United States Department of Agriculture
Forest Service
Golconda Job Corps Civilian Conservation Center
August 2014
Cafeteria Modifications
Contract Documents
AUSD
CAFETERIA MODIFICATIONS 001500 – 1
GOLCONDA JOB CORPS CCC LIST OF DRAWINGS AND SPECIFICTIONS
SECTION 001500
GOLCONDA JOB CORPS CCC
CAFETERIA MODIFICATIONS
LIST OF DRAWINGS AND SPECIFICATIONS
PART 1 – GENERAL
1.1 DESCRIPTION
A. List of Contract Drawings:
1. Index of Sheets:
T0.1 Title Sheet - General H1.1 Asbestos Removal and Tile Floor Plans H1.2 Photographs H1.3 Photographs A1.1 First Floor and Dishwashing Partial Plans A1.2 Photographs A2.1 Roof Replacement Plan and Photographs E1.1 Electrical Floor Plans E1.2 Photographs
9 Total Plan Sheets in this Contract
B. List of Contract Specifications
1. Index of Specifications
DIVISION 1 - GENERAL REQUIREMENTS
Section 001500 List of Drawings and Specifications Section 010150 General Requirements
DIVISION 2 – EXISTING CONDITIONS
Section 024119 Selective Demolition Section 028213 Asbestos Abatement
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
Section 074113 Metal Roof Panels
DIVISION 9 – FINISHES
Section 095334 PVC Suspended Ceiling Section 096513 Resilient Wall Base and Accessories Section 096516 Slip Resistant Sheet Vinyl Flooring
CAFETERIA MODIFICATIONS 001500 – 2
GOLCONDA JOB CORPS CCC LIST OF DRAWINGS AND SPECIFICTIONS
Section 096519 Resilient Tile Flooring Section 097200 Vinyl Wall Covering
DIVISION 10 – SPECIALTIES
Section 102613 Wall and Door Protection
DIVISION 11 – EQUIPMENT
Section 114000 Foodservice Equipment
DIVISION 23 – MECHANICAL
Section 230500 Mechanical Materials and Methods
DIVISION 26 – ELECTRICAL
Section 260500 Electrical Materials and Methods Section 260553 Identification for Electrical Systems Section 262413 Main Distribution Panels Section 262416 Panelboards
CAFETERIA MODIFICATIONS 010150 – 1
GOLCONDA JOB CORPS CCC GENERAL REQUIREMENTS
SECTION 010150
GENERAL REQUIREMENTS
PART 1 – SUMMARY OF WORK
1.
1.1 DESCRIPTION
A. Work for this project requires the contractor to be responsible for supplying all labor, materials, equipment, utilities, miscellaneous items, freight and delivery and all necessary valid licenses and permits for the work summarized as follows:
1. Remove metal roof and install new roof.
2. Remove asbestos containing floor tile and mastic and install new flooring.
3. Replace electrical panels, circuit breakers, and associated electrical components.
4. Remove dishwashing room ceramic tile on floor, walls, and ceiling. Remove floor, wall, and ceiling mounted electrical, mechanical and plumbing devices. Remove dishwasher and associated equipment, stainless steel kitchen shelves and tables.
Provide and install new vinyl floor and wall covering systems, and suspended grid ceiling system. Reinstall electrical, mechanical, and plumbing devices. Provide and install new lighting, dishwasher, and associated electrical devices and lighting.
B. This project is located at the Golconda Job Corps Civilian Conservation Center on a 200-acre site in the Shawnee National Forest near Golconda, Pope County, Illinois. Travel on Route 13 east to Harrisburg. Turn right on Route 34 south. Travel approximately 30 miles to Junction of Highway 146 and 34. Travel directly across on Highway 146 south for approximately 3 miles. The Center is located at the end of the 3 mile road. The Golconda Job Corps Center address is: 345 Job Corps Road, Golconda, Illinois 62938.
Driving directions can be obtained from the Center by calling 618-285-6601.
1.2 USE OF PREMISES
A. Use of Site: Confine constructions operations to immediate area of work. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Full Government Occupancy: Government will occupy site and buildings during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations.
C. Driveways and Entrances: Keep driveways, parking areas, loading areas and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government and authorities having jurisdiction.
