This project specification document and related solicitation are for replacing the domestic water distribution system and reconstructing roads at the Jenny Lake Campground in Grand Teton National Park. The specification covers upgrading piping to HDPE and abandoning existing lines to minimize disturbance, placing empty conduit for future electrical work, and fully reclaiming and repaving road surfaces. Work will be conducted in one phase under a single prime contract awarded by the National Park Service Intermountain Region. The contractor must follow standards for historic property treatment and mitigate impacts to archaeological resources, night skies, and protected wildlife. Construction must minimize soil and vegetation impacts, control dust and noise, and include revegetation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_2_Jenny_Lake_Campground_Section_26_05_43_0002.pdf | ||
| Sol_140P1423R0027_Amd_0002.pdf | ||
| Amendment_2_Site_Visit_Sign_In_Sheet_0002.pdf | ||
| Amendment_2_Questions_and_Answers_0002.docx | DOCX document | |
| Sol_140P1423R0027_Amd_0001.pdf | ||
| Amendment_1_Site_Visit_Map_0001.pdf | ||
| B08_40620388_Attachment_5_Limitation_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| B08_40620388_Attachment_3_General_References.pdf | ||
| B03_40620388_Teton_County_Heavy_WY2023033_01062023.pdf | ||
| B08_40620388_Attachment_2_Project_Experience_Form.docx | DOCX document | |
| B08_40620388_Attachment_1_Contract_Admin.docx | DOCX document | |
| Sol_140P1423R0027.pdf | ||
| A06_40620388_Jenny_Lake_Campground_Final_Stamped_Plans_04-26-2023.pdf | ||
| B08_40620388_Attachment_4_Past_Performance_Questionnaire.docx | DOCX document |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GRAND TETON NATIONAL PARK
JENNY LAKE CAMPGROUND
GRTE
PMIS NO. 240717
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
INTERMOUNTAIN REGION
April 2023
04.26.2023
GRTE - 240717 TOC-1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work
01 26 01 Contract Modification Procedures
01 27 00 Definition of Contract Line Items
01 31 00 Project Management & Coordination
01 32 16 Construction Schedule
01 33 23 Submittal Procedures
01 35 13.22 Archeological Protection
01 35 23 Safety Requirements
01 40 00 Quality Requirements
01 42 00 Reference Standards
01 50 00 Temporary Facilities and Controls
01 57 19.12 Noise & Acoustics Management
01 57 23 Temporary Storm Water Pollution Prevention
01 67 00 Product Requirements
01 73 40 Execution
01 74 19 Construction Waste Management and Disposal
01 77 00 Closeout Procedures
01 78 23 Operation and Maintenance Data
DIVISION 02 – SITE WORK
02 01 00 Maintenance of Existing Conditions
02 41 00 Demolition and Salvage
DIVISION 03 – CONCRETE
03 20 10 Site Reinforcing Steel
03 31 00 Concrete for Site Structures
03 35 00 Concrete Sidewalks
DIVISION 10 – SPECIALTIES
10 14 53 Traffic Signage
GRTE - 240717 TOC-2
DIVISION 26 – ELECTRICAL
26 05 43 Underground Ducts and Raceways for Electrical Systems
DIVISION 31 – EARTHWORK
31 00 00 Earthwork
31 05 25 Utility Line Marking
31 11 00 Clearing and Grubbing
31 11 01 Rock Excavation
31 14 00 Earth Stripping and Stockpiling
31 23 21 Dewatering
31 27 00 Aggregate Base
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 00 00 Tree Protection
32 01 16 Milling of Asphalt Pavement
32 11 26 Asphalt Base Course
32 12 16 Asphalt Concrete Pavement
32 13 73 Concrete Paving Joint Sealants
32 17 23 Pavement Markings
32 17 26 Detectable Warning Panels
32 33 00 Landscaping and Site Furnishings
32 91 19 Topsoil
32 92 20 Seeding
DIVISION 33 – UTILITIES
33 12 13 Water Distribution Systems
33 31 23 Fusible High-Density Polyethylene (HDPE) Pipe & Fittings
GRTE - 240717 01 11 00 - 1
051121 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. Work Phases
3. Work Under Other Contracts
4. Government-Furnished Materials
5. Contractor Use of Site
6. Public Use of Site
7. Conduct of Operations
8. Work Restrictions
9. NPS Standard Mitigations and Stipulations Attachment
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Grand Teton National Park, Jenny Lake Campground, Teton Park Road, Moose, WY 83012.
