire risk operations could be terminated at 1300 local time.
b. All burning could be stopped, including debris burning fires.
c. Patrolman may be required for a period of 2 hours after high fire risk operations and 1 hour after end of work shift. The Contractor shall provide the patrolman unless the contract is for equipment rental, in which case the Government will provide the patrolman.
H.2.5.12. Pump and Trailer. Not required.
H – 3 - PREWORK CONFERENCE
Prior to commencement of work, the Contractor shall attend a meeting to discuss the contract terms, work performance requirements, and safety. Also at this meeting such items as work progress schedule, slash treatment, camping/worksite plan, communications, and fire prevention plans shall be finalized in writing.
H – 4 - CAMPING AND WORKSITE CONDITIONS
H.4.1. Camping and Worksite Plan shall be consistent with requirements set forth in this section, Section I, and the camping permit which is required. The Contractor shall provide a general plan with the technical proposal, and shall provide a more specific plan based on items awarded, prior to start work.
H.4.2. The Contractor shall be aware of and abide by the rules of the Kootenai National Forest applicable to forest visitors.
H.4.3. The Contractor shall obtain a camping permit from the Fortine Ranger District prior to camping on Forest Service land. Final payment shall be withheld until the authorized camping area has been cleaned up to the requirements of the Camping Permit.
If the Contractor does not obtain a camping permit but requires his/her employees to obtain the camping permit, the Contractor remains responsible for campsite clean up and his/her employees conduct while camping on National Forest land.
H.4.4. Contractor Information: The Contractor shall abide by the OSHA’s Field Sanitation Standard Fact Sheet No. OSHA 92-25, which applies to agricultural establishments hiring 11 or more workers for hand labor.
H – 5 - CAMPING PROVISIONS FOR LABOR INTENSIVE CONTRACTS
The following provisions apply to all camping on National Forest lands during performance of this contract:
1. These provisions are in addition to those contained in, or provided for, in the clause titled “Use of Premises”, in this contract.
2. Every structure used as shelter shall provide protection from the elements. Where heat adequate for weather conditions is not provided, other arrangements should be made to protect workers from the cold. Firewood may be cut only after obtaining a District Firewood Permit.
3. The campsite will not encroach beyond the boundaries designated by the Forest Service. The campsite shall be located so as to minimize impacts on streams, lakes, and other bodies of water. No camping shall be permitted within developed recreation sites or along primary recreation roads.
4. The campsite shall have a clean appearance at all times.
5. Upon abandonment of any campsite, or termination, revocation, or cancellation of camping privileges, the contractor shall remove, within 10 calendar days, all structures and improvements except those owned by the United States, and shall restore the site, unless otherwise agreed upon in writing or in the camping permit. If the contractor fails to remove all structures or improvements within the 10 calendar days, they shall become the property of the United States, but that will not relieve the contractor of liability for the cost of their removal and restoration of the site.
6. Unless otherwise designated by the Contracting Officer, the use of this area is not exclusive, and may be granted to other Permittees, contractors, or recreating public. Disorderly conduct is not permitted.
7. Damaging or removing any natural feature or other property of the Forest Service is prohibited.
8. Servicing of equipment in the campsite is not permitted, unless the campsite is within the project area.
9. Sanitary facilities shall be provided for storing food. Ice chests or coolers, with ice supply made from potable water and replenished as necessary, shall be provided and sufficient for the storage of perishable food items.
10. An adequate and convenient potable water supply shall be provided in each camp for drinking and cooking purposes.
11. Toilet facilities adequate for the capacity of the camp shall be provided and supplied with adequate toilet paper. Such facilities shall be serviced and maintained in a sanitary condition.
12. Garbage shall be collected, stored, and disposed of in such a manner as to prevent scattering by the wind, minimize attraction of flies, and discourage access by rodants.
13. Basic first aid supplies shall be maintained, available and under the charge of a person trained to administer first aid. The supplies shall include:
a. Gauze pads (at least 4x4 inches)
b. Two large gauze pads (at least 8x10 inches)
c. Box adhesive bandages (band-aids)
d. One package of gauze roller bandage at least 2 inches wide
e. Two triangular bandages
f. Scissors
g. At least one blanket
h. Tweezers
i. Adhesive tape
j. Latex gloves
k. Resuscitation device such as resuscitation bag, airway, or pocket mask
14. Any washing of laundry shall be done in such a way as to provide for washing and rinsing without polluting lakes, streams, or other flowing water.
15. Waste water must be disposed of away from living and eating areas and in a fashion that minimizes pollution to lakes, streams, and other flowing water.
