A04_40614693_GRTE_Jenny_Lake_One-Way_Micro_Surfacing_2023_-_SOW.pdf

PDF 311 KB Posted

Attached to
GRTE-JENNY LAKE ONE-WAY MICRO SURFACING Federal contract opportunity
Solicitation number
140P1423R0014
Issued by
Department of the Interior National Park Service Intermountain Region

About this file

This scope of work document outlines a microsurfacing and pavement marking project for Grand Teton National Park's Jenny Lake One-Way road. The contractor will apply a polymer-modified microsurfacing mix, restripe the road to allow for one-way vehicle traffic and two-way bicycle traffic, install new pavement markings, and install removable flexible delineators. The work must be completed between June 1-30, 2023. The contractor will be responsible for traffic control, preparing the road surface, complying with weather limitations, applying the microsurfacing mixture according to specifications, laying out and applying new pavement markings, and installing delineators and cups at key turning areas. The document provides additional details on tasks, quantities, job conditions, safety requirements, quality assurance, inspections, warranties, and post-award obligations.

This federal contract opportunity posting is for the above-described microsurfacing and pavement marking project on the Jenny Lake One-Way road in Grand Teton National Park. The estimated price range for the project is $250,000 to $500,000. Davis-Bacon wage rates apply. The solicitation is set aside 100% for small businesses. Interested offerors must register in SAM and have current online representations and certifications. Questions are due by a specified date prior to the proposal due date.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

Micro Surfacing and Pavement Marking Application &

Removable Flexible Delineator Installation Jenny Lake One-Way

Grand Teton National Park

I. GENERAL

A. Background Information: This Scope of Work (SOW) outlines tasks to apply a polymer-modified micro surfacing mix, new pavement markings, and install removable flexible delineators to the one-way section of the Jenny Lake Road, also known as the Jenny Lake One-Way (JLOW) in Grand Teton National Park (the Park).

The JLOW is a 2.5 mile long, 18’ wide paved, one-way road with a striped bicycle lane from its intersection with String Lake Road to its intersection with the Teton Park Road. To address safety concerns, the road will be restriped to allow for one-way vehicle traffic and two-way bicycle traffic.

The contractor will be allowed to close the road for up to four days to complete the work.

Due to the impacts of weather and the need for public notification of work, the contractor will coordinate with the Contracting Officer’s Representative (COR) to set the exact date and time of work performance between 3 and 5 business days prior to work. This area requires a road closure for the work to be performed so advanced public notification by the park to the public is required.

II. SPECIFICATIONS AND SCOPE

A. Description of Work: The work will consist of the Contractor, in accordance with local, state, and federal regulations, and the terms and conditions of the solicitation/contract, providing all labor, supervision, materials (unless specified elsewhere in this Scope of Work), tools, equipment, supplies, transportation, vehicles, and other items, services and incidentals necessary to apply micro surfacing and apply pavement marking in the new layout to the JLOW. All work required by the project documents to complete the work successfully and satisfactorily in its entirety will be performed by the Contractor.

B. Location: The 2.5 mile one-way section of the Jenny Lake Road begins with its intersection with String Lake Road to its intersection with the Teton Park Road in Grand Teton National Park.

This work does not include Jenny Lake Lodge Parking or Jenny Lake Overlook Parking (except as noted on details) but does include all other turnouts.

C. Period of Performance: June 1 – June 30, 2023

D. Specifications:

1. Micro Surfacing aggregate Conform to ISSA A143 and the following:

(1) Gradation Table 703-8

(2) Los Angeles abrasion, AASHTO T 96, Grading D 30 percent max.

(3) Sand equivalent AASHTO T 176, 65 min.

Alternate Method No. 2, Reference Method

(4) Soundness of aggregate using sodium sulfate, 15 percent loss max.

AASHTO T 104 (5 cycles)

Table 703-8 Micro Surfacing and Slurry Seal Aggregate Gradation

Sieve Size Percent by Mass Passing Designated Sieve (AASHTO

T 27 & AASHTO T 11)

Grading Designation

I II III

⅜ inch (9.5 mm) − 100 100 No. 4 (4.75 mm) 100 90 − 100 70 − 90 No. 8 (2.36 mm) 90 – 100 65 − 90 45 − 70 No. 16 (1.18 mm) 65 – 90 45 − 70 28 − 50 No. 30 (600 µm) 40 – 65 30 − 50 19 − 34 No. 50 (300 µm) 25 – 42 18 − 30 12 − 25 No. 100 (150 µm) 15 − 30 10 − 21 7 − 18 No. 200 (75 µm) 10.0 − 20.0 5.0 − 15.0 5.0 − 15.0

2. Mineral filler Conform to AASHTO M 17.

3. Polymer-modified emulsified asphalt for micro-surfacing Conform to ISSA A143, except use Section 6, Emulsified Asphalt Residue by evaporation of AASHTO T 59 to determine percent residue.

