Draft Statement of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| QUESTIONS_AND_ANSWERS-3.pdf | ||
| Questions-Answers_AmendedSpec.pdf | ||
| Attachment-3_LoadRatingRequirement.pdf | ||
| Amendment_01.pdf | ||
| Questions-Answers1.pdf | ||
| Questions-Answers1.pdf | ||
| Attachment-4_WageDeterminationAK7.pdf | ||
| Attachment-5_Past_Performance_Worksheet.docx | DOCX document | |
| AG-0109-S-17-0005_HoonahBridges.pdf | ||
| Attachment-1_2017_Hoonah_Bridges_Signed_170222.pdf | ||
| Attachment-2_Hoonah_Bridges_SuppSpecs.pdf | ||
| DRAFT_Hoonah_Bridges_SupplementalSpecs_170201.pdf | ||
| DRAFT_HoonahBridges_Drawings.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAFT
C.1 PROJECT SCOPE
A. Description: The intent of this contract is to remove, repair and replace existing bridges, guardrails, approach railings, and perform routine road maintenance located on National
Forest System Roads on Chichagof Island near Hoonah, Alaska. Contractors are encouraged to visit the work sites to review conditions. Pay particular attention to section H.4 Submittals, Material Certifications and Testing Reports for list of required submittals. This work includes:
Table One - Synopsis of work sites
Road # Milepost Existing
Structure
Replacement
Structure
Gov’t or
Contractor
Furnished
Present
Location of
Replacement
Approach
Rails
Required
8502 5.784 70’ modular
Reinstall same bridge Gov’t
8502 MP
5.784
Yes –
Contractor furnished
8504 0.156 40’ log stringer
40’ Hamilton
EZ bridge
Gov’t (Cont.
furnish substructure)
Rowan Bay No
8504 0.360 40’ log stringer
40’ glulam slab Gov’t Rowan Bay No
8504 0.439 55’ log stringer 80’ glulam Gov’t
Road 85304
MP 2.141
No
8508 6.802 30’ modular
40’ glulam slab Gov’t Rowan Bay
Yes –
Contractor furnished
8509 0.170 60’ modular 90’ glulam Gov’t
8530 MP
11.128 No
8530 11.128 90’ glulam
102’ welded girder Contractor New
Yes –
Contractor furnished
85082 0.436 56’ log stringer 70’ modular Contractor New No
85304 2.141 80’ glulam
90’ welded girder Contractor New
Yes –
Contractor furnished
AG-0109-S-17-0005
Table Two – Base Bid and Options
Base Bid Option One Option Two
Road # Milepost Road # Milepost Road # Milepost
8502 5.784 8509 0.170 85082 0.436
8504 0.156 8530 11.128
8504 0.360
8504 0.439
8508 6.802
85304 2.141
A total of nine bridges are to be installed. This includes three new contractor furnished bridges and six government furnished bridges. Government furnished bridges come from a variety of sources. Two are installed on the Hoonah road system and are to be relocated to new locations, three are in Rowan Bay, one is to be removed and installed in the same location.
Transporting three government furnished bridges from the Rowan Bay Marine
Access Facility on Kuiu Island to their respective installation sites on the Hoonah road system.
Removing two modular bridges from their current installation sites and transporting for storage to a rock pit on road 8508 at milepost 7.922. Installing replacement bridges at these sites.
Removing four log stringer bridges and installing replacement bridges at these sites.
See Table One for replacement structures.
Removing a 70’ modular (Big R) bridge, reconstructing installation site and reinstalling same bridge.
Removing an 83’ glulam bridge on road #85304 at MP 2.141. Transport to its new installation site on road #8504 at MP 0.439. Furnish, deliver and install new 90’ bridge with transverse beams, all Thrie beam guardrail, transition rails, approach rails, longitudinal treated timber decking, longitudinal untreated wearing surface, backwalls, concrete abutments, object markers, and reflectors.
Removing a 90’ glulam bridge on road #8530 at MP 11.128. Transport to its new installation site on road #8509 at MP 0.170. Furnish and install new 102’ bridge with transverse beams, all Thrie beam guardrail, transition rails, approach rails, longitudinal treated timber decking, longitudinal untreated wearing surface, backwalls, concrete abutments, object markers, and reflectors.
Perform all work necessary for the placement and installation of each of the bridges at their respective locations. Installation work to include but not limited to the following: Remove and dispose of existing embankment soil material, supply and prepare material including various sized fill rock and rip rap for all necessary embankment construction and approach roadway grading, properly install all substructure elements including standard spread footing, pre cast concrete abutments and bridge backwalls, place and connect bridge elements in their proper fashion and location, and grade approach roads to match new bridge elevations. Furnish and install four (4) object markers and posts at bridge ends.
Bridges that are dismantled by the contractor and reused in this contract shall have all bridge pieces and hardware inventoried. Any damaged or missing items shall be replaced by the contractor, no additional payment will be made.