16. The contractor shall take all reasonable precautions to prevent and suppress forest fires. No material shall be disposed of by burning in open fires during the closed season established by law or regulation without the written permission from the Forest Service.
17. The contractor shall comply with the following fire regulations during fire season:
a. A shovel, axe or pulaski, 10 quart pail which is full of water for immediate use and a fire extinguisher with an Underwriters Laboratory (UL) rating of at least 1:A 10:BC is required during the fire season.
b. All fire rings or outside fireplaces will be approved by the Forest Service representative. The area will be cleared down to mineral soil for a distance of 1 foot outside of the ring or fireplace and it will not have any overhanging material. Fire rings will be dismantled and material disposed prior to leaving the site.
c. All generators and other internal combustion engines will be equipped with USFS approved spark arrestors and/or factory designed muffler and exhaust system in good working order. They will be located in a cleared area with the same requirements as in (b).
d. All fuel will be stored in UL approved flammable storage containers and be located at least 50 feet from any open flame or other source of ignition.
18. Any violation of these conditions constitutes a breach of contract, and may result in revocation of camping approval.
19. The Forest Service reserves the right to terminate a camping permit at any time.
H - 6 - EMPLOYMENT OF ELIGIBLE WORKERS (FSAR 4G52.222-701) (DEC 1999)
Section 274A of the Immigration and Nationality Act (8 USC 1324a) makes it unlawful for an employer to hire unauthorized aliens. The Immigration and Naturalization Service (INS) has established the Form I-9, Employment Eligibility Verification Form, as the document to be used for employment eligibility verification (8 CFR 274a).
The Contractor is required to (1) have all employees complete and sign the I-9 Form to certify that they are eligible for employment; (2) examine documents presented by the employee and ensure the documents appear to be genuine and related to the individual; (3) record information about the documents on the form, and complete the certification portion of the form; (4) retain the form for 3 years, or 1 year past the end of employment of the individual, whichever is longer.
It is illegal to discriminate against any individual (other than a citizen of another country who is not authorized to work in the United States) in hiring, discharging, or recruiting because of that individual's national origin or citizenship status.
Compliance with Section 274A of the Immigration and Nationality Act (8 U.S.C. 1324a) is a material condition of the contract. If the Contractor employs unauthorized workers during contract performance in violation of Section 274A, the Government may terminate the contract, in addition to other remedies or penalties prescribed by law.
For further information on the requirements of the Act, Contractors should contact the Employer and Labor Relations Officer of their local INS office.
H – 7 - LABOR STANDARDS FOR CONTRACTS INVOLVING MIGRANT AND SEASONAL AGRICULTURAL WORKERS (FSAR 4G52.222-702) (DEC 1999)
(a) General. This contract is subject to the Migrant and Seasonal Agricultural Workers Protection Act (MSPA) (29 U.S.C 1801-1872) and to Department of Labor regulations implementing MSPA (29 CFR 500). The purpose of MSPA is to eliminate activities that are detrimental to migrant and seasonal agricultural workers, to require registration of farm labor Contractors, and to ensure necessary protections for the workers. In addition to traditional farm labor activities, the Act applies to predominately manual forestry work including, but not limited to tree planting, release, pre-commercial thinning, site preparation, and wildland fire fighting.
(b) Definitions "Migrant Agricultural Worker" and "Seasonal Agricultural Worker,” as used in this clause, mean individuals employed in agricultural (including forestry) work on a seasonal or temporary basis. A worker who moves from one seasonal activity to another is employed on a seasonal basis even though the worker may continue to be employed during a major portion of the year. Migrant workers are required to be absent overnight from their permanent place of residence. Seasonal workers are not required to be absent overnight from their permanent place of residence. Members of the Contractor's immediate family are not considered to be either migrant or seasonal workers. "Immediate family" includes only (1) spouse; (2) children, stepchildren, or foster children; (3) parents, stepparents, or foster parents; and (4) brothers and sisters.
"Farm Labor Contractor," as used in this clause, means an individual who, for any money or other valuable consideration, paid or promised to be paid, performs any recruiting, soliciting, hiring, employing, furnishing, or transporting of any migrant or seasonal agricultural worker.
(c) Registration Requirement. Any Contractor who provides or hires migrant or seasonal workers to perform agricultural or manual forestry work shall first obtain a Certificate of Registration from the Department of Labor or an authorized State agency. The Contractor shall carry the Certificate at all times while engaged in contract performance, and shall display it upon request. Any of the Contractor's employees who perform any one or more of the activities defined for a "Farm Labor Contractor" in paragraph (b) must have their own Farm Labor Contractor Employee Certificate.
