This is Construction Bid Addendum No. 3 issued by the Michigan Department of Technology, Management and Budget (DTMB), State Facilities Administration Design & Construction Division for the Petobego Dam Removal project in Grand Traverse County. The addendum, issued on August 14, 2026, clarifies bidding documents and incorporates modifications and interpretations into the contract. The bid opening date remains unchanged at August 19, 2026. The project, identified as File Number 751/22040.BDW, is being managed by the Professional Spicer Group with Project Director Bruce Watkins, P.E., and approved by Warren Miller, P.E. The addendum includes responses to fourteen contractor questions and attaches historical drawings related to the project. Key clarifications address permit responsibilities, construction staking requirements, tree removal protocols, restoration specifications, equipment access, biodegradable hydraulic oil requirements, and streambed aggregate specifications.

The addendum establishes that Spicer Group is responsible for obtaining the EGLE WRD permit while the contractor is responsible for their portion of the DTMB SESC permit and the MDOT ROW permit. Spicer Group will provide construction staking, eliminating the need for a separate surveyor hire. Tree and shrub removal is required within specified limits of disturbance but without a defined list, and no live stakes will be installed despite initial specification language. Restoration requirements specify the use of coir/jute netting within channels and areas steeper than 2H:1V slopes, with mulch acceptable in areas outside designated restoration zones. Equipment working in the stream must use biodegradable hydraulic oil, and streambed aggregate must consist of materials ranging from 3/8 inch to 2 inches with a median grain size of 1 inch, rather than standard 10A drain stone.

View the file

Other files

File Type Posted
Addendum_1_22040.pdf PDF
Service Disabled Veteran Owned Business Info Sheet 2025.pdf PDF
Specs_22040.pdf PDF
Plans2_22040.pdf PDF
Plans1_22040.pdf PDF
Addendum_2_22040.pdf PDF
Advertisement_22040.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 (Rev 6/25)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND

BUDGET

State Facilities Administration Design & Construction Division

CONSTRUCTION BID ADDENDUM NO. 3

This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.

TO:

ALL BIDDERS

DATE ISSUED

8/14/2026

PROJECT NAME

Petobego Dam Removal / Grand Traverse County

FILE NUMBER

751/22040.BDW

PROFESSIONAL

Spicer Group

PROJECT DIRECTOR

Bruce Watkins, P.E.

BID OPENING DATE:

8/19/2026

ADDENDUM ITEMS: (attach additional sheets and drawings if required)

ITEM 1: Bid Opening Date is unchanged and remains as 8/19/2026.

ITEM 2: Additional Questions/Answers (attached).

ACKNOWLEDGEMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.

PROFESSIONAL: Warren Miller. P.E. DATE: 8/14/2026

APPROVED BY:

PROJECT DIRECTOR: Bruce Watkins, P.E. DATE: 8/14/2026

ITEM 3: Historic Drawings (attached).

http://www.michigan.gov/SIGMAVSS

QUESTIONS/ANSWERS AS OF 8/14/2026

1. Question: Section 00120, 2 states “If the Owner has secured any permits” please clarify who is responsible for securing the three (3) permits listed in this section.

Answer: Spicer Group is responsible for obtaining the EGLE WRD permit. The contractor is responsible for their portion of the DTMB SESC permit and obtaining the MDOT ROW permit.

2. Question: Is the contractor required to hire a registered land surveyor for the staking and Site Layout Drawings? If so, where is the work paid under?

Answer: Spicer Group will provide construction staking.

3. Question: Section 31 10 00, 3.4, C states “remove trees and shrubs indicated.

Remove stumps, main root ball, surface rock, and as indicated on the plans”. Can these trees be shown on the drawings, with a quantity and dbh?

Answer: Remove trees and shrubs within the specified limits of disturbance as needed to perform the work. There is not a list of trees to be removed.

4. Question: Will tree removal be required to be completed outside the bat roost, or has there been a survey performed?

Answer Special tree-cutting time windows related to bat roosting are not anticipated.

5. Question: Section 31 25 00, 2, 2.2, C requires live stakes, but none are shown on the drawings, please clarify if they are part of the scope. If so, provide species, quantity and planting plan.

Answer: There will not be any live stakes installed for this project.

6. Question: Will the coir/jute blanket be required for all restoration or just as shown on the drawings? Is mulch acceptable in areas restored outside the areas shown on the drawings.

Answer: Use coir/jute net within the channel and any other areas that 2H:1V or steeper.

7. Question: There is conflicting language on how the access road is to be restored, can you please clarify expectations for the final conditions for restoration (gravel re-established v. topsoil, seed, mulch road)?

Answer: Addendum No. 2 addresses the access road question.

8. Question: The limits of disturbance/snow fence is drawn at 15’ wide. Are we able to clear that area as needed to get equipment in?

Answer: Trees may be removed within the disturbance limits.

9. Question: What is the flow we have to maintain?

Answer: Addendum No. 2 addresses this question.

10. Question: How long are the sheet piles?

Historical plans (attached) show the sheet pile length as 6 feet.

11. Question: How many stop longs can we take oƯ to reduce the upstream water height?

Answer: All stop logs can be removed. Refer to the General Timing and Sequencing notes on Sheet 3.

12. Question: Do we need to use biodegradable hydraulic oil?

Answer: Yes, biodegradable hydraulic oil will be required for equipment working in the stream.

13. Question: In the general timing & sequence page it refers to a shoreline construction detail on sheet 6. I don’t see that detail.

Answer: The detail is shown below:

14. Question: Can we use 10A Drain stone for the rounded aggregate for stream channel?

Answer: The streambed aggregate should have more variability than the 10A aggregate (3/8 inch to 2 inches) and should have a median grain size of 1 inch.

A5185226
A5185227
A5185228
A5185229