B. Jenny Lake is one of the most popular visitor areas within the park. The Jenny Lake campground is a small, but important campground within Grand Teton National Park. Work for this project consists of:
1. Upgrading and replacing the domestic water distribution network throughout the Jenny
Lake Campground. The water system construction will utilize open-trench placement, all new HDPE distribution piping, and abandonment of the existing piping in-place as to limit ground disturbance.
2. The placement of empty dry utility conduit and pull boxes at points within the campground, to allow minimal ground disturbance in the future, when adding electrical pedestals at select camp sites.
3. Reconstruction of the asphalt roadway surface throughout the entire campground, with full depth roadway reclamation in select areas. Roadway replacement will be in-kind, with spurs and roadways maintaining their existing widths and size (primarily single lane, except for the main road entering the loop and the small parking area.
C. Project will be constructed under a single prime contract.
1.3 WORK PHASES
A. The Work shall be conducted in one phase.
GRTE - 240717 01 11 00 - 2
1.4 WORK UNDER OTHER CONTRACTS
A. General: Cooperate with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate Work of this
Contract with work performed under separate contracts.
B. Concurrent Work: Government has awarded separate contract(s) for the following construction operations near the Project site. Those operations will be conducted simultaneously with work under this Contract.
1. Moose Wilson Road Phase 1 - WY NPS GRTE 2017(1): A separate contract has been awarded for the bridge replacement, roadway reconstruction, grading, aggregate, asphalt pavement, and minor concrete placement. While Moose Wilson Road is outside the Jenny
Lake Campground project limits, it does impact egress into Grand Teton National Park at one of the park’s primary entrance stations.
1.5 GOVERNMENT-FURNISHED MATERIALS
A. In case of Government -furnished materials:
1. Government will arrange and pay for delivery of Government-furnished items according to Contractor's Construction Schedule.
2. Contractor is responsible for initial inspection, receiving, unloading, and handling
Government-furnished items at Project site.
3. Government will inspect delivered items for damage after delivery. Contractor shall be present for and assist in Government's inspection.
4. Government will arrange for replacement if Government-furnished items are damaged, defective, or missing.
5. Contractor is responsible for protecting Government-furnished items from damage during storage and handling, including damage from exposure to the elements.
6. If Government-furnished items are damaged as a result of Contractor's operations, Contractor shall repair or replace them.
7. Contractor shall install and otherwise incorporate Government-furnished items into Work.
B. Government-Furnished Materials:
1. Government will provide 42 Bearsaver FS30-UP models for this project. This will include
42 pole mount kits that will be used to mount the government provided bear boxes.
1.6 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of site for construction operations. Limit use of premises to areas within the construction limits indicated on drawings. Do not disturb portions of
Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations only to areas identified on the plans. Unless, there is reasonable cause for activities involving boulders, bear boxes, signs, utility lines, etc. If the construction limits are to be violated, permission must be obtained from
Contracting Officer (CO) prior to conducting work outside of limits.
GRTE - 240717 01 11 00 - 3
2. Limit site disturbance, including earthwork and clearing of vegetation, to 5 feet beyond building perimeter; 5 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter; 3 feet beyond primary roadway curbs and main utility branch trenches; and 3 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields). Areas that require additional staging areas should be coordinated with the Contracting Officer (CO).
B. Storage of Materials: Confine storage of materials to areas within the limits of construction or within the staging area as shown on plans. Staging area is located approximately 10 miles North of the project site, location is commonly referred to as the RKO Pit.
C. Parking: Confine parking to areas within the limits of construction or within the staging area as shown on plans.
D. Stockpiling: Confine stockpiling to disturbed areas within the identified construction limits.
E. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer (CO) and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
F. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to
Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
G. Construction Camp: Establishment of a camp within park will not be permitted.
H. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
I. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.
GRTE - 240717 01 11 00 - 4
1.7 PUBLIC USE OF SITE
A. Jenny Lake Campground will be closed to the public during construction.
B. Contractor shall conduct his operations to ensure the least inconvenience to public.
1.8 CONDUCT OF OPERATIONS
A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 2 business days in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.9 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7 a.m. to 7 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: 7 a.m. to 7 p.m., but only as permitted by the Contracting Officer.
2. Early Morning Hours: As permitted by the Contracting Officer.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two business days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Hours and length of Utility Shutdowns shall be approved by the Contracting Officer.
D. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within 25 feet of any building entrance, operable windows, or outdoor air intakes.
