Spec 024100 Demolition
View the file
Other files for this federal contract opportunity
Show all 46
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
04-01-13
02 41 00 - 3
SECTION 02 41 00 DEMOLITION
PART 1 - GENERAL
DESCRIPTION:
This section specifies demolition and removal of buildings, utilities, pavements and concrete slabs, other structures and debris.
PROTECTION:
| Perform demolition in such manner as to eliminate hazards to persons and property; to minimize interference with use of adjacent areas, utilities and structures or interruption of use of such utilities; and to provide free passage to and from such adjacent areas of structures. |
| Provide safeguards, including warning signs, barricades, temporary fences, warning lights, and other similar items that are required for protection of all personnel during demolition and removal operations. |
| Maintain fences, barricades, lights, and other similar items around exposed excavations until such excavations have been completely filled. |
| Provide enclosed dust chutes with control gates from each floor to carry debris to truck beds and govern flow of material into truck. Provide overhead bridges of tight board or prefabricated metal construction at dust chutes to protect persons and property from falling debris. |
| Prevent spread of flying particles and dust. Sprinkle rubbish and debris with water to keep dust to a minimum. Do not use water if it results in hazardous or objectionable condition such as, but not limited to; ice, flooding, or pollution. |
| In addition to listed fire and safety rules to be observed in performance of work, include following: |
| No wall or part of wall shall be permitted to fall outwardly from structures. |
| Wherever a cutting torch or other equipment that might cause a fire is used, provide and maintain fire extinguishers nearby ready for immediate use. Instruct all possible users in use of fire extinguishers. Obtain a hot work permit. |
| Keep hydrants clear and accessible at all times. Prohibit debris from accumulating within a radius of 15 feet of fire hydrants. |
| Before beginning any demolition work, the Contractor shall survey the site and examine the drawings and specifications to determine the extent of the work. The contractor shall take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government; any damaged items shall be repaired or replaced as approved by the Contracting Officer. The Contractor shall coordinate the work of this section with all other work and shall construct and maintain shoring, bracing, and supports as required. The Contractor shall ensure that structural elements are not overloaded and shall be responsible for increasing structural supports or adding new supports as may be required as a result of any cutting, removal, or demolition work performed under this contract. Do not overload structural elements. Provide new supports and reinforcement for existing construction weakened by demolition or removal works. Repairs, reinforcement, or structural replacement must have Contracting Officer’s approval. |
UTILITY SERVICES:
| Demolish and remove outside utility service lines shown to be removed. |
| Remove abandoned outside utility lines. |
PART 2 - PRODUCTS (NOT USED) PART 3 – EXECUTION
DEMOLITION:
Completely demolish, remove and dispose of buildings entirely including structures, foundations, utilities, equipment, furnishings and all appurtenances related or connected thereto, to full depth within five feet of the existing facility to be demolished.
Debris, including brick, concrete, stone, metals and similar materials shall become property of Contractor and shall be disposed of daily, off Government property to avoid accumulation at the demolition site. Materials that cannot be removed daily shall be stored in areas specified by the Contracting officer.
Remove existing utilities as indicated or uncovered by work and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the Contracting Officer. When utility lines are encountered that are not indicated on the drawings, the Contracting Officer shall be notified prior to further work in that area.
CLEAN-UP:
On completion of work of this section and after removal of all debris, leave site in clean condition. Clean-up shall include off Government property disposal of all items and materials not required to remain property of the Government as well as all debris and rubbish resulting from demolition operations.
- - - E N D - - -