CAFETERIA MODIFICATIONS 010150 – 2
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
1.3 PROJECT SCHEDULING
A. Schedule the majority of the work associated with asbestos removal and tile replacement, dishwashing room tile removal and new finishes, and electrical project work to occur during either winter or summer break. Breaks are approximately 2 weeks long and occur over Christmas/New Years and July 4th holidays. During this time students are on vacation and the facility is closed.
1.4 WORK RESTRICTIONS
A. Nonsmoking Buildings: Smoking is not permitted within the buildings or within 25 feet (8 m) of entrances, operable windows, or outdoor air intakes.
1.5 CONTRACTOR’S RESPONSIBILITIES
A. Confine storage of materials to areas as approved by the CO.
B. Provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations.
C. Minimize disturbance of surrounding areas. Return surrounding areas disturbed by construction activities to their original condition.
1.6 FIELD VERIFICATION
A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.
1.7 PERMITS
A. Obtain permits for work required by County, State, or Federal laws or regulations.
PART 2 – DEFINITION OF ITEMS AND PAYMENT
2.
2.1 DESCRIPTION
A. This section explains what is and what is not included in each pay item; the limits or cut-off points where one item ends and another begins; and basis of payment for work items listed in the Schedule of Items.
B. Payment: For each individual item listed here and in the Schedule of Items, payment shall be full compensation for all work related to the particular item in accordance with these specifications, and as shown on the drawings.
CAFETERIA MODIFICATIONS 010150 – 3
2.2 SCHEDULE OF ITEMS
A. Schedule of Items: The project Schedule of Items includes several sections to organize the work into Base Items and Optional Items.
1. Provide pricing for all items listed in the Schedule of Items.
2. Contract award will be made for all Base Items.
3. Optional Items will be awarded based on available project funding.
a. Optional Items 3 and 4: Only one of these optional items will be awarded.
B. Base Items (BI):
1. Base Item No. 1- Metal Roof Replacement
a. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor and incidentals to remove and dispose of metal roof panels, flashing, gutters, and down spouts; provide and installation of new metal roof panels, flashing, gutters, and downspouts.
C. Optional Items (OI):
1. Optional Item No. 1- Dining Area Asbestos Flooring Abatement
a. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor and incidentals to remove and dispose of vinyl flooring and wall base; abate asbestos containing floor flooring and mastic; and provide and installation of new resilient flooring and resilient wall base.
2. Optional Item No. 2- Electrical Panel Replacement
a. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor and incidentals required for the removal and replacement of one 800 amp panel, two 225 amp panels and associated circuit breakers with new 800 amp panel, two 225 amp panels, and circuit breakers, including demolition, disposal, and reconnection of electrical circuits.
3. Optional Item No. 3- Main Distribution Panel Service
a. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor and incidentals to perform preventative maintenance cleaning and adjustment of 1200 amp main distribution panel and associated circuit breakers including tightening wire terminals and verifying circuit breakers trip/open at originally designed protection settings.
4. Optional Item No. 4- Main Distribution Panel Replacement
a. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor and incidentals required for the removal and replacement of 1200 amp main distribution panel and associated
CAFETERIA MODIFICATIONS 010150 – 4
circuit breakers with new 1200 amp panel and circuit breakers, including demolition, disposal, and reconnection of electrical circuits.
5. Optional Item No. 5- Dishwashing Room
a. Payment: The contract lump sum price as shown in the Schedule of Items includes all materials, equipment, labor and incidentals to remove and dispose of ceramic and quarry tile installed on floor and ceramic tile installed on walls, and ceiling; remove miscellaneous mechanical, plumbing, and electrical devices. Provide and installation of new floor underlayment and preparation of wall surfaces; provide and installation of new vinyl floor and wall systems; provide and installation of suspended vinyl grid ceiling system;
provide and installation of new electrical devices and lighting; provide and installation of new dishwasher and associated equipment, provide and installation of stainless steel wall protection panels and corners. Reinstall and connect removed mechanical, plumbing, electrical and kitchen equipment and devices.
PART 3 – ACCIDENT PREVENTION
3.
3.1 DESCRIPTION
A. This section consists of establishing an effective accident prevention plan and providing a safe environment for personnel and visitors.