GRTE - 240717 01 11 00 - 5
1.10 NPS Standard Mitigations and Stipulations Attachment
A. See Attachment 1.10.A, immediately following this Section, which includes standard mitigations and stipulations to be abided by throughout the duration of this project.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
Revised 28 March 2018
Grand Teton National Park (GRTE) John D. Rockefeller, Jr. Memorial Parkway (JODR) Standard Mitigations and Stipulations
NOTE: Some projects and activities are proposed by non-National Park Service (NPS) individuals, groups, partners, officials, agencies, organizations, businesses, etc. These proposals are usually initiated through a special use permit request or are part of an agreement, contract, commercial authorization, or other signed record between the NPS and the non-NPS entity. In these cases, the appropriate NPS employee will serve as the Project Leader and “liaison” to ensure proper compliance procedures are being followed. The “liaison” will be the contact with the non-NPS entity.
The Project Leader is responsible for ensuring the following mitigations and stipulations are followed. The non-NPS entity will contact the NPS Project Leader if any of the mitigations and stipulations reference a specific phone number below. The Project Leader will contact the referenced office or individual and will advise the non-NPS entity.
Congress charged the NPS with managing the lands under its stewardship “in such manner and by such means as would leave them unimpaired for the enjoyment of future generations” (NPS Organic Act, 16 USC 1). As a result, NPS staff routinely evaluate and implement mitigation measures whenever conditions occur that could adversely affect the sustainability of national park system resources.
Mitigation is defined in the Code of Federal Regulations (40 CFR 1508.20) as:
• Avoiding the impact altogether by not taking a certain action or parts of an action.
• Minimizing impacts by limiting the degree or magnitude of the action and its implementation.
• Rectifying the impact by repairing, rehabilitating, or restoring the affected environment.
• Reducing or eliminating the impact over time by preservation and maintenance operations during the life of the action.
• Compensating for the impact by replacing or providing substitute resources or environments.
The following mitigation measures were developed to minimize the degree and/or severity of adverse effects and would be implemented as appropriate during approved project activities. The NPS may need to obtain federal and state environmental permits and, as part of that process, additional mitigation measures could be required by other agencies.
Assessment of Effect
• If previously unknown archeological resources and/or human remains are discovered during construction, all work in the immediate vicinity (600 feet) of the discovery shall be halted until the resources are identified and documented and an appropriate mitigation strategy developed. Contact the Branch Chief of Cultural Resources (307-739-3671).
Assessment of Effect – Cultural Landscapes
• All vegetation modification, including tree removal, at National Register of Historic Places -listed or -eligible properties shall be reviewed and approved by the Section 106 specialists (as well as by wildlife and vegetation specialists).
Attachment 1.10.A (10 pages)
• All work on or near historic buildings, structures, sites, and landscapes shall be conducted in accordance with the Secretary of the Interior's Standards for the Treatment of Historic Properties in consultation with the Branch Chief of Cultural Resources (307-739-3671). Any deviation from the approved specifications must be submitted for further review.
Assessment of Effect – Historic Structures
• All work on or near historic buildings, structures, sites, and landscapes shall be conducted in accordance with the Secretary of the Interior's Standards for the Treatment of Historic Properties in consultation with the Branch Chief of Cultural Resources (307-739-3671). Any deviation from the approved specifications must be submitted for further review.
• Consult with NPS cultural resource specialists or archaeologists in advance (generally 60 days) of any ground disturbing activities or work on or near buildings, structures, sites and landscapes eligible for or determined eligible for listing in the National Register of Historic Places.
• Inform all contractors and subcontractors of the penalties for illegally collecting artifacts or intentionally damaging archeological sites or historic properties.
Night Sky
• Project shall comply with NPS lighting guidelines to reduce impacts to the night sky and wildlife. This will include, but is not limited to, low-level lighting, minimized glare, downward focused light fixtures, and energy efficient light sources.
Park Operations & Mgmt – Aviation
• The following stipulation applies to all unmanned aircraft and aircraft managed by the Department of the Interior and Department of Agriculture in accordance with the Teton Interagency Aviation Management Plan. Coordinate all aircraft activities including unmanned aircraft with the Park's Interagency Aviation Officer (307-739-3339/5524) at least 30 days in advance. Flight requests or flight schedules should be submitted to the Aviation Officer by the requestor and be returned to the requestor if approved from Teton Interagency Dispatch. Flight requests or flight schedules for nonemergency missions need to be submitted allowing enough time for approval of project aviation safety plans, aircraft selection or procurement, and selection of aircraft management and necessary support personnel.