(d) Worker Protections. The Contractor shall comply with the following protections and standards related to wage disclosure, record keeping, vehicle safety, and housing:
(1) The Contractor shall display and maintain at the place of employment the MSPA poster provided by the Department of Labor.
(2) Wage and Payroll Standards
(i) The Contractor shall disclose in writing to each worker in a language common to the worker the full terms of their employment, including workers compensation information, at the time they are recruited or hired. The Department of Labor provides an optional Form WH-516 for Contractor's use in disclosure.
(ii) The Contractor must keep the following payroll records for each employee: name, address, social security number, basis for wages (that is, per hour, per tree, per acre), number of units earned if paid on a per unit basis, hours worked, total pay, withholdings and purpose for each, and net pay. Payroll records shall be retained for 3 years.
(iii) Payments must be made no less frequently than every 2 weeks or semi-monthly. At the time of each payment, the Contractor shall provide to the employee a written itemization of the information listed in paragraph (ii) and shall include the employer's tax identification number.
(iv) If paid on a piece rate basis, the employee's wage must be at least equivalent to the required hourly wage for the hours worked, including overtime differential for time in excess of 40 hours per week.
(3) Motor Vehicle Safety
(i) The Contractor must be registered to transport employees, unless employees provide their own transportation or carpool by their own arrangement in one of their own vehicles. The authorization to transport employees must appear on the Contractor's certificate. If the Contractor directs or requests employees to carpool, the registration requirement is still applicable. Any driver who transports workers for a fee or at the direction of the Contractor must be registered as a farm labor Contractor or a farm labor Contractor employee.
(ii) Any vehicle under the ownership or control of the Contractor shall comply with safety standards applicable to that vehicle. Generally, passenger vehicles or station wagons must comply with Department of Labor regulations at 29 CFR 500.104. Vehicles other than passenger vehicles or station wagons which are driven more than 75 miles must comply with Department of Transportation Regulations at 29 CFR 500.105. All drivers must have a current, valid State driver’s license.
(iii) Each vehicle under the ownership or control of the Contractor that is used to transport any migrant or seasonal agricultural worker shall be covered by vehicle insurance of $100,000 per seat (maximum $5,000,000). A workers compensation policy that covers the workers while being transported plus an additional property damage policy for $50,000 for loss or damage in any one accident to the property of others may be substituted for the vehicle insurance requirement.
(4) Housing
(i) The Contractor shall house workers only in a commercial establishment or a facility that has been certified by a health authority or other appropriate agency. The Contractor must post the certificate of occupancy at the housing site.
(ii) The authorization to furnish housing, other than commercial lodging, must appear on the Contractor's certificate.
(e) For further information on the requirements of the Act, Contractors should contact their local Wage and Hour Division of the Department of Labor.
H - 8 - FSAR 4G52.222-703 Migrant and Seasonal Agricultural Worker Protection Act Registration (DEC 1999)
The Migrant and Seasonal Agricultural Worker Protection Act (MSPA) (29 U.S.C. 1801-1872) and implementing regulations issued by the Department of Labor (29 CFR 500), require any employer who hires or anticipates hiring employees subject to MSPA to obtain an MSPA registration number.
If the contractor employs or anticipates hiring employees subject to MSPA, the contractor shall provide a valid U.S. Department of Labor MSPA Registration Number to the Contracting Officer within 10 days after notification of award of the contract.
The Government may demand that the contractor display MSPA registration at any time during contract performance if it appears that the contractor is employing workers subject to MSPA. On demand, the contractor shall display its MSPA registration or state why it is exempt from MSPA.
Compliance with MSPA is a material condition of the contract. If the contractor fails to provide a valid MSPA number in accordance with this clause, or falsely states that it is exempt from the MSPA, the Government may terminate the contract, in addition to other remedies or penalties prescribed by law.
H – 9 - PERSONAL PROTECTIVE EQUIPMENT
1. The contractor will train in the safe operation and use of equipment to all workers using such equipment.
2. Personal protective equipment, including personal protective equipment for eyes, face, head, and extremities shall be provided, used, and maintained in a sanitary and reliable condition wherever it is necessary by reason of hazards or processes encountered in a manner capable of causing injury or impairment in the function of any part of the body.
3. Defective or damaged personal protective equipment shall not be used.
4. The contractor shall provide, at no cost to the employee, to each employee who operates a chain saw, chain saw chaps and assure the chaps are worn during saw operations. These chaps must be approved by Underwriters Laboratory or meet Forest Service specification 6170-47. The chaps shall cover the full length of the thigh to the top of the boot on each leg.