3.2 SUBMITTALS
A. Accident Prevention Plan: Before on-site work begins, submit a company approved accident prevention plan. This plan will be posted in the contract file. Design the plan to address Federal, State, and Local Occupational Safety and Health requirements that apply to this project. Notice to proceed will not be made until the plan is received. As a minimum the plan shall include:
1. Name, position title and contact information of company executive responsible for approving the Accident Prevention Plan.
2. Name and contact information of supervisor responsible to carry out the plan.
3. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, government personnel, and the Contractor's employees. Identify the work included under each phase by reference to specification section or division numbers.
4. Contingency plans for emergency situations such as medical, fire, hazard material spills and other contract assessed hazard prevention and abatement requirement needs that apply to this project.
B. Certificates: Provide certificates from a mechanic that all mechanical equipment has been inspected and meets OSHA requirements.
CAFETERIA MODIFICATIONS 010150 – 5
C. Submit a copy of test reports, as required by OSHA, for personnel working with hazardous materials.
D. Submit a brief report of safety meetings and of inspections.
E. Upon request, submit proof of employees' qualifications to perform assigned duties in a safe manner.
3.3 QUALITY ASSURANCE
A. Clauses entitled "Accident Prevention" and "Permits and Responsibilities" of the General Provisions: In case of conflicts between Federal, state, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. Qualifications of Employees: Ensure employees are physically qualified to perform assigned duties in a safe manner.
3.4 ACCIDENT REPORTING
A. Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Within 7 calendar days of a reportable accident, fill out and forward to the CO a CA-1 form, which may be obtained from CO.
B. All Other Accidents: Report all other accidents to the CO as soon as possible and assist the CO and other officials as required in the investigation of the accident.
3.5 FIRST AID FACILITIES
A. Provide adequate facilities for the number of employees and the type of construction at the site.
3.6 PERSONNEL PROTECTIVE EQUIPMENT
A. Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.
3.7 EMERGENCY INSTRUCTIONS
A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
3.8 PROTECTIVE EQUIPMENT
A. Inspect personal protective equipment daily and maintain in a serviceable condition.
Clean, sanitize, and repair, as appropriate, personal items before issuing them to another individual.
CAFETERIA MODIFICATIONS 010150 – 6
B. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
3.9 SAFETY MEETINGS
A. As a minimum, conduct weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.
3.10 HARD HATS AND PROTECTIVE EQUIPMENT AREAS
A. The CO will designate a hard hat area. Post the hard hat area in a manner satisfactory to the CO.
B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary protective equipment at all times. As a minimum, provide two hard hats for use by visitors. Change liners before reissuing hats.
3.11 TRAINING
A. First Aid: Provide adequate training to ensure prompt and efficient first aid.
B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
PART 4 – SUBMITTAL PROCEDURES
4.
4.1 DESCRIPTION
A. This section includes administrative and procedural requirements for submittals.
4.2 DEFINITIONS
A. Action Submittals: Written and graphic information that requires Contracting Officer’s (CO's) responsive action.
B. Informational Submittals: Written information that does not require CO's approval.
Submittals may be rejected for not complying with requirements.
4.3 PROCEDURES
A. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.
CAFETERIA MODIFICATIONS 010150 – 7
1. Initial Review: Allow 10 working days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Allow 10 working days for processing each re-submittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
B. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space approximately 2 by 3 inches on label or beside title block to record
Contractor's review and approval markings and action taken by CO.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. Other necessary identification.
C. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
D. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.
E. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
F. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
G. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
H. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.
CAFETERIA MODIFICATIONS 010150 – 8
I. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
4.4 ACTION SUBMITTALS
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Number of Copies: Submit four copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Compliance with recognized trade association standards.
g. Compliance with recognized testing agency standards.
4.5 INFORMATIONAL SUBMITTALS
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit two copies of each submittal, unless otherwise indicated. CO will not return copies.
2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
B. Contractor's Construction Schedule: Provide a construction schedule.
C. Cost Breakdown: Following award provide a cost breakdown schedule listing main types of work with associated costs for each bid item.
PART 5 – TEMPORARY FACILITIES AND CONTROLS
CAFETERIA MODIFICATIONS 010150 – 9
5.