• The following stipulation applies to manned aircraft activities not directly managed by Teton Interagency Aviation and that require a special use permit or scientific research permit. For each day of activity where any type of aircraft is used the permit holder or aircraft operator shall contact Teton Interagency Dispatch (307-739-3630) prior to and at the end of the operation.
Park Operations & Mgmt – Construction General
• Hours of work may be determined by the park to avoid construction disturbance to visitors, park residents, or wildlife.
• The location of all potential utility lines in work areas shall be field located and marked prior to work to avoid disturbance conflict.
• Maintain a safe construction zone. Fence around open holes when personnel are not present and provide for a slope out of the hole such that wildlife trapped in the excavation may be able to escape.
• Control dust during construction by minimizing soil exposure, watering, and using other dust prevention methods.
Attachment 1.10.A
• Dispose of construction and/or demolition debris (e.g., old water lines, appurtenances, water tanks, valves, packaging materials, trash) at appropriate areas designated by the park. When possible, debris will be disposed of at a materials recycling facility.
• All project zones will be kept trash free at all times.
• To minimize the amount of ground disturbance, staging and stockpiling areas will be located in previously disturbed sites, away from visitor use areas to the extent possible. All staging and stockpiling areas shall be returned to pre-construction conditions following project completion.
Parking of construction vehicles will be limited to these staging areas, existing roads, and previously disturbed areas.
• Identify and define construction zones with construction tape, snow fencing, or other material prior to any construction activity. Use the zone to confine activity to the minimum area required for construction. Construction activities, including material staging and storage, cannot occur beyond the construction zone fencing.
• A traffic control plan for use during construction as approved by the park will be developed and enforced to minimize disruption to visitors and park operations and to ensure safety of the public, park employees, and residents.
Park Operations & Mgmt - Communications
• Inform contractors (construction workers and supervisors) about the special sensitivity of park values, regulations, and appropriate housekeeping.
• Contractors will coordinate with park staff to minimize disruption of normal park activities.
• If the project or activity occurs within or immediately adjacent to park housing areas, coordinate with the park's Housing Program Manager (307-739-3577) at least one week before the project or activity is scheduled to begin and immediately after it is completed.
Park Operations & Mgmt - Utilities
• Notify Park Facilities Management Utility Systems staff (307-739-3366) prior to a contractor connecting to or repairing a water or sewer line in the park. Any repairs to potable water lines must be coordinated with the park, and any potable water line that loses pressure during construction will be required to be placed into Boil Order status until a sample can be collected and tested.
• Following construction, furnish the GRTE GIS Office (307-739-3493) with utility location information, including a shapefile using coordinates NAD83 UTM 12N, company name, and type and number of lines.
Soils, Topography, Geology – Construction
• Avoid rutting or excessive soil compaction caused by vehicles or equipment. Construction activities shall be restricted during saturated soil conditions or severe weather conditions to avoid damage to soils and vegetation. In the event of adverse weather conditions, the project leader will consult with the SRM Vegetation Branch (307-739-3678) to ensure that ground conditions are acceptable for project activities.
Soils, Topography, Geology – Disturbance
• To minimize the amount of ground disturbance, locate staging and stockpiling areas in previously disturbed sites to the extent possible. Return all staging and stockpiling areas to pre-construction conditions following construction.
Soils, Topography, Geology – Erosion Control
• To minimize soil loss/erosion at the project site, erosion control best management practices (BMPs) including protection measures such as sediment traps, silt fences, erosion check screens/filters, jute mesh, will be used if necessary, to prevent the loss of soil.
Soils, Topography, Geology – Topsoil
• Topsoil should be salvaged at the beginning of all ground disturbance activities by scraping the topsoil to the side prior to deeper digging. Topsoil refers to the uppermost layers of soil and includes fine particles, small roots, rocks, and cobbles. It is usually darker in color, and is the layer in which the majority of roots grow and beneficial microorganisms exist. It is usually the top 2-6 inches.
Conserving topsoil will minimize impacts to vegetation and help preserve valuable micro-organisms and the native seed bank.
• Store salvaged topsoil separately from other materials. Limit the height of topsoil stockpiles to 36 inches. Do not stockpile topsoil or subsoil within drip line of remaining trees. Excess soil will be stored only at approved locations.
• Replace topsoil and other excavated soils and rock in the proper order, cobble lowest, then subsoil, then topsoil. Use a trench box if one is needed to reduce disturbance. Spread topsoil as near to the original location as possible.
• During the final stages of project implementation, scarify and loosen compacted subsoils to a minimum depth of 12 inches prior to replacing the salvaged topsoil. Soil decompaction will be done with equipment that has ripping teeth, placed a maximum of 12 inches apart.