5. The contractor shall assure that each employee wears foot protection that provides adequate traction and ankle support. Employees operating chain saws shall wear foot protection that is constructed with cut-resistant material which will protect the employee against contact with a running chain saw.
6. The contractor shall provide, at no cost to the employee, and assure that each employee who works in an area where there is potential for head injury from falling objects or flying objects wears a hard hat that meets the minimum requirements of American National Standards Institute (ANSI) standard Z89.1-1997.
7. The contractor shall provide, at no cost to the employee, eye protection where there is potential for eye injury due to flying objects. This eye protection must meet the minimum requirements of ANSI standard Z87.1-2003.
The contractor shall provide, at no cost to the employee, hearing protection where there is a potential for hearing loss due to high intensity noise e.g., chain saw operation
H-10 - ENVIRONMENTAL MANAGEMENT SYSTEM (EMS)
Definition. An EMS provides a systematic approach for continually improving environmental performance. An EMS identifies the major environmental aspects and associated impacts that occur on a National Forest or Grassland. There are controls already in place to manage these impacts, such as NEPA analysis, best management practices (BMPs), and resource monitoring. The EMS simply documents and ensures that these controls are in place and working as intended. EMS is an ongoing process that formalizes the Forest Service’s commitment to adaptive management and continual improvement of the environment.
Environmental Objectives:
1. Invasive Weeds – Reduce invasive weed introduction or spread through improved and more effective control and management.
2. Vegetation Management – 1) Restore or maintain vegetation health including the improvement or maintenance of resilient, native wildlife habitat and 2) Reduce fuels in a pattern and location to decrease fire intensity in the proximity of WUI or Community Wildfire Protection Plan areas.
3. Travel Management – 1) Reduce the existing road systems’ contributed sediment and impairment of water quality and aquatic habitats and 2) Improve security for grizzly bears or elk through the designation of roads, trails, and areas for motor vehicle use.
BARRICADES, WARNING SIGNS, AND OTHER DEVICES
The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.
The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.
Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.
The contractor is responsible for the safety of the public and the safe passage of vehicles on the 250 road when work is being done on adjacent roads above Road 250 where rock and other debris may fall or roll to the road. Temporary closures (less than 1 hour) or Flaggers may be necessary. Additional signs would be required also.
…As a minimum, it is anticipated that the following type and number of signs will be required:
| Location |
| Designation |
| Quantity |
| At the beginning of each road being worked on that junctions with Rd. 250. |
| ROAD CLOSED |
| 1 |
LANDSCAPE PRESERVATION
(a) Do not remove, deface, injure, or destroy trees, shrubs, lawn, or natural features not designated for treatment. This does not include access roads. Confine operations to within the clearing limits or other areas designated in the contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Retrieve material which falls outside of these limits and dispose of, or incorporate in the work.
Preserve the scenic and natural environment along this construction project.
(b) Do not allow objectionable material to enter any stream, river, lake, or other body of water. Retrieve material which falls in these areas and dispose of, or incorporate in the work, and repair damage to vegetation or structures outside the project limits.
(c) Do not operate equipment or otherwise disturb the natural vegetation and soil beyond the construction limits.
ENVIRONMENTAL PROTECTION
Prevention of Oil Spills.
The contractor is required to have a spill plan. The plan will contain a description of the specific hazardous materials, procedures, and spill containment that will be used, including inventory, storage, and handling.
All vehicles carrying fuel will have specific equipment and materials needed to contain or clean up any incidental spills at the project site.
All pumps and generators used in or near streams will have appropriate spill containment structures and/or absorbent pads in place during use.
When storage facilities for oil or oil products are on site, appropriate preventive measures shall be taken to insure that any spill of such oil or oil products does not enter any stream or any other body of water. If a spill of petroleum product should occur in water, immediately notify the Contracting Officer and appropriate state agencies.
Service all equipment only in the areas approved by the Contracting Officer. If the total oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of 660 gallons, prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Meet all applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.
Contractor shall ensure that all personnel involved in handling and packaging the hazardous waste are trained for the level of expertise required for the proper performance of the task and, in particular, in the areas of chemical incompatibility, general first aid procedures, and spills. Provide handling and personal protective equipment appropriate to ensure safe handling of the hazardous waste according to 29 CFR 1910.120). Notify the Forest Service of all hazardous material that may be brought onto the National Forest.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. The contractor must clean up spills or leaks in a manner that complies with Federal, state, and local laws and regulations and to the satisfaction of the CO. Any spills resulting in a detectable sheen on water shall be reported to the EPA National Response Center (1-800-424-8802). Any spills over 25 gallons will be reported to the Idaho Division of Environmental Quality and cleanup will be initiated within 24 hours of the spill. When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
Equipment Fuel/Oil Leakage.