5.1 DESCRIPTION
A. This section consists of requirements for temporary facilities and controls, including utilities, support facilities, and security and protection facilities.
5.2 UTILITIES
A. Water Service: Use of Government existing water service facilities will be permitted without metering and without payment of use charges, as long as facilities are cleaned and maintained in a condition acceptable to CO. At Substantial Completion, restore these facilities to condition existing before initial use.
B. Sanitary Facilities: Use of Government sanitary facilities will be permitted, as long as facilities are cleaned and maintained in a condition acceptable to CO. At Substantial Completion, restore these facilities to condition existing before initial use.
C. Electric Power and Lighting Service: Use of Government's existing electric power and lighting service will be permitted without metering and without payment of use charges, as long as equipment is maintained in a condition acceptable to CO. Contractor shall provide emergency power, as needed to continue construction work, when construction activities and sequencing requires power to be turned off or interrupted.
D. Telephone Service: The Contractor is responsible for providing telephone service deemed necessary for the duration of the construction.
5.3 STORAGE AREAS
A. Coordinate on-site storage requirements with the Contracting Officer.
5.4 CONSTRUCTION WASTE DISPOSAL FACILITIES
A. Provide waste-collection containers in sizes adequate to handle recycled and waste from construction operations. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other waste.
5.5 SUPPORT FACILITIES INSTALLATION
A. Locate temporary construction and support facilities for easy access.
5.6 SECURITY AND PROTECTION FACILITIES INSTALLATION
A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects. Restrict use of noisemaking tools and equipment to hours that will minimize complaints from persons or firms near Project site.
CAFETERIA MODIFICATIONS 010150 – 10
B. Barricades, Warning Signs, and Lights: Comply with standards and code requirements for erecting structurally adequate barricades. Paint with appropriate colors, graphics, and warning signs to inform personnel and public of possible hazard. Where appropriate and needed, provide lighting, including flashing red or amber lights.
C. Fire Protection:
1. Store combustible materials in containers in fire-safe locations.
2. Maintain unobstructed access to fire extinguishers, fire hydrants, fire-protection facilities, stairways, and other access routes for firefighting. Prohibit smoking in hazardous fire-exposure areas.
3. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition.
PART 6 – EXECUTION REQUIREMENTS
6.
6.1 DESCRIPTION
A. This section consists of general procedural requirements governing execution of the Work including, but not limited to, the following:
1. General installation of products.
2. Progress cleaning.
3. Protection of installed construction.
4. Correction of the Work.
6.2 EXAMINATION
A. Existing Conditions: Before beginning work, investigate and verify the existence and location of mechanical and electrical systems and other construction affecting the Work.
B. Acceptance of Conditions: Examine areas, and conditions, with Installer. Record observations.
1. Examine roughing-in for electrical systems to verify actual locations of connections before equipment and fixture installation.
2. Proceed with installation only after unsatisfactory conditions have been corrected.
Proceeding with the Work indicates acceptance of surfaces and conditions.
6.3 PREPARATION
A. Field Measurements: Take field measurements as required to fit the Work properly.
B. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to CO.
CAFETERIA MODIFICATIONS 010150 – 11
Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents.
6.4 INSTALLATION
A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.
1. Make vertical work plumb and make horizontal work level.
B. Comply with manufacturer's written instructions and recommendations for installing products.
C. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.
6.5 PROGRESS CLEANING
A. General: Clean Project site and work areas daily, including common areas. Dispose of materials lawfully.
1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.
2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F (27 deg C).
3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.
B. Site: Maintain Project site free of waste materials and debris.
C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.
D. Waste Disposal: Burying or burning waste materials on-site will not be permitted.
Washing waste materials down sewers or into waterways will not be permitted.
6.6 PROTECTION OF INSTALLED CONSTRUCTION
A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.
6.7 CORRECTION OF THE WORK
A. Repair or remove and replace defective construction. Restore damaged substrates and finishes.
CAFETERIA MODIFICATIONS 010150 – 12
1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.
PART 7 – WASTE MANAGEMENT AND RECYCLING
7.
