AG-2B46-S-17-0010

CONCORDE RESTORATION SERVICE

PREVIOUS RECEIVED QUESTIONS & ANSWERS

ADDITIONAL QUESTIONS:

1. The contract specifications indicated 149 work days during the period of June – October as the period of performance. The solicitation SF 1442 in line 11 states 510 calendar days from notice to proceed. What is the actual period of performance for this project? Please clarify.

A. Actual performance days are 149. Refer to Sec F, clause 4I 52.249-70 severe weather days which are estimated non-work time frames.

Contractual completion time is 510 days.

2. The contract specifications indicated 149 work days during the period of June – October as the period of performance. Weather permitting can the contractor work in the other months outside of the June – October performance period?

A. Yes if preapproved from NRCS.

3. What is the value to of the bid bond?

A. Refer to the bid bond form; instructions. By law it is the minimum of 20% of bid price.