• Do not drive or operate equipment on newly replaced topsoil. Do not re-enter the project site once revegetation/restoration work has been initiated and/or completed.
Soundscapes-Idling
• To reduce noise and pollution emissions, construction equipment and all motor vehicles will not idle any longer than is necessary.
Soundscapes-Mufflers
• Ensure that motorized vehicles and equipment have properly functioning mufflers.
Vegetation
• Coordinate all project work with park vegetation specialists regarding invasive, non-native plant
(weed) treatments, revegetation requirements, costs, and scheduling. Contact the SRM Vegetation Branch (307-739-3678).
• Limit ground disturbance to the smallest area possible to reduce disturbance to soil and native plants and reduce the potential for the introduction and/or spread of non-native, invasive plant species.
• Plant survey for rare and/or sensitive species are required prior to ground disturbing activities and must be conducted during growing seasons when these species could be identified.
Vegetation – Exotic Plants
• Seed mixes used for revegetation in roadside corridors will be composed of native species and approved by SRM Vegetation Branch staff.
• Prior to project implementation, SRM Vegetation staff will conduct invasive, nonnative plant surveys in the project area. Invasive weed control measures will be implemented to monitor and mitigate impacts within the first 3 years (minimum) of construction.
• To reduce the threat of nonnative, invasive vegetation being introduced to the park, all imported material (i.e., sand, gravel, rock, rip-rap, etc.) must be obtained from a park approved or county weed district approved source. Teton County Weed and Pest has currently approved as weed-free the various Evans Construction pits in Teton County. If a new material source is requested, park vegetation staff will seek county-approved material source pits and/or perform a nonnative, invasive plant inspection.
• Material sources, including sand, gravel, rock, rip-rap, mulch, etc. that is not attained form a county or park approved weed-free material sources must be precooked (300 degrees) or washed to prevent spread on invasive weeds in the park.
Vegetation – Miscellaneous
• Vegetation beyond the estimated scope of disturbance shall not be damaged or removed without prior approval via the project documents or by park vegetation management staff.
• To facilitate revegetation and non-native, invasive plant management, provide the SRM Vegetation Branch (307-739-3678) via project documents, with an estimate of potential ground disturbance at least 4 weeks prior to work and with the dimensions of the disturbed area after the work is complete.
• Consider minimizing ground and vegetation disturbance by boring or other alternatives to trenching activities.
• Use wooden mats for vehicle and equipment access to the site to limit damage to existing vegetation.
• Avoid destruction of individuals or populations of sensitive plant species or alteration of their habitat when conducting ground disturbing activities. SRM vegetation staff will notify project managers of rare or sensitive plant species for project documents prior to initiation of activities.
• For roadside brush removal activities, parts under 3" in diameter may be "lopped and scattered" into adjacent forested vegetation so that it is 6 inches or less in depth measured immediately after treatment. If chipping, broadcast chips so that chip depth is less than 2 inches measured immediately after treatment.
Vegetation - Trees
• Preserve existing trees to the extent possible, and during trenching operations, avoid damaging the roots of nearby trees.
• Tree/ Slash Removal - When trees are felled as part of project right of way clearing, remove all tree parts greater than 3” in diameter from the site except those pieces (“slash”) needed for revegetation or reclamation of the disturbance. The limbs, tops, and miscellaneous residue left by forest thinning and pruning activities are commonly called slash.
• Tree/ Slash Removal - Tree parts (slash) under 3" in diameter (not chips) may be "lopped and scattered" into adjacent forested vegetation so that it is 6 inches or less in depth measured immediately after treatment. If the <3" slash is chipped, broadcast the chips so that chip depth is less than 2 inches measured immediately after treatment. Chips may also be removed from the park for other uses.
• Stumps resulting from tree removal shall be flush cut level with the ground and no higher than 2” as measured from the uphill side.
Vegetation – Weed/Seed Free
• If a material source does not have an approval for weed-free, or if a material source fails an inspection, then the material must be clean of weed seed materials and dirt debris before entering the park. That typically entails cooking material such as sand and gravel to 300 degrees F. For larger rock and rip-rap, the rock can be separated from smaller dirt materials, and washed prior to entering the park.
• All vehicles and equipment shall arrive at the job site in a condition free of mud, dirt, and plant material. A method such as pressure washing prior to transport will be needed to comply with this requirement. Prior to offloading of any equipment, inspection and verbal approval must be obtained from the park resource management representative or delegated representative. The spread of non-native, invasive plant species in the park is a serious concern, and no equipment will be allowed to offload or remain within the park if dirt or other contaminants with the potential to harbor seeds or other plant material is apparent.