7.1 DESCRIPTION
A. This Section consists of administrative and procedural requirements for recycling and disposal of nonhazardous waste.
7.2 GENERAL
A. Provide handling, containers, storage, signage, transportation, and other items as required to implement waste disposal.
B. Identify anticipated types of waste generated and determine whether it will be recycled or disposed.
7.3 RECYCLING WASTE
A. The contractor is encouraged to recycle waste materials where possible. Revenues, savings, rebates, tax credits, and other incentives received for recycling waste materials shall accrue to the Contractor.
B. Provide marked containers or bins for controlling recyclable waste.
C. Separate recyclable waste from other waste materials, trash, and debris.
D. Remove recyclable waste from the property and transport to recycling receiver or processor.
7.4 DISPOSAL OF WASTE
A. General: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill.
1. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
B. Burning: Do not burn waste materials.
C. Disposal: Remove waste materials from Government's property and legally dispose of them.
PART 8 – OPERATIONS AND MAINTENANCE MANUALS
8.
CAFETERIA MODIFICATIONS 010150 – 13
8.1 DESCRIPTION
A. This Section consists of administrative and procedural requirements for operation and maintenance manuals.
8.2 SUBMITTALS
A. Submit two manuals in final form at least 15 working days before final inspection.
8.3 OPERATION AND MAINTENANCE MANUALS
A. Assemble a complete set of operation and maintenance data indicating the operation and maintenance of each system, subsystem, and piece of equipment not part of a system.
Include operation and maintenance data required in individual Specification Sections and as follows:
1. Operation Data: Include emergency instructions and procedures, system and equipment descriptions, operating procedures, and sequence of operations.
2. Maintenance Data: Include manufacturer's information, list of spare parts, maintenance procedures, maintenance and service schedules for preventive and routine maintenance, and copies of warranties and bonds.
B. Organization: Unless otherwise indicated, organize each manual into a separate section for each system and subsystem, and a separate section for each piece of equipment not part of a system. Each manual shall contain a title page, table of contents, and manual contents.
C. Title Page: Enclose title page in transparent plastic sleeve. Include the following information:
1. Subject matter included in manual.
2. Name and address of Project.
3. Name and address of Job Corps.
4. Date of submittal.
5. Name, address, and telephone number of Contractor.
6. Cross-reference to related systems in other operation and maintenance manuals.
D. Table of Contents: List each product included in manual, identified by product name, indexed to content of volume, and cross-referenced to Specification Section.
E. Manual Contents: Organize into sets of manageable size. Arrange contents alphabetically by system, subsystem, and equipment. If possible, assemble instructions for subsystems, equipment, and components of one system into a single binder.
1. Binders: Heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, in thickness necessary to accommodate contents, sized to hold 8-1/2-by-11-inch paper; with clear plastic sleeve on spine to hold label describing contents and with pockets inside covers to hold folded oversize sheets.
CAFETERIA MODIFICATIONS 010150 – 14
a. Identify each binder on front and spine, with printed title "OPERATION
AND MAINTENANCE MANUAL," Project title or name, and subject matter of contents. Indicate volume number for multiple-volume sets.
2. Dividers: Heavy-paper dividers with plastic-covered tabs for each section. Mark each tab to indicate contents. Include typed list of products and major components of equipment included in the section on each divider, cross-referenced to Specification Section number and title of Project Manual.
3. Protective Plastic Sleeves: Transparent plastic sleeves designed to enclose diagnostic software diskettes for computerized electronic equipment.
4. Drawings: Attach reinforced, punched binder tabs on drawings and bind with text.
a. If oversize drawings are necessary, fold drawings to same size as text pages and use as foldouts.
b. If drawings are too large to be used as foldouts, fold and place drawings in labeled envelopes and bind envelopes in rear of manual. At appropriate locations in manual, insert typewritten pages indicating drawing titles, descriptions of contents, and drawing locations.
F. Content: Include operation and maintenance data required in individual Specification Sections and equipment descriptions, operating standards, operating procedures, operating logs, wiring and control diagrams, and license requirements.
