Questions-Answers1.pdf
PDF 683 KB Posted
- Attached to
- Bridge Remove/Repair/Replace - Hoonah, AK Federal contract opportunity
- Solicitation number
- AG-0109-S-17-0005
About this file
Responses to Questions
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| QUESTIONS_AND_ANSWERS-3.pdf | ||
| Questions-Answers_AmendedSpec.pdf | ||
| Attachment-3_LoadRatingRequirement.pdf | ||
| Amendment_01.pdf | ||
| Questions-Answers1.pdf | ||
| Attachment-1_2017_Hoonah_Bridges_Signed_170222.pdf | ||
| Attachment-2_Hoonah_Bridges_SuppSpecs.pdf | ||
| AG-0109-S-17-0005_HoonahBridges.pdf | ||
| Attachment-4_WageDeterminationAK7.pdf | ||
| Attachment-5_Past_Performance_Worksheet.docx | DOCX document | |
| DRAFT_HoonahBridges_Drawings.pdf | ||
| DRAFT_Hoonah_Bridges_SupplementalSpecs_170201.pdf | ||
| DRAFT_StatementOfWork_HoonahBridges_170201.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AG-0109-S-17-0005
BRIDGE REMOVE/REPAIR/REPLACE – HOONAH, ALASKA
QUESTIONS AND ANSWERS #1
March 26, 2017
Q1. At Rowan Bay are the bridges right there to grab or do we need to transport them?? What is the landing like there? Is there a dock? Is there a nice beach to land on with a Barge? Can I get pictures of facility?
A1. There is a low angle ramp, dock, and LTF at Rowan Bay. The dock is approx. ¼ mile from the ramp. The bridges are stored near the ramp. Ramp and float pictures attached.
Rowan Bay Float
Rowan Bay LTF
Q2. The 2 bridges we build in the field as long as they meet specs - all good?
A2. This question is unclear, but any bridges installed in performance of this contract must meet contract specifications.
Q3. Can we use Forest Service Cabin in Freshwater Bay once we get that far into wilderness?
A3. The Forest Service will not provide government housing for contractor use as part of contract terms.
Q4. Can we land certain equipment at Freshwater Bay as needed to complete the job?
A4. Yes, a sheet pile bulkhead and barge loading ramp are available at Freshwater Bay.
Q5. Would there be dismemberment of funds as we went to keep the project funded all the way through completion?
A5. Assuming you mean “disbursement of funds”, progress payments are allowed in accordance with the Payments Clause included in the solicitation. See Section I (52.232-5
Payments under Fixed-Price Construction Contracts – full text is available at www.acquisition.gov/far.
Q6. Are you planning on this year for this project??
A6. No. Period of performance for the base is from contract award through September 30, 2018. Awarding of Options will extend the period of performance for 60 days. See Section
F.1 and H.16 for project completion requirements. Also see Section H.4 for restrictions on in stream work.