Cottoner_Project_Specifications.docx
DOCX document 24 KB Posted
- Attached to
- Building Demolitions Mark Twain National Forest
- Solicitation number
- AG-64R4-S-16-0026JS
About this file
Specs
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AG-64R4-S-16-0026_0001_Cottoner_and_Roby_Demolitions.pdf | ||
| Roby_Dwelling_and_Cottoner_Radio_Building_Demolition_Solicitation_Questions.docx | DOCX document | |
| Cottoner_Attachment_C.docx | DOCX document | |
| Wage_Determination_1996-0223.pdf | ||
| Roby_Project_Specifications.docx | DOCX document | |
| Attachment_B_Roby_Lead_Risk_Assessment.pdf | ||
| Cottoner_Attachment_A.pdf | ||
| Technical_and_Green_Plan_Forms.rtf | RTF text file | |
| Attachment_A_ROBY_ASBESTOS_REPORT.pdf | ||
| Cottoner_Attachment_A_1_Asbestos_Inspection_Report_Ann.pdf | ||
| Cottoner_Radio_Building_Location_Map.docx | DOCX document | |
| AG-64R4-S-16-0026_Cottoner_and_Roby_Demolitions.pdf | ||
| Roby_Location_Map.docx | DOCX document | |
| Cottoner_Attachment_B.docx | DOCX document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Copyright 2013 by The American Institute of Architects (AIA) Exclusively published and distributed by Architectural Computer Services, Inc. (ARCOM) for the AIA
SECTION 011000 - SUMMARY
PART 1 - GENERAL
| 1.1 | PROJECT INFORMATION |
| A. | Project Identification: Cottoner Radio Building Removal from Mark Twain National Forest. |
| B. | Owner: USDA Forest Service, Mark Twain National Forest, 401 Fairgrounds Road, Rolla, MO 65401. |
Retain "Architect's Consultants" Paragraph below if providing contact information for Architect's consultants for Project use.
Copy and re-edit subparagraph below for each consultant. Coordinate with requirement in Section 012000 "Price and Payment Procedures" to arrange schedule of values data by design consultant contracts for purposes of delineating the scopes of multiple certifications of payments.
Retain "Design-Builder" Paragraph below for design-build projects.
Retain "Project Web Site" Paragraph below if Project uses a project Web site, project extranet, or FTP site for information and document management.
| C. | The Work consists of: |
| 1. BASE - 1: The work consists of removing and disposing of the Cottoner Radio Building from the Potosi/Fredericktown Ranger District, on the Mark Twain National Forest. Removal of the building shall include all attached structures, existing rubbish, and trash and contents in and adjacent to the building down to the concrete slab. The concrete slab shall be left in place unless removal is awarded under OBI - 01. All materials shall be removed from government property. The building is approximately 40’ x 20’ with an additional 20’x 20’ attached room. The walls are approximately 11’ high. Contractor is responsible to confirm actual building dimensions. | |
| 2. OBI – 01: The work consists of removing the concrete slab and foundation of the building. All materials shall be removed from government property. | |
| 3. OBI – 02: The work consists of removing the concrete lookout tower piers (4 each) located to the north of the radio building. A drawing showing the typical construction of the tower piers is attached for reference only (See Attachment C). The tower height is assumed to have been 100’. There may be a copper wire buried around the perimeter of the tower piers. The copper wire can be left in place but shall be left a minimum of 6 inches below grade. All other materials shall be removed from government property. | |
| D. | Owner-Furnished Products: There are no Government-Furnished products on this contract. |
| E. | Project Location (T32N, R8E, Sec. 18): From Fredericktown, MO travel South on State Highway 76 approximately 5 miles to State Highway “A”. Travel East on State Highway “A” approximately 5 miles to FR2180. The radio building is located at the tower site approximately 1 mile at the end of FR2180. |
NOTE: Any road repair work required for access to the Cottoner Radio building site will be performed by the Potosi/Fredericktown District personnel. Any trees required to be removed to facilitate demolition of the building will be evaluated and accomplished by the District personnel.
| 1.2 | WORK RESTRICTIONS |
| A. | Contractor's Use of Premises: During demolition, Contractor will have full use of site indicated. Contractor's use of premises is limited only by Owner's right to perform work or employ other contractors on portions of Project. |
| 1.3 | CONTRACT TIME: |
| A. | Contract time shall be 21 Calendar Days. |
| 1.4 | SCHEDULE |
| A. | Within 10 days after issuance of the Notice to Proceed the contractor shall submit a plan and schedule for removal of any designated improvements or material on the parcel. The work shall be performed in accordance with the approved plan and schedule. Work shall begin within 10 contract days from the Notice to Proceed. |
| 1.5 | CERTIFICATIONS |
| A. | Contractor personnel shall be certified by appropriate federal and state regulatory agencies to meet federal and local certification requirements in asbestos removal. All work with asbestos containing materials shall be performed with, and under the supervision of, skilled and experienced asbestos contractors directly employed by the Contractor, and certified in accordance with national and state standards. Contractor employees shall have a minimum of 16 hours of asbestos training by a person certified with the State of Missouri. Proof of certification for each employee shall be submitted to the COR prior to the start of work. |
| 1.6 | NOTIFICATION AND FEES |
| A. | Contractor is responsible for providing all required notifications concerning the removal and disposal of ACM per all Local, State and Federal regulations having jurisdiction and for the payment of any required fees. |
| 1.7 | MEASUREMENT AND PAYMENT |
| A. | BASE – 1: Measurement for removal of building and appurtenances will be considered a lump sum (LS) unit. |
| B. | OBI – 01: Measurement for removal of the concrete slab and foundation will be considered a lump sum (LS) unit. |
| C. | OBI – 02: Measurement for the excavation and removal of the concrete tower piers will be considered a lump sum (LS) unit. |
| 1.8 | BASIS OF PAYMENT |
| A. | The accepted removal of improvements will be paid at the contract lump sum (LS) price per Unit of Measure (Job). |
First subparagraph below contains an example of limitations on Contractor's use of premises; delete if not applicable. Insert other descriptions of areas or types of limited use, requirements for cooperation with Owner's personnel, noninterference with Owner's or public use, and other necessary restrictions if required.