G. Descriptions: Include the following:
1. Product name and model number.
2. Manufacturer's name.
3. Equipment identification with serial number of each component.
4. Equipment function.
5. Operating characteristics.
6. Performance curves.
7. Engineering data and tests.
8. Complete nomenclature and number of replacement parts.
H. Source Information: For each product, list name, address, and telephone number of Installer or supplier.
I. Operating Procedures: Include startup, break-in, and control procedures; stopping and normal shutdown instructions; routine, normal, seasonal, and weekend operating instructions; and required sequences for electric or electronic systems.
J. Systems and Equipment Controls: Describe sequence of operation, and diagram controls as installed.
K. Maintenance Procedures: For each system, subsystem, and piece of equipment not part of a system, include manufacturers' maintenance documentation, maintenance
CAFETERIA MODIFICATIONS 010150 – 15
procedures, maintenance and service schedules, drawings and diagrams for maintenance, nomenclature of parts and components, and recommended spare parts for each component part or piece of equipment.
L. Maintenance and Service Schedules: Include service and lubrication requirements, list of required lubricants for equipment, and separate schedules for preventive and routine maintenance and service with standard time allotment.
M. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances and conditions that would affect validity of warranties or bonds. Organize warranty documents into an orderly sequence based on the table of contents of the Project Manual.
1. Provide heavy paper dividers with plastic-covered tabs for each separate warranty.
Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer.
PART 9 – CLOSEOUT PROCEDURES
9.
9.1 DESCRIPTION
A. This section consists of administrative and procedural requirements for contract closeout, including, but not limited to, the following:
1. Inspection procedures.
2. Project Record Documents.
3. Final cleaning.
9.2 SUBSTANTIAL COMPLETION
A. Definition of Substantial Completion: The Date certified by the Contracting Officer when construction is sufficiently complete, in accordance with the Contract Documents, so the Government can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents.
B. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete in request.
1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete.
2. Advise Contracting Officer (CO) of pending insurance changeover requirements.
3. Submit specific warranties, workmanship bonds, final certifications, and similar documents.
4. Obtain and submit releases permitting Government unrestricted use of the Work and access to services and utilities. Include occupancy permits, operating certificates, and similar releases.
CAFETERIA MODIFICATIONS 010150 – 16
5. Prepare and submit Project Record Documents, operation and maintenance manuals, Final Completion construction photographs and photographic negatives, and similar final record information.
6. Complete startup testing of systems.
7. Complete final cleaning requirements, including touchup painting.
8. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.
C. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by CO, that must be completed or corrected before certificate will be issued.
1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.
2. Results of completed inspection will form the basis of requirements for Final Completion.
9.3 FINAL COMPLETION
A. Preliminary Procedures: Before requesting final inspection for determining date of Final Completion, complete the following:
1. Submit certified copy of CO’s Substantial Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by CO. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.
2. Submit evidence of final, continuing insurance coverage complying with insurance requirements.
3. Instruct Government personnel in operation, adjustment, and maintenance of products, equipment, and systems.
B. Inspection: Submit a written request for final inspection for acceptance. On receipt of request, CO will either proceed with inspection or notify Contractor of unfulfilled requirements. CO will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.
1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.
9.4 LIST OF INCOMPLETE ITEMS (PUNCH LIST)
A. Preparation: Submit three copies of list. Include name and identification of each space and area affected by construction operations for incomplete items and items needing
CAFETERIA MODIFICATIONS 010150 – 17
correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.
9.5 PROJECT RECORD DOCUMENTS
A. General: Do not use Project Record Documents for construction purposes. Protect Project Record Documents from deterioration and loss. Provide access to Project Record Documents for CO's reference during normal working hours.
B. Record Drawings: Maintain and submit one set of blue- or black-line white prints of Contract Drawings and Shop Drawings.
1. Mark Record Prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to prepare the marked-up Record Prints.
a. Give particular attention to information on concealed elements that cannot be readily identified and recorded later.
b. Record data as soon as possible after obtaining it. Record and check the markup before enclosing concealed installations.
2. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at the same location.
3. Note Construction Change Directive numbers, Change Order numbers, alternate numbers, and similar identification where applicable.
4. Identify and date each Record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location. Organize into manageable sets;
bind each set with durable paper cover sheets. Include identification on cover sheets.
9.6 FINAL CLEANING
A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.
B. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.
C. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a portion of Project:
1. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.