Supply and install all components necessary to construct approach rail system in accordance with all relevant specification standards listed in section C.2 of this document. Approach rail system to include, but not limited to: steel approach rail, timber rail posts, transition rail connection to bridge rail, and all connection and standard safety materials. See design documents for all specific construction details.
See Table One for list of bridges requiring approach rails. Approach rail systems are incidental to contractor furnished bridges.
Install four (4) object markers and posts at bridge ends. All signage to be installed per design documents and relevant specification standards listed in section C.2 of this document.
Bridge sites may only be closed to public during times in which the contractor is physically on site performing work and shall remain open at all times when contractor IS NOT on site. Contractor MUST notify COR a minimum of 7 days before anticipation of road closures, and public notifications will be posted as stated in C.3. Contractor is limited to a two week maximum road closure at any one site.
The Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies to perform all work listed on the schedule of items, specifications and drawings.
Refer to drawings for complete and detailed description of work.
Payment will be made only for those items listed on Bid Schedule. All other work is incidental to those pay items.
B. Location: Hoonah, Alaska is located on Chichagof Island, approximately 40 air miles west of Juneau. All sites for this project are located on the main Hoonah road system.
Hoonah is a full service community, with daily commercial air service and air taxi services and regularly scheduled ferry and commercial barge services. See vicinity map for road and bridge site locations.
C. Rock source locations can be found at:
ROAD NUMBER MILEPOST
8508 0.23
8508 5.01
ROAD NUMBER MILEPOST
8508 7.20
8508 7.92
8508 10.45
8530 11.79
8533 0.37
85026 0.73
85026 0.00
85304 0.81
8508_12.86R 0.09
8508_9.23L 0.05
8531_0.61R 0.06
D. Waste to be disposed at designated waste sites, determined by CO/COR.
E. Price range for this project is between $1,000,000 and $5,000,000.
C.2 SPECIFICATIONS
The following specifications are included by reference. The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract.
D.O.T. FHA STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS
AND BRIDGES ON FEDERAL HIGHWAY PROJECTS FP-03 U.S. Customary Units
BEST MANAGEMENT PRACTICES BMP’S Soil and Water Conservation Handbook
FSH 2509.22 and NATIONAL BEST MANAGEMENT PRACTICES for WATER
QUALITY MANAGEMENT ON NATIONAL FOREST SYTEM LANDS FS-990
Manual on Uniform Traffic Control Devices (MUTCD)
USDA FOREST SERVICE – Sign Installation Guide 0371-2812 MTDC
FLH Standard Specifications (FP-03) can be obtained from the Federal Highway
Administration Home Page on the Internet. It is in Word or Adobe Acrobat page description format at: http://flh.fhwa.dot.gov/resources/specs/fp-03.htm; or online at:
http://bookstore.gpo.gov/
The BMP Soil and Water Conservation Handbook, FSH 2509.22 can be found at:
http://www.fs.usda.gov/detail/r10/landmanagement/?cid=fsbdev2_038796
And the National BMP Handbook can be found at:
http://www.fs.fed.us/biology/resources/pubs/watershed/FS_National_Core_BMPs_April2012.p df http://flh.fhwa.dot.gov/resources/specs/fp-03.htm http://bookstore.gpo.gov/ http://www.fs.usda.gov/detail/r10/landmanagement/?cid=fsbdev2_038796 http://www.fs.fed.us/biology/resources/pubs/watershed/FS_National_Core_BMPs_April2012.pdf http://www.fs.fed.us/biology/resources/pubs/watershed/FS_National_Core_BMPs_April2012.pdf
The MUTCD can be obtained from the Federal Highway Administration Home Page on the
Internet. It is in HTML or PDF page description format at:http://mutcd.fhwa.dot.gov/
Or hard copies are available for purchase online at:http://bookstore.gpo.gov/
The USDA Forest Service – Sign Installation Guide is included by reference. The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract The Forest Service Sign Installation guide can be obtained upon request.
C.3 SAFETY AND PUBLIC NOTIFICATION
Warning signs will be placed at the proper locations to warn the public of road work. All signs shall meet the minimum requirements as established by the Manual of Uniform Traffic Control
Devices (MUTCD), 2003 edition. The contractor shall post a notice of where and when the public might expect delays due to project work at several publicly located bulletin boards in
Hoonah.
C.4 DAMAGE TO STRUCTURES
The Contractor shall be held liable for any damage caused by his/her personnel or equipment to any existing bridges, ditches, culverts, signs, or riprap at culvert inverts. Repair of structures damaged by the Contractor's operations, shall be the Contractor's responsibility at no cost to the
Government.
C.5 AGAR 452.211-72 Statement of Work/Specifications (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities
(except as otherwise specified), to perform the Statement of Work/Specifications referenced in
Section J.