All equipment used for instream work will be cleaned of external oil, grease, dirt and mud; and leaks repaired; prior to arriving at the project site. All equipment will be inspected by the Contracting Officer’s Representative before unloading at site. Any leaks or accumulations of grease will be corrected before entering streams or areas that drain directly to streams or wetlands.
Equipment used for in-stream or riparian work (including chainsaws and other hand power tools) will be fueled and serviced in an area approved by the CO. When not in use, vehicles will be stored in the designated staging area. The staging area should be in an area that will not deliver fuel, oil, etc. to streams.
Oil-absorbing floating booms, and other equipment such as pads and absorbent “peanuts” appropriate for the size of the stream, will be available on-site during all phases of construction. For small streams with few pools or slack water, booms may not be effective. Use pads and straw bales to anchor booms if necessary. Booms will be placed in a location that facilitates an immediate response to potential petroleum leakage.
NOXIOUS WEED CONTROL
In order to prevent the potential spread of noxious weeds into work areas, Contractor shall be required to use weed-free equipment.
The following is considered proof of weed-free equipment:
The Contractor will be required to clean all construction equipment prior to entry on to national forest land. This cleaning shall remove all dirt and plant parts and material that could carry noxious weed seeds into the work area. Only clean construction equipment inspected by the Forest Service will be allowed to operate within the work area. All subsequent move-ins of construction equipment shall be treated in the same manner as initial move-in. "Construction equipment" does not include pickup trucks and personal vehicles.
Straw/Hay Bales shall be certified as “Weed Free”. The source field shall be inspected and certified by the county extension agent from the county that the straw/hay is grown. Each shipment onto the forest shall be accompanied by a certification tag stating that it is weed free. The contractor shall furnish the forest service with a statement of certification.
H 11 - 52.204-11 American Recovery and Reinvestment Act--Reporting Requirements. (MAR 2009)
(a) Definitions. As used in this clause--
"Contract," as defined in FAR 2.101, means a mutually binding legal relationship obligating the seller to furnish the supplies or services (including construction) and the buyer to pay for them. It includes all types of commitments that obligate the Government to an expenditure of appropriated funds and that, except as otherwise authorized, are in writing. In addition to bilateral instruments, contracts include (but are not limited to) awards and notices of awards; job orders or task letters issued under basic ordering agreements; letter contracts; orders, such as purchase orders, under which the contract becomes effective by written acceptance or performance; and bilateral contract modifications. Contracts do not include grants and cooperative agreements covered by 31 U.S.C. 6301, et seq. For discussion of various types of contracts, see FAR Part 16.
"First-tier subcontract" means a subcontract awarded directly by a Federal Government prime contractor whose contract is funded by the Recovery Act.
"Jobs created" means an estimate of those new positions created and filled, or previously existing unfilled positions that are filled, as a result of funding by the American Recovery and Reinvestment Act of 2009 (Recovery Act). This definition covers only prime contractor positions established in the United States and outlying areas (see definition in FAR 2.101). The number shall be expressed as "full-time equivalent" (FTE), calculated cumulatively as all hours worked divided by the total number of hours in a full-time schedule, as defined by the contractor. For instance, two full-time employees and one part-time employee working half days would be reported as 2.5 FTE in each calendar quarter.
"Jobs retained" means an estimate of those previously existing filled positions that are retained as a result of funding by the American Recovery and Reinvestment Act of 2009 (Recovery Act). This definition covers only prime contractor positions established in the United States and outlying areas (see definition in FAR 2.101). The number shall be expressed as "full-time equivalent" (FTE), calculated cumulatively as all hours worked divided by the total number of hours in a full-time schedule, as defined by the contractor. For instance, two full-time employees and one part-time employee working half days would be reported as 2.5 FTE in each calendar quarter.
"Total compensation" means the cash and noncash dollar value earned by the executive during the contractor's past fiscal year of the following (for more information see 17 CFR 229.402(c)(2)):
(1) Salary and bonus.
(2) Awards of stock, stock options, and stock appreciation rights. Use the dollar amount recognized for financial statement reporting purposes with respect to the fiscal year in accordance with the Statement of Financial Accounting Standards No. 123 (Revised 2004) (FAS 123R), Shared Based Payments.
(3) Earnings for services under non-equity incentive plans.