CAFETERIA MODIFICATIONS 010150 – 18
2. Remove tools, construction equipment, machinery, and surplus material from Project site.
3. Touch up and otherwise repair and restore marred, exposed finishes and surfaces.
Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or restoration.
D. Comply with safety standards for cleaning. Do not burn waste materials. Do not bury debris or excess materials on Government property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from Project site and dispose of lawfully.
END OF SECTION 010150
CAFETERIA MODIFICATIONS 024119 - 1
GOLCONDA JOB CORPS CCC SELECTIVE DEMOLITION
SECTION 024119
SELECTIVE DEMOLITION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes demolition, cutting, patching, repairs and removal of selected portions of a building or structure.
B. See Division 2 through 26 Sections for specific requirements and limitations applica-ble to individual parts of the work.
1.2 DEFINITIONS
A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.
B. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and re-installed.
C. Remove and Reinstall: Detach items from existing construction, prepare them for re-use, and reinstall them where indicated.
1.3 SUBMITTALS
A. Predemolition Photographs or Videotape: Show existing conditions of adjoining con-struction and site improvements that might be misconstrued as damage caused by se-lective demolition operations. Submit before Work begins.
1.4 QUALITY ASSURANCE
A. Regulatory Requirements: Comply with governing EPA notification regulations be-fore beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.
B. Standards: Comply with ANSI A10.6 and NFPA 241.
C. Visual Requirements: Do not cut and patch construction in a manner that results in visual evidence of cutting and patching. Do not cut and patch construction exposed on the exterior or in occupied spaces in a manner that would, in CO's opinion, reduce the building's aesthetic qualities. Remove and replace construction that has been cut and patched in a visually unsatisfactory manner.
1.5 PROJECT CONDITIONS
CAFETERIA MODIFICATIONS 024119 - 2
A. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.
1. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from authorities having jurisdiction.
B. Government assumes no responsibility for condition of areas to be selectively demol-ished.
1. Conditions existing at time of inspection for bidding purpose will be maintained by Government as far as practical.
C. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work. If materials suspected of containing hazardous materials are encoun-tered, do not disturb; immediately notify Contracting Officer (CO). Hazardous mate-rials will be removed by Government under a separate contract.
D. Storage or sale of removed items or materials on-site will not be permitted.
E. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.
1. Maintain fire-protection facilities in service during selective demolition opera-tions.
PART 2 – PRODUCTS
2.
2.1 REPAIR MATERIALS
A. Use repair materials identical to existing materials.
1. If identical materials are unavailable or cannot be used for exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent pos-sible.
2. Use materials whose installed performance equals or surpasses that of existing materials.
PART 3 – EXECUTION
3.
3.1 EXAMINATION
A. Verify that utilities have been disconnected and capped.
B. Survey existing conditions and correlate with requirements indicated to determine ex-tent of selective demolition required.
CAFETERIA MODIFICATIONS 024119 - 3
C. Inventory and record the condition of items to be removed and reinstalled and items to be removed and salvaged.
D. When unanticipated mechanical, electrical, or structural elements that conflict with in-tended function or design are encountered, investigate and measure the nature and ex-tent of conflict. Promptly submit a written report to CO.
E. Examine surfaces to be cut and patched and conditions under which cutting and patch-ing are to be performed.
1. Compatibility: Before patching, verify compatibility with and suitability of sub-strates, including compatibility with existing finishes or primers.
2. Proceed with installation only after unsafe or unsatisfactory conditions have been corrected.
3.2 UTILITY SERVICES
A. Existing Utilities: Maintain services indicated to remain and protect them against damage during selective demolition operations.
B. Do not interrupt existing utilities serving occupied or operating facilities unless au-thorized in writing by CO and authorities having jurisdiction. Provide temporary ser-vices during interruptions to existing utilities, as acceptable to CO and to authorities having jurisdiction.
1. Provide at least 72 hours notice to CO if shutdown of service is required during changeover.
3.3 PREPARATION
A. Temporary Partitions: Erect and maintain dustproof partitions and temporary enclo-sures to limit dust and dirt migration and to separate areas from fumes and noise.
3.4 POLLUTION CONTROLS
A. Dust Control: Use water mist, temporary enclosures, and other suitable methods to limit spread of dust and dirt. Comply with governing environmental-protection regulations.
