United States Department of Agriculture
Research, Education, and Economics Agricultural Research Service
Eastern Business Service Center, Acquisition Branch 1815 North University Street
Peoria, IL 61604-3902 USDA is an Equal Opportunity Provider and Employer
AG-32SC-S-16-0046 Demo 15 Bldgs, BARC, Beltsville, MD Amendment 003 – Questions & Answers II – 7SEP16
7. Due to the spread out nature of this project, can the recycle 60% and the landfill diversion spec be disregarded? Most worthwhile items have already been removed.
A. No.
8. Who is responsible for the demo permit and SEC plan/implementation?
A. The contractor.
9. Is there a suitable borrow area on site as alluded to in the spec?
A. No, Specification 31 20-11.3.2.D indicates “D. Borrow Material: Borrow material shall be from a site off of Government property.”
10. What about the additional HazMats not listed/quantified in the reports (mostly chemicals)?
A. Make your proposal based on the quantities described in the contract documents.
11. The spec lists who is responsible for marking the utilities but who is cutting and capping them (quantity??)?
A. Specification 02 41 00.3.1.C indicates “C. Remove existing utilities as indicated or uncovered by work and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the Contracting Officer.”
12. Does the bridge near the antenna array have a weight limit?
A. Specification 01010.1.7.C indicates “C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer.” If the contractor desires to use unusually heavy equipment, temporary roads may be considered for approval by the Contracting Officer.”
13. When will the 180 days start? After the proper paperwork/environmental? For example there was some question as to whether or not you have the required generator EPA ID #.
A. Upon receipt of the Notice to Proceed.
14. Will the sites be released all at once?
A. Yes.
END of Questions & Answers