"Limits" Subparagraph below is based on requirements of LEED-NC Credit SS 5.1. See Evaluations.
"Driveways, Walkways, and Entrances" Subparagraph below is an example of a special requirement appropriate to many projects. Revise to suit Project or delete.
PART 2 - PRODUCTS (Not Used) PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
Demolition/Removal of the Cottoner Radio Building
Copyright 2013 by The American Institute of Architects (AIA) Exclusively published and distributed by Architectural Computer Services, Inc. (ARCOM) for the AIA
SECTION 024119 - SELECTIVE DEMOLITION
PART 1 - GENERAL
| 1.1 | SECTION REQUIREMENTS |
| A. | Items indicated to be removed and salvaged remain Owner's property. Carefully detach from existing construction, in a manner to prevent damage, and deliver to Owner ready for reuse. Include fasteners or brackets needed for reattachment elsewhere. |
| B. | Pre-demolition Photographs: Pictures showing the existing conditions of the building are attached (See Attachment B) for the contractor’s reference only. Contractor is responsible for confirming actual site conditions prior to submission of offers. |
| C. | Post-Demolition Photographs: Contractor shall submit photographs showing the condition of the existing sites after demolition of the building and site cleanup. |
Retain, revise, or delete first paragraph below to suit Project. Insert other limitations if necessary, such as when adjacent floors will be occupied.
| D. | Asbestos: |
| 1. | The Cottoner Radio Building has been tested for ACM. The floor tiles in the main section of the building (approximately 40’ x 20’) have tested positive for ACM. The ACM is considered friable. The laboratory report is attached (See Attachment A). The Asbestos Building Inspector Report (Attachment A-1) is also attached. |
| 2. | All materials shall be removed in accordance with Missouri Department of Natural Resources (MDNR) regulations and any other agency having jurisdiction. If the contractor encounters suspect ACM not previously identified, the contractor shall stop work and immediately notify the Contracting Officer’s Representative (COR) so the Forest Service can have the suspect material sampled and tested. |
| 3. | Contractor personnel shall be certified by appropriate federal and state regulatory agencies to meet federal and local certification requirements in asbestos removal. All work with asbestos containing materials shall be performed with, and under the supervision of, skilled and experienced asbestos contractors directly employed by the Contractor, and certified in accordance with national and state standards. Contractor employees shall have a minimum of 16 hours of asbestos training by a person certified with the State of Missouri. Proof of certification for each employee shall be submitted to the COR prior to the start of work. |
| E. | Hazardous Material: The contractor may encounter small quantities of hazardous material as defined by the Missouri Department of Natural Resources (MDNR). This material shall be recycled or disposed of in a manner that maintains the material’s qualifications as “small quantities” in accordance with MDNR regulations. In the event the contractor encounters what is reasonably suspected to be large quantities of hazardous matter, the contractor shall immediately cease work and notify the COR. If the Forest Service determines the suspect material is not hazardous or does not constitute a large quantity of hazardous material the contractor will be notified to continue the work. |
PART 2 - PRODUCTS
| 2.1 | PEFORMANCE REQUIREMENTS |
| A. | Regulatory Requirements: Comply with EPA regulations and with hauling and disposal regulations of authorities having jurisdiction. |
| B. | Standards: Comply with ANSI/ASSE A10.6 and NFPA 241. |
PART 3 - EXECUTION
| 3.1 | DEMOLITION |
| A. | Maintain services/systems indicated to remain and protect them against damage during selective demolition operations. Before proceeding with demolition, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of the building. |
| B. | Locate, identify, shut off, disconnect, and seal or cap off indicated utility services and mechanical/electrical systems serving areas to be selectively demolished. |
Retain "Refrigerant" Paragraph below if selective demolition includes mechanical equipment containing refrigerant. Refrigerant may be part of equipment such as air-conditioning units, chillers, refrigerators, freezers, icemakers, heat pumps, dehumidifiers, and drinking water coolers.
| C. | Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain. |
| D. | The contactor shall at all times take necessary precautions to protect the life and health of all persons employed on the project. The contractor shall be familiar with the latest accepted accident prevention methods and shall provide necessary safety devices and safeguards accordingly. |
| E. | Provide and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished. |
| F. | Removal of buildings shall include all attached structures. Under no circumstances shall the contractor burn, grind, pulverize or otherwise reduce any portion of the building into fine particles. The contractor shall remove all components of the buildings unless otherwise specified. All existing wood and other material attached to concrete and masonry construction shall be removed. |
All ground disturbances not associated with the removal of the concrete slab and foundation (OBI – 01) and concrete tower piers (OBI – 02) shall be avoided. All holes or depressions caused from the removal of the concrete slab and foundation and concrete tower piers shall be filled and smoothed to match the existing adjacent ground as much as possible using the existing soil material disturbed by the removal excavations.
No ground disturbance shall be permitted outside a distance of 25 feet from the building on the South/Southwest side of the radio building due to cultural considerations.
| I. | Remove demolition waste materials from Project site and legally dispose of them in an EPA-approved landfill or in a method consistent with current MDNR regulations. No materials can be buried or burned on site. |
| J. | Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began. |
| K. | Seed and mulch any areas of ground disturbance. Seeding and mulching shall be considered incidental to the pay items. |
END OF SECTION 024119