1. Wet mop floors to eliminate trackable dirt and wipe down walls and doors of demolition enclosure.
B. Disposal: Remove and transport debris in a manner that will prevent spillage on adja-cent surfaces and areas.
1. Remove debris from elevated portions of building by chute, hoist, or other de-vice that will convey debris to grade level in a controlled descent.
CAFETERIA MODIFICATIONS 024119 - 4
C. Cleaning: Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.
3.5 DEMOLITION
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work with-in limitations of governing regulations.
1. Neatly cut openings and holes plumb, square, and true to dimensions required.
Use cutting methods least likely to damage construction to remain or adjoining construction. Do not overcut corners or masonry construction.
2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.
3. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.
4. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.
5. Dispose of Demolished items and materials promptly.
B. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by CO, items may be re-moved to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.
3.6 CUTTING, PATCHING, AND REPAIRS
A. General:
1. Promptly repair damage to adjacent construction caused by selective demolition operations.
2. Employ skilled workers to perform cutting, patching, and repairs.
B. Protection: Protect existing construction during cutting, patching, and repairs to pre-vent damage. Provide protection from adverse weather conditions for portions of pro-ject that might be exposed during cutting, patching, and repair operations.
C. Adjoining Areas: Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.
D. Existing Services: Where existing services are required to be removed, relocated, or abandoned, bypass such services before cutting to minimize interruption of services to occupied areas.
CAFETERIA MODIFICATIONS 024119 - 5
E. Cutting: Cut existing construction by sawing, drilling, breaking, chipping, grinding, and similar operations, using methods least likely to damage elements retained or ad-joining construction.
1. Provide temporary support of work to be cut.
2. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots as small as possible, neatly to size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.
3. Existing Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces.
4. Proceed with patching after construction operations requiring cutting or repairs are complete.
F. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other Work. Patch with durable seams that are as invisible as possible. Provide materials and comply with installation requirements specified in other Sections of these Specifications.
G. Repairs: Where repairs to existing surfaces are required, patch to produce surfaces suitable for new materials.
1. Completely fill holes and depressions in existing masonry walls that are to re-main with an approved masonry patching material applied according to manu-facturer's written recommendations.
H. Finishes: Restore exposed finishes of patched areas and extend restoration into ad-joining construction in a manner that eliminates evidence of patching and refinishing.
3.7 DISPOSAL OF DEMOLISHED MATERIALS
A. General: Promptly dispose of demolished materials. Do not allow demolished mate-rials to accumulate on-site.
B. Burning: Do not burn demolished materials.
C. Disposal: Transport demolished materials off Government property and legally dis-poses of them.
END OF SECTION 024119
CAFETERIA MODIFICATIONS 028213 - 1
GOLCONDA JOB CORPS CCC ASBESTOS ABATEMENT
SECTION 028213
ASBESTOS ABATEMENT
PART 1 - GENERAL
1.
1.1 SUMMARY
A. This Section includes general requirements for asbestos abatement for removal disposal, and testing associated with asbestos floor tile and mastic.
1.2 SUBMITTALS
A. As specified in Division 1 Section, “Submittal Procedures.”
1. Provide certification of General Abatement Contractor, Abatement Supervisor and Workers.
2. Provide abatement plan.
B. Closeout Submittals: As specified in Division 1 Section “Closeout Procedures.”
1. Submit copies of completed "Transportation and Disposal Manifest" forms for asbestos waste materials removed during the abatement process prior to requesting final payment.
2. Certification: Submit written certification that no asbestos-containing materials or hazardous materials have been used or incorporated in the new Work. Submit certification prior to Final Completion.
1.3 QUALITY ASSURANCE
A. Worker's Qualifications: Perform abatement work under the direct supervision of an Illinois certified supervisor.
B. Perform work to meet requirements of the Illinois Department of Public Health.
PART 2 – PRODUCTS (NOT USED)
2.
PART 3 – EXECUTION
3.
3.1 GENERAL ASBESTOS ABATEMENT
A. Comply with Illinois Department of Public Health when abating asbestos containing materials.
3.
This is the start of the file's text. The full file is on GovTribe.