C.6 AGAR 452.211-73 ATTACHMENTS TO STATEMENT OF
WORK/SPECIFICATIONS (FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
C.7 SPECIAL PROJECT SPECIFICATIONS AND FOREST SERVICE
SUPPLEMENTATIONS
The following specifications and supplementations to FP-03 are hereby made part of this solicitation and any resultant contract:
101 - Terms, Format, and Definitions
102 - Bid, Award, and Execution of Contract
103 - Scope of Work
104 - Control of Work
105 - Control of Material http://bookstore.gpo.gov/
106 - Acceptance of Work
107 - Legal Relations and Responsibility to the Public
108 - Prosecution and Progress
109 - Measurement and Payment
152 - Construction Survey and Staking
153 - Contractor Quality Control
155 - Schedules for Construction Contracts
157 - Soil Erosion Control
171 - Weed and Disease Prevention
201 - Clearing and Grubbing
202 - Additional Clearing and Grubbing
203 - Removal of Structures and Obstructions
204 - Excavation and Embankment
205 - Rock Blasting
209 - Structure Excavation and Backfill
251 - Riprap
301 - Untreated Aggregate Courses
30311(01) - Blading
552 - Structural Concrete
553 - Prestressed Concrete
555 - Steel Structures
556 - Bridge Railing
557 - Timber Structures
563 - Painting
571 - Prefabricated Bridges
625 - Turf Establishment
651 - Development of Pits & Quarries
703 - Aggregate
718 - Traffic Signing and Marking Material
861 – Maintenance of Bridge Surface
SPECIAL NOTE: The above is a list of major specifications applicable to this contract. Other specifications referred to within these specifications (even though not specifically listed) are also fully applicable to the solicitation and any resultant contract.
Submittals, Material Certifications and Testing Reports
In addition to the items listed below reference FP-03 and the FSSS for all the required submittals, material certifications and/or testing reports that shall be submitted for this project.
Submittal Title Referenced By
Specification No.
Submittal Date
Schedule of Work Prior to Work Starting
Job Specific Safety Plan Prior to Work Starting
Notification of Subcontracting Prior to Subcontractor Starting Work
Quality Control Plan FP-03 153.02 Prior to Work Starting
Erosion Control Plan FSSS 157 14 days prior to Construction
AISC Certification for IBR (internediate steel bridges)
FP-03 555.03 Prior to bridge order
Welding ANSI/AWS Code D1.5 FP-03 555.03 Prior to bridge order
Steel fabrication/erection drawings FP-03 555.06,
104.03 (b)
30 days prior to construction
Shipping plans FP-03 555.06 Prior to shipment from fabrication plant
Galvanizing plant certification FP-03 555.05, 106.03, 717.07
Prior to galvanizing
Material Certifications and Testing
Reports
FSSS 553, 554,
555, 556, 557, 571, 573, 601 &
703.05. FP-03
555.05
30 days prior to construction
Wood grade/treatment FP-03 555.06, 106.03, 557.19, 557.04, 716.04
30 days prior to construction
Hardware material certifications FP-03 717.01, 106.03
30 days prior to construction
Shop drawings bridge & guardrail FP-03 555.06, 556.10
30 days prior to construction
Shop drawings bearing pad assemblies FP-03 564.03, 717.10
30 days prior to construction
As built drawings/manufacturer’s data sheets
NA 30 days after construction
CREEK CROSSINGS: Schedule and conduct bridge and instream work to minimize disturbance to streams.
Road Number Milepost
Instream Work Timing
8502 5.784 June 15-July 15
8504 0.156 June 01-July 15
8504 0.360 June 01-July 15
8504 0.439 June 01-July 15
Road Number Milepost
Instream Work Timing
8508 6.802 June 01-Sept 01
8509 0.170 June 01-Sept 01
8530 11.128 June 01-July 15
85082 0.436 June 15-Sept 01
85304 2.141 June 15-July 15
1. Do not cross streams without Contracting Officer approval.
2. Submit a written equipment crossing plan to the Contracting Officer for approval 14 calendar days before creek crossing is planned. Two machine crossings will be permitted for all streams designated on the drawings as fish streams or listed in the above table.
Outside of this time period, no machine crossings will be permitted if fish eggs are present in the gravel or adult fish are present in the stream; otherwise two machine crossings will be permitted.
3. Limit machine crossings to two times for all live streams not designated on the drawings as fish streams with pipes 48” and larger to be installed.
4. Do not leave temporary bridges in place between September 15 and March 15, unless approved in advance in writing by the Contracting Officer.
In stream work will only be allowed only at low flows.
Obtain necessary permits for floating camps, floats, shore ramps, and other appurtenances associated with project operations from the following State of Alaska and Federal Agencies:
1. ADNR – Alaska Department of Natural Resources.
2. ADEC – Alaska Department of Environmental Conservation.
3. ADGC – Alaska Department of Governmental Coordination.
4. EPA – US Environmental Protection Agency.
5. DA, COE – US Army Corps of Engineers.
6. USCG – US Coast Guard.