A06_Aluminum_Handrails.docx
DOCX document 30 KB Posted
- Attached to
- MN FERGUS FALLS WMD HANDRAIL STAIRS
- Solicitation number
- 140FF027Q0027
- Issued by
- Not on record
About this file
This is a specifications document for selective demolition and removal work on exterior second-level deck handrailing and steel staircase components. The work encompasses removal of all handrail elements including posts, balusters, top and bottom rails, brackets, and fasteners; complete steel staircase assembly removal including stringers, treads, landing platform, posts, and anchorage hardware; and restoration of affected surfaces. The contractor must provide temporary fall protection during demolition, mechanical lifting equipment for safe stair assembly removal, grinding and sanding tools, and exterior-grade wood filler and corrosion-resistant sealant for patching. Work requires inspection of existing conditions prior to demolition, notification to the Owner of any concealed structural deterioration discovered, and sealing of exposed fastener holes with corrosion-resistant sealant. The contractor is responsible for protecting adjacent structures, siding, windows, doors, and landscaping from damage; maintaining safe working conditions in compliance with OSHA 29 CFR 1926; and daily debris removal with site cleanup to broom-clean condition upon completion. Steel components should be recycled when feasible, and all disposal must comply with local regulations. Coordination with the Owner is required for access and safety during demolition operations, and all work must be documented with written confirmation of component removal and photographs of connection points after removal.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A06_Prefabricated_Steel_Stair_System.docx | DOCX document | |
| Sol_140FF027Q0027.pdf | ||
| A06_Submittal_Register.docx | DOCX document | |
| A05_Statement_of_work.docx | DOCX document | |
| A06_Project_Coordination.docx | DOCX document | |
| A06_Drawings.pdf | ||
| A06_Definitions_and_Standards.docx | DOCX document | |
| B03_Wage_Determination.pdf | ||
| A06_Submittals.docx | DOCX document | |
| A06_Closeout.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DIVISION 5 SECTION 05730
METALS ALUMINUM HANDRILS
PART 1 – GENERAL
1.1 SUMMARY
· Work includes selective demolition and removal of the existing exterior second‑level deck handrailing and steel staircase.
· Work includes protection of adjacent structures, restoration of affected surfaces, disposal of removed materials, and required documentation.
1.2 REFERENCES
· OSHA 29 CFR 1926 – Safety and Health Regulations for Construction.
· Local building codes, latest adopted edition.
1.3 SUBMITTALS
· Written confirmation that all specified components have been removed.
· Photographs documenting deck and stair connection points after removal.
· Written report of concealed structural deterioration discovered during demolition, if any.
1.4 SITE PROTECTION AND CONDITIONS
· Protect adjacent structures, siding, windows, doors, and landscaping from damage
· Maintain safe working conditions and provide temporary fall protection when railings or stairs are removed.
· Contractor shall provide all necessary labor, tools, equipment, and safety measures.
1.5 COORDINATION
· Coordinate with Owner for access and safety during demolition operations.
· Verify existing conditions before beginning removal work.
PART 2 – PRODUCTS
2.1 MATERIALS
• Exterior‑grade wood filler for patching deck fastener holes
• Corrosion‑resistant sealant for exposed metal fastener holes
2.2 EQUIPMENT
· Mechanical lifting equipment suitable for safe removal of steel stair assembly.
· Grinding and sanding tools for smoothing edges and remaining attachment surfaces
PART 3 – EXECUTION
3.1 PREPARATION
· Inspect existing deck and stair assembly prior to demolition.
· Install temporary fall protection prior to removing railings or stair components.
3.2 HANDRAILING REMOVAL
· Remove all handrail components: posts, balusters, top and bottom rails, brackets, and fasteners.
· Cut or extract fasteners flush with deck framing.
· Grind or sand any sharp or protruding edges created during removal.
· Do not cut or damage structural members during removal.
· Remove and dispose of handrailing materials per Section 3.6
3.3 STEEL STAIRCASE REMOVAL
· Remove full stair assembly: stringers, treads, landing platform (if present), posts, and anchorage hardware.
· Use mechanical lifting equipment where needed for safe removal.
· Remove anchor bolts, lag screws, weld plates, and brackets.
· Grind or patch remaining weld tabs, plates, and attachments flush.
· Install temporary fall protection immediately following removal.
3.4 STRUCTURAL INTERFACE PROTECTION
· Inspect rim joist, ledger, and adjacent framing for damage.
· Notify Owner if any concealed deterioration encountered.
· Seal exposed fastener holes with corrosion‑resistant sealant.
· Maintain temporary barriers at deck edges until further construction is completed.
3.5 SURFACE RESTORATION
· Fill wood fastener holes with exterior‑grade filler unless otherwise directed.
· Grind concrete or steel surfaces smooth where anchors or plates were removed.
· Clean area of debris, dust, and metal shavings.
3.6 DISPOSAL AND CLEANUP
• Remove demolition debris from site daily
• Recycle steel components when feasible
• Dispose of non‑recyclable materials per local regulations
• Leave site broom‑clean upon completion
05500-1