Fish and Wildlife
• Work that includes influence or direct disturbance to a wetland or stream should not be conducted during fish spawning periods. Spawning phenology by species is dependent on location of waterway, so please contact the SRM Fish and Wildlife Branch Fisheries Biologist (307-739-3666) for specifics.
• Consult with SRM Fish and Wildlife biologists (307-739-3666) regarding culvert design to allow for fish and wildlife passage where applicable.
• To prevent introduction of terrestrial or aquatic invasive species, all equipment, including rubber-tired land and tracked land vehicles, construction and facility equipment, watercraft, and personal use equipment such as diving gear, must be thoroughly cleaned, and inspected by park personnel before being operated or launched in the park.
• Unless otherwise noted (i.e., elk rutting and near sage grouse leks), limit routine construction activities to 30 minutes after sunrise to 30 minutes prior to sunset to avoid disturbance to wildlife.
• To protect special status species:
o Inform staff about the potential for special status species in or near the area of the proposed activity. Work will cease if a special status species is discovered in the project area, until park staff re-evaluates the project. Protective measures, including potential modification of the work or the work schedule, could be determined necessary.
o Ensure that all mitigations/conservation measures determined through Endangered Species Act Section 7 consultation with the U.S. Fish and Wildlife Service (USFWS) are followed.
o In circumstances when it is deemed necessary to conduct activities near sites known to support threatened or endangered species, such work will be performed in a way (specified by the park biologist) to minimize impacts to the listed species (e.g., working quietly on-site, and minimizing time in or near habitats en route to their work sites).
• All project activities must comply with GRTE’s Superintendent’s Compendium related to food storage and park recommended best management practices for living and working in bear country.
Bear “attractants” include food, drinks, garbage, cooking utensils, dirty / soiled pots/pans/plates, stoves, grills (charcoal or gas), empty or full coolers, storage containers with food or previously holding food (except approved bear resistant canisters), beverage containers, pet food/bowls, and any odorous item that may attract a bear such as toiletries.
o At all times in all locations, including the backcountry, all staff (NPS, Volunteers-in-Parks (VIPs), contractors, etc.) must ensure that all bear attractants are attended at all times. All unattended attractants must be stored securely inside a building, a bear resistant food storage locker (if available), in a hard sided vehicle with doors locked and windows closed, or in an Interagency Grizzly Bear Committee (IGBC) approved portable bear resistant food storage canisters; or disposed of properly in a bear-resistant garbage receptacle. Backpacks and/or daypacks containing unsecured attractants (i.e. not in a canister) must not be left unattended.
o All personnel must attend a briefing on proper food/attractant storage and bear safety presented by a qualified member of the park's bear management team or their designee.
Please contact the park's Bear Management Office (307-739-3673) at least two weeks prior to the desired start date to schedule a briefing.
o All human-bear conflicts must be reported to Teton Interagency Dispatch Center immediately (307-739-3301). All bear sightings must be reported to the park’s Bear Management Office (307-739-3673) within 24 hours.
o Provide for proper storage and disposal of materials that may be toxic to bears. All potentially toxic attractants, including petroleum products, must be stored or disposed of in such a way that they are not available to bears.
o Construction debris must be separated from human food garbage and disposed of in dumpsters that can be closed at night. No open dumpsters are allowed. A request for an exception to the open dumpster stipulation, however, can be made to the project manager who will consult with the park’s Bear Management Office to determine if such use will be authorized. The use of open dumpsters will only be considered if the following conditions can be met: the open dumpster must be stored behind a locked fence out of view and inaccessible to the public, will be labeled construction debris only, and be inspected daily to ensure that no human food garbage is in the dumpster.
• For all projects occurring within the Grizzly Bear Primary Conservation Area (PCA), coordinate with the Bear Management Office (307-739-3673) to ensure that all project activities comply with habitat standards in the Final Conservation Strategy for the Grizzly Bear in the Greater Yellowstone Area (USFWS 2016, http://igbconline.org/yellowstone-subcommittee/), and to the extent practicable, that projects occurring in occupied grizzly bear habitat outside of the PCA adhere to the spirit of standards in the Final Conservation Strategy (USFWS 2016).
