Advantor Upgrade for Program Office Work.docx
DOCX document 14 KB Posted
- Attached to
- Advantor Upgrades @ DTOC
- Solicitation number
- W50S71-20-Q-8038
- Issued by
-
Department of the Army National Guard
View the file
Other files
| File | Type | Posted |
|---|---|---|
| JandA 20-005 Advantor for DTOC Combined Buys - open market.pdf | ||
| Soliciation W50S71-20-Q-8038 Advantor - open market.pdf | ||
| Advantor Upgrade for Open Storage Work.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Advantor Upgrade for Program Office
Access Control Refresh
· Upgrade SF/Xi to SF/Xi6.2 with badging, including new report printer, badging printer, switch and
· firewall.
· Upgrade panels 5001, 5002 & 5003 to IG2 FIPS panels.
· Remove Main Entry 140 from 5002 and cap with plate.
· Remove ECC 1 Rm 131 from 5003 and cap with plate.
· Replace all existing card readers (now Prox/Pro) with HID RPK40 readers.
IDS Refresh
· Upgrade IDS panels in Program Office area with IG2 FIPS panels.
· Provide and install ITK keypads to replace TSK Keypads (2 total).
· Replace all motion sensors with AP669 sensors.
· Replace perimeter BMS with HSS
· Perform turnkey installation of all components, including all necessary conduit and wiring.
· Wire above ceilings will be installed on J-hooks or in cable trays.
· Wire below ceilings will be in EMT Conduit.
· Conduct Contractor Verification Testing and commission system into service.
· Provide software instruction on SF/Xi6 system, including enrollment, schedule set up and system administration.
· Provide as-built drawings of final configuration, including device placement and wire paths.
The Government will provide the following collateral support:
· Provide storage and staging space for project materials.
· Provide access to work areas in conformance with pre-arranged installation schedule.
· Provide AutoCAD floor plans as necessary for creation of as-built drawing.
· Provide access to 120VAC power for all components requiring AC Power (Advantor to perform power connections.)
· *All electrical work to be performed by a licensed electrician