Corvallis_IT_infrastructure_Upgrades..pdf
PDF 105 KB Posted
- Attached to
- IT Infrstructure Upgrade Corvallis, OR
- Solicitation number
- AG-32SD-S-17-0024
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions_during_the_site_survey_030717.pdf | ||
| ARS_Corvallis_-_Diagrams_032417.pdf | ||
| ARS_Corvallis_OR_Network_Infrastructure_Upgrade_SOW_Final_021717.pdf | ||
| SF18.pdf | ||
| ARS_Corvallis_SMF_Cable_Diagrams.pdf | ||
| ARS_Corvallis_Phase_1_BOM.pdf | ||
| OR42__Linn.txt | TXT text file | |
| OR22_Benton.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Will a Project Manager need to be onsite every day or can this individual work remotely?
It will be a mix, could be as much as a week or possibly one day a week per month.
2. Will all configurations be provided for new devices?
Yes you will be working in conjunction with ARS OCIO office.
3. What is the current maintenance window to perform network changes?
Changes will happen on a as needed basis.
4. What is the anticipated downtime for this migration?
Minimal downtime is anticipated.
5. Is there a document repository in place for Visio diagrams and configuration templates?
This will be created during the project.
6. Is all material per the BOM already onsite?
No
7. How long do you anticipate on-site support for the transition?
We anticipate this individual be on site for the period of performance even if the work completes early this will ensure a proper transition to the next phase contractor.
8. Is there already a proposed design, if so can we see a more detailed current state and proposed?
The proposed design is included in the Statement of work.
9. What is the proposed outcome as reference on page 6?
To replace wireless service that is currently provided by Oregon State University.
10. Has a High Level Diagram (HLD) been created?
Yes
11. Has a Low Level Diagram (LLD) been created?
12. Will logon credentials be provided to access existing network infrastructure?
13. Has a timeframe been determined yet for completion of project?
The period of performance will be June 1, 2017 – March 31, 2018.
14. How do you anticipate getting contractor clearances? Can contractors use clearance from previous government contracts?
Public trust basic level security clearance.
15. How much work space will be provided for contractor’s onsite?
Space to be determined if additional accommodations are required please specify.
16. Can most network configuration work be performed remotely via VPN?
17. Can you provide console access to all new network gear via a terminal so that staging can be done remotely? If there isn't one will the contractor be allowed to install one?
18. Will bid and performance bonds be required?