• Conservation recommendations (CR) provided in the USFWS 2016 biological opinion on the Historic Properties Management Plan to protect minimize or avoid effects to grizzly bear::
o CR1. Minimize human interaction and potential grizzly bear mortality by continuing the Park’s hazing strategies to prevent grizzly bears from becoming habituated to human residences.
o CR2. Grizzly bears concentrate in certain areas during specific time periods to take advantage of concentrated food sources or because the area provides a high seasonal food value due to diversity in vegetation and plant phenology (e.g., important spring or fall range). Where grizzly bear use is known or likely to occur and where practicable, delay disturbing activities during the spring in spring habitats to minimize displacement of grizzly bears.
o CR3 Manage building construction/removal and other activities in a manner that will minimize noise and visual disturbances and facilitate safe movement through habitat by grizzly bears.
o CR4. Control speed, traffic, and parking to minimize negative impacts to grizzly bear activity, including active enforcement of speed limits.
Attachment 1.10.A http://igbconline.org/yellowstone-subcommittee/ http://igbconline.org/yellowstone-subcommittee/
• All project activities will adhere to all relevant conservation measures outlined in the Lynx Conservation Assessment and Strategy (USFWS revised 2013). In particular, harvest of trees on site for the proposed activities within Lynx Analysis Units and/or in Critical Lynx Habitat will not be authorized without further review and analysis in consultation with USFWS.
• All project activities will comply with GRTE’s Superintendent’s Compendium closures implemented around wolf den/rendezvous sites. Should a den or rendezvous site not previously known be found within 1 mile of the proposed activity a seasonal area closure would be implemented as needed, typically between 15 April and 15 August.
• Prohibit construction activities before 8 a.m. and after 6 p.m. during the elk rutting and migration period (typically from September 1 to December 1, or as recommended by the park biologists).
• Avoid construction, maintenance, or other disturbing activities in crucial ungulate winter ranges (15 December to 15 April) and in identified ungulate parturition ranges (15 May - 30 June). See mitigation reference maps.
• Fencing (including temporary fencing for construction projects and permanent fencing) used in projects will comply with wildlife friendly fencing standards. Consult with the SRM Fish and Wildlife Branch Ungulate Biologist (307-739-3488) for assistance with specifications and appropriate design.
• For all herbicide applications, to the extent possible please conform to best management practices for wildlife. This includes following MSDS label instructions and avoiding sensitive times/areas for wildlife (e.g. bird nesting, fawning, den sites, bloom periods for pollinators).
• All wildlife-vehicle collisions must be reported to Teton Interagency Dispatch as soon as possible.
• A bat mitigation plan must be developed prior to initiating preservation, maintenance, or other activities in park structures that could negatively affect bats, their roosts, or hibernacula and/or if bat sign (bat vocalizations, smell of a bat roost, bat droppings on floors or walls, bat carcasses or skeletons, oily marks (from fur) around possible access points and roost areas, lack of cobwebs along beams, feeding remains such as moth wings or other insect parts, or other sign) is observed at any site. Buildings with any of the following characteristics (largely undisturbed; large roof void; large dimension roof timbers with cracks, joints and holes; uneven roof covering with gaps; ; hanging tiles or wood cladding; setting close to woodland and/or water; early 20th century or older construction; or roof warmed by the sun) may have a high probability of being used by bats.
- It is the responsibility of the park project lead to notify park biologists proposed work activities, and to schedule surveys with enough lead time to minimize project implementation delays. If roosting bats are found in buildings, work on those structures will be delayed until after the roosting period. Qualified personnel must perform a survey within the appropriate timeframe (i.e., spring surveys for maternity roosts, summer surveys for summer roosts, winter surveys for hibernacula) prior to initiating work and, if bats are found, develop a mitigation plan.
Wildlife – Amphibians
• Care will be taken not to disturb any wildlife species (amphibians, reptiles, migratory birds, mammals, raptors, or bats) found nesting, hibernating, estivating (in an inactive dormant state during hot, dry periods), or otherwise living in, or immediately nearby, worksites.
• Prior to work in or near wetlands or waterways the area will be assessed for its importance to amphibian species and prohibitions and limitations shall be set in order to protect these species.
Wildlife – Birds
• All project activities must comply with the Migratory Bird Treaty Act of 1918 (MBTA; 16 U.S.C.