4. Composition of Mix.

Conform to ISSA A143, Recommended Performance Guideline For Micro Surfacing.

5. Paint and Glass Beads Pavement marking paint shall comply with AASHTO M-248, Type “F”, or waterborne pavement markings from the Hederal Highway Administration, Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14 2014, USDOT, FHWA, Section 718.10, Waterborne Traffic Paint. Centerlines, stop bars, arrows, crosswalks, bicycle symbols, accessible parking symbols, and lane delineation shall be white. Bicycle lane shall be painted green at turning conflict areas, as indicated in attached details. Contractor shall provide a paint submittal. Reflective glass beads, complying with AASHTO M-247, Type 1, shall be used for all paint applied under this contract, with exception to the green bike lane striping.

6. Stencils

Contractor shall furnish their own stencils. Symbols shall be applied in accordance with MUTCD requirements for the posted speed limit.

7. Removeable Flexible Delineators

3”+ diameter, 30” tall white removable flexible delineators with 360° reflective sheeting.

Installed in road with embedded anchor cup mount. City Post Model EAC (Embedded Anchor Cup) or approved equal.

E. Tasks:

Task 1: Apply micro surfacing mix, as described in Section H.

Task 2: Layout new pavement markings on roadway, as described in Section I.

Task 3: Apply new pavement markings on roadway, as described in Section I.

Task 4: Install removable flexible delineators, as described in Section J.

F. Surface Preparation:

1. Contractor shall prepare the asphalt surface to be treated so that it will be free of all dirt, sand, weeds, grass, moisture and excessive grease. The contractor will be required to remove dust, dirt, sand, leaves, plants and debris from the asphalt surface. The surface shall be cleaned with a power broom, air brooms, supplemented by hand sweeping, power vacuum, drier or any other means required to remove deleterious matter and moisture.

Washing with adequate drying time may be required if debris cannot be swept off.

G. Weather Limitations:

Apply only when the following apply:

(a) Ambient air temperature is above 45 °F (7 °C);

(b) Surface temperature in the shade is above 45 °F (7 °C);

(c) Weather is not foggy, rainy, or overcast; and

(d) Temperatures below 32 °F (0 °C) are not anticipated for at least 24 hours after application.

H. Application of Micro Surfacing Mixture:

Application Rate for Micro Surfacing

Aggregate Type(1) Application Rate (lb/yd2)

Type II 15 – 20

Type III 25 – 30

(1) See Table 703-8 for aggregate gradations.

1. Note: Micro surfacing mixture to be applied to the Jenny Lake One-Way from its intersection with the String Lake to its intersection with the Teton Park Road. Do not apply micro surface to the Jenny Lake Lodge Parking Area or the Jenny Lake Overlook, except for areas under the stop bars, new turn arrows, and new hatching.

2. Fog the surface with water in front of the spreader.

3. Prior to starting application of micro surfacing, calibrate each mixing unit to be used on the project in accordance with ISSA A143. Clean the spreader box prior to start of each work shift.

4. Blend the additives with the aggregate. Pre-wet the aggregate in the pugmill before mixing with the polymer-modified emulsified asphalt.

5. Mix the surfacing material a maximum of 4 minutes. Ensure the mix is of uniform consistency as it leaves the mixer and conforms to the approved JMF. Adjust mineral filler and polymer-modified emulsified asphalt content during construction when approved by the CO to adjust for variations in field conditions.

6. Carry sufficient mix in the spreader to completely cover the surface. Spread the mix with a spreader box. In areas not accessible to the spreader use hand squeegees to work the mix.

7. Maintain quality control documentation and make available to the CO upon request and at completion of work. At a minimum of 4 times daily calculate the percent emulsion content, aggregate spread rate, and yield of the mixture from the equipment computer display readings and report to the CO.

8. Provide straight lines along curbs and shoulders and do not allow runoff onto these areas.

Provide straight and neat starting and ending joints by masking surfaces at the start, end, and other locations as directed by the CO.

9. For transverse joints, use a butt joint. Use building paper placed over previously placed micro surfacing or other suitable method to avoid double placement of micro surfacing.

Remove ridges or bumps in the finished surface.

10. For longitudinal joints, place joints on lane lines. Use half passes and odd-width passes only in turnouts and parking areas. Do not use half passes for the last pass in paved areas.

Overlap longitudinal joints no more than 3 inches (75 millimeters). Limit the elevation difference at joints to less than ¼ inch (6 millimeters).

11. Allow treated areas to cure completely before opening to traffic. Cure is complete when clear water can be pressed out of the placed mix with a piece of paper without discoloring the paper.

