Construction Specification 94—Contractor Quality Control
1. Scope The work consists of developing, implementing, and maintaining a quality control system to ensure that the specified quality is achieved for all materials and work performed.
2. Equipment and materials Equipment and material used for quality control shall be of the quality and condition required to meet the test specifications cited in the contract. Testing equipment shall be properly adjusted and calibrated at the start of operations and the calibration maintained at the frequency specified.
Records of equipment calibration tests shall be available to the engineer at all times. Equipment shall be operated and maintained by qualified operators as prescribed in the manufacturer's operating instructions, the references specified, and as specified in section 10 of this specification.
All equipment and materials used in performing quality control testing shall be as prescribed by the test standards referenced in the contract or in section 10.
All equipment and materials shall be handled and operated in a safe and proper manner and shall comply with all applicable regulations pertaining to their use, operation, handling, storage, and transportation.
3. Quality control system Method 1—The contractor shall develop, implement, and maintain a system of quality control to provide the specified material testing and verification of material quality before use. The system activities shall include procedures to verify adequacy of completed work, initiate corrective action to be taken, and document the final results. The identification of the quality control personnel and their duties and authorities shall be submitted to the contracting officer in writing within 15 calendar days after notice of award.
Method 2—The contractor shall develop, implement, and maintain a system adequate to achieve the specified quality of all work performed, material incorporated, and equipment furnished before use. The system established shall be documented in a written plan developed by the contractor and approved by the contracting officer. The system activities shall include the material testing and inspection needed to verify the adequacy of completed work and procedures to be followed when corrective action is required. Daily records to substantiate the conduct of the system shall be maintained by the contractor. The quality control plan shall cover all aspects of quality control and shall address, as a minimum, all specified testing and inspection requirements.
The plan provided shall be consistent with the planned performance in the contractor's approved construction schedule. The plan shall identify the contractor's onsite quality control manager and provide an organizational listing of all quality control personnel and their specific duties. The written plan shall be submitted to the contracting officer within 15 calendar days after notice of award. The contractor shall not proceed with any construction activity that requires inspection until the written plan is approved by the contracting officer.
7/8/2008
CONTRACTOR QUALITY CONTROL
All methods—The quality control system shall include, but not be limited to, a rigorous examination of construction material, processes, and operation, including testing of material and examination of manufacturer's certifications as required, to verify that work meets contract requirements and is performed in a competent manner.
4. Quality control personnel Method 1—Quality control activities shall be accomplished by competent personnel. A competent person is: One who is experienced and capable of identifying, evaluating, and documenting that materials and processes being used will result in work that complies with the contract; and, who has authority to take prompt action to remove, replace, or correct such work or products not in compliance. Off-site testing laboratories shall be certified or inspected by a nationally recognized entity. The Contractor shall submit to the Contracting Officer, for approval, the names, qualifications, authorities, certifications, and availability of the competent personnel who will perform the quality control activities.
Method 2—Quality control activities shall be accomplished by competent personnel who are separate and apart from line supervision and who report directly to management. A competent person is one who is experienced and capable of identifying, evaluating, and documenting that material and processes being used will result in work that complies with the contract, and who has authorization to take prompt action to remove, replace, or correct such work or products not in compliance. Offsite testing laboratories shall be certified or inspected by a nationally recognized entity. The contractor shall submit to the contracting officer, for approval, the names, qualifications, authorities, certifications, and availability of the competent personnel who will perform the quality control activities.
5. Post-award conference The contractor shall meet with the contracting officer before any work begins and discuss the contractor's quality control system. The contracting officer and the contractor shall develop a mutual understanding regarding the quality control system.
6. Records The contractor's quality control records shall document both acceptable and deficient features of the work and corrective actions taken. All records shall be on forms approved by the contracting officer, be legible, and be dated and signed by the competent person creating the record.
Unless otherwise specified in section 10 of this specification, records shall include:
a. Documentation of shop drawings including date submitted to and date approved by the contracting officer, results of examinations, any need for changes or modifications, manufacturer's recommendations and certifications, if any, and signature of the authorized examiner.
b. Documentation of material delivered including quantity, storage location, and results of quality control examinations and tests.
c. Type, number, date, time, and name of individual performing quality control activities.
d. The material or item inspected and tested, the location and extent of such material or item, and a description of conditions observed and test results obtained during the quality control activity.
e. The determination that the material or item met the contract provisions and documentation that the engineer was notified.
f. For deficient work, the nature of the defects, specifications not met, corrective action taken, and results of quality control activities on the corrected material or item.
7. Reporting results The results of contractor quality control inspections and tests shall be communicated to the engineer immediately upon completion of the inspection or test. Unless otherwise specified in section 10, the original plus one copy of all records, inspections, tests performed, and material testing reports shall be submitted to the engineer within one working day of completion. The original plus one copy of documentation of material delivered shall be submitted to the engineer before the material is used.
8. Access The contracting officer and the engineer shall be given free access to all testing equipment, facilities, sites, and related records for the duration of the contract.
9. Payment Method 1—For items of work for which lump sum prices are established in the contract, payment is made as the work proceeds, after presentation by the contractor of invoices showing related costs and evidence of charges by suppliers, subcontractors, and others for furnishing supplies and work performed. If the total of such payments is less than the lump sum contract price for this item, the remaining balance is included in the final contract payment. Payment of the lump sum contract price constitutes full compensation for completion of the work.
Payment is not made under this item for the purchase cost of material and equipment having a residual value.
Method 2—For items of work for which lump sum prices are established in the contract, payment is prorated and paid in equal amounts on each monthly estimate. The number of months used for prorating shall be the number estimated to complete the work. The final month's prorate amount is made with the final payment. Payment as described above constitutes full compensation for completion of the work.
Payment is not made under this item for the purchase cost of material and equipment having a residual value.
All methods—Compensation for any item of work described in the contract, but not listed in the bid schedule, is included in the payment for the item of work to which it is made subsidiary. Such items and the items to which they are made subsidiary are identified in section 10.
10. Items of work and construction details
Items of work to be performed in conformance with this specification and construction details are:
a. Bid Item 2, Contractor Quality Control
(1) This item shall consist of providing all equipment, materials, labor, and services necessary to ensure that the specified quality is maintained on all work performed during the contract.
(2) The contractor shall notify the Government’s Inspector prior to making quality control tests.
(3) Quality control tests shall be conducted in accordance with applicable ASTM specifications or WVDOH specifications, using equipment specified in the specifications.
(4) Method 1 of Sections 3 and 4 shall apply.
(5) Method 2 of Section 9 shall apply.
b. WVDOH Aggregate Base Course
(1) Certification Tests
The contractor shall provide typical test results for each required gradation of aggregate base course to be supplied showing that the aggregate meets the requirements of the specifications and drawings. The typical test results shall be attached to the Certification of Materials.
Aggregate delivered to the site shall be represented by typical test results and gradation test results which are less than nine months old at the time of delivery.
(2) On-site Tests
On-site tests will be conducted according to WVDOH Standards and Specifications Section 307, Crushed Aggregate Base Course.
c. WVDOH Marshall Hot-Mix Asphalt
The certification and on-site tests shall be conducted according with WVDOH Standards and Specifications Division 400 – Bituminous Pavements, Section 401.