703) and Executive Oder 13186. Under the MBTA, it is illegal to "take" migratory birds, their eggs, feathers or nests. “Take” is defined (50 CFR 10.12) to include “pursuing, hunting, shooting, wounding, killing, trapping, capturing, or collecting.” The MBTA does not distinguish between “intentional” and “unintentional” take. Migratory birds include songbirds, waterfowl, shorebirds, and raptors. All project activities must also comply with GRTE’s Superintendent’s Compendium seasonal closure regulations for raptors, trumpeter swans, great blue herons, and other sensitive bird species.
o In general, park biologists recommend that to prevent impacts to nesting migratory birds and to avoid project delays, schedule work involving vegetation clearing, tree felling, fill placement, excavation, or other construction activities for outside of the nesting season. The breeding season is generally as follows for migratory songbirds (1 May to 1 August), or as dictated by nesting chronology.
o Before commencement of any activities that involve removal or manipulation of vegetation including large trees, grasses, and shrubs during the breeding season (see above) contact park biologists to schedule a survey for nesting birds. Surveys must be conducted by qualified personnel before tree removal and/or ground disturbing activities begin. To the extent possible, schedule surveys prior to 1 March the year of the proposed work.
o Inspect hazard trees for potential nest sites. Fell hazard trees that may contain nests outside the breeding season, if possible, unless there is an imminent threat to human health and safety.
o Work must be completed within two weeks of the nesting bird survey. If this is not possible, another survey must be scheduled with park biologists.
o Active bird nests located during surveys will be protected until nestlings fledge or the nest fails. Park biologists will monitor nests, determine mitigations, and provide updates to the project leader on nesting status.
o It is the responsibility of staff to report any nesting bird activity in the vicinity of proposed activity to park biologists in a timely way so that they may assess whether additional mitigation measures are needed to comply with the MBTA.
• Eagles are specifically protected under the Bald and Golden Eagle Protection Act of 1940 (16 U.S.C.
668-668c) and the MBTA. Project activities must not lead to the take of bald or golden eagles. The Bald and Golden Eagle Protection Act defines “take” to include disturbing birds.
o Implement seasonal closures (typically February 1 to August 15) of ½ mile (GYBEMP 1989, USFWS 2007) around occupied bald eagle nests and prohibit work on or occupancy of area within the closures while they are in effect.
o It is the responsibility of the staff to report any eagle activity in the vicinity of proposed activity to park biologists in a timely way so that they may assess whether additional mitigation measures are needed to comply with the BGEPA and MBTA.
• All project activities must comply with GRTE’s Superintendent’s Compendium closure regulations for sage-grouse leks and to the extent practicable all project activities occurring within occupied sage-grouse habitat within the core sage-grouse area will apply the management direction and conservation measures outlined in the Wyoming Governor's Executive Order 2015-4 and the Upper Snake River Basin Sage-Grouse Conservation Plan (2014).
o Continue to implement a seasonal closure (generally 15 March – 1 June) around the Moulton sage-grouse lek.
o Prohibit removal of shrub-steppe habitat within 4 miles of an occupied sage-grouse lek to protect breeding, nesting, and brood rearing habitat for sage-grouse in the park (generally between March 15 and June 30, or as recommended by park biologists monitoring sage-grouse). Exceptions may be made on a limited and case-by-case basis.
o Limit new permanent facilities (including, but not limited to roads, buildings, well pads, pipelines, leach fields, and vegetation treatments) within 0.6 miles of active sage-grouse lek areas.
o Restrict maintenance and rehabilitation activities between the hours of 6:00 p.m. and 8 a.m. at proposed activities within 4 miles of active leks/nesting complexes (generally from March 15
– June 30, or as recommended by park biologists).
o Limit noise to less than 10 decibels above ambient measures from 6:00 p.m. to 8:00 a.m. at the perimeter of leks (generally from March 1 – May 15, or as recommended by park biologists).
o Efforts will be made to minimize disturbance to mature sagebrush cover in identified winter concentration areas.
o Power or other utility lines should be buried when possible. If such lines cannot be buried, lines should be raptor proofed and located at least 0.6 miles from the perimeter of occupied sage-grouse leks. New transmission lines should be authorized or conducted only when it can be demonstrated that the activity will not cause declines in sage-grouse populations.
Construction of new transmission lines should occur July 1 and March 14. Power lines should be placed along or adjacent to existing long-term linear disturbance features whenever possible.
o Park biologists will use the Wyoming Density and Disturbance Calculation Tool (DDCT) to assess activities that involve vegetation or ground disturbance within the sage-grouse core area that correspond with recommended mitigations for sage-grouse and their habitat.
GRTE - 240717 01 26 01 - 1
012721 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager (PM), Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
GRTE - 240717 01 26 01 - 2
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.
The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: The hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
3) Workers Compensation – Policy and company calculation to be made available.
4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.
5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.
GRTE - 240717 01 26 01 - 3
6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.
Include as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. Proposal shall be detailed with itemized…