12. Remove streaks and transverse ripples as defined by ISSA A143 from the finished surface.

Ensure the finished micro surfacing has a uniform texture free of scratches, tear, and other surface irregularities. Repair areas with surface irregularities or where the micro surfacing does not conform to the job-mix-formula at the direction of the CO.

13. Remove and dispose of material spills and associated debris appropriately at the end of each day.

14. Perform an initial vacuum sweep of the micro surfacing one day after the micro surfacing application. Remove loose or shedding material from the treated surface areas.

15. Two weeks to one month after completion of micro surfacing application, sweep the entire treated surface.

I. Pavement Marking Layout

1. From intersection with String Lake Rd. to intersection with the Teton Park Road

(approximately 13,150’):

a. Restripe road to a 5’ width northbound bicycle lane from edge of pavement to inside edge of 4” double solid yellow centerline and a southbound lane occupying the remaining width of the road (approx. 13-20’). Delineate with a 4” double solid yellow centerline. In cases where the road width fluctuates above or below 18’ width, maintain the 5’ width northbound lane and variate the southbound lane, as necessary and appropriate.

b. Paint the 5’ width bicycle lane green (AASHTO bicycle lane standard color) at turning conflict areas, as shown in the attached details.

c. Add bicycle sharrows in the southbound lane approximately every 250’ as shown in the mockup below. Add through arrows in the southbound lane where shown in the attached details. Add bicycle lane arrows in the northbound lane approximately every 250’. Stagger symbols, as shown in mockup below.

d. Add striping at intersections and conflict areas as shown in the attached details.

e. Replace accessible parking symbol (1 total) and associated parking space markings in their current location in southern parking area pullout.

f. Replace 2 crosswalks (approx. 40’) in their current location.

g. At the intersection with the Historic Jenny Lake Campground Rd., paint a bicycle symbol with through/right turn arrow to direct cyclists onto the Campground Road.

2. Contractor shall be responsible for the layout of the new pavement marking locations.

J. Removable Flexible Delineator and Cup Installation

1. Install flexible delineator and cups according to manufacturer’s installation guide at key turning conflict areas as shown in the details. These areas are:

a. Jenny Lake Lodge

b. Jenny Lake Overlook

c. Southern parking area at the intersection with the Historic Jenny Lake Campground

Rd.

d. Intersection at Teton Park Road

2. Provide a minimum of 20 spare flexible delineator to the Park.

K. Project Tasks:

1. The Contractor will be required to emplace road barricades at the north and south end of the road during work. Road barricades will be provided by the government, if needed. The contractor is responsible to coordinate for the barricades, pick them up, and return them at the end of the project.

L. Quantities

1. 4” double solid centerline (yellow) 13,150’

2. 4” Type B dashed line (white) 270’

3. 4” Type B hatching (white) 605’

4. Through Arrow (white) 10

5. Bicycle w/ Sharrow (white) 52

6. Bike Lane Bicycle Symbol & Arrow (white) 52

7. 24” Stop Bar (white) 81’, or 18 sqyd

8. Accessible Parking Symbol 1 ea

9. Green Bike Lane Painting 396 ln, or 220 sqyd

10. Crosswalk 40 ln

11. Flexible Delineator and Cup 78 ea

12. Spare Flexible Delineators 20 ea

• Note: all quantities approximate

III. JOB CONDITIONS AND CONTRACTOR’S USE OF PREMISES

A. Hours of Contractor Performance, Points of Contact, and Work Coordination:

1. Work shall be performed between the hours of 7:00 a.m. and 6:00 p.m. local time, Monday through Friday, excluding federal holidays, and except when otherwise indicated by the Contracting Officer (CO). Work outside the standard hours is prohibited unless approved by the CO.

Federal Holidays:

Juneteenth (observed) June 20 Independence Day July 4

2. Work Coordination: Before initiating any work, the Contractor shall meet with the COR and agree on: a sequence of procedures, communications; the location of barriers; use of Park restrooms if approved by the COR; and any other incidentals to the project.

3. Project Superintendent: You must employ a full-time site Superintendent for the project.

The site Superintendent’s duties shall include the overall management of the project, coordination of the sub-contractors work, and liaison with the CO and the COR. No work shall be performed without the presence of the superintendent or a competent representative on the job-site. A competent representative is as defined by the Occupational Safety and Health Administration (OSHA) Standards for Construction Industry part 1926.32, Definitions (29 C.F.R. 1926 OSHA).

4. 24‐Hour Point of Contact: Provide the CO and COR with a 24‐hour number or numbers where the designated project Superintendent and an alternate can be contacted at any time.

5. Park Dispatch Number: If unable to reach the COR by phone or in case of emergency, contact the Park’s Dispatch Center at (307) 739-3301.

B. Public Use Areas

1. The work to be performed is on government property. Contractor’s operations should be conducted to respect the public nature of these properties and, to the extent practical, not to interfere with the public’s visitation and use of the surrounding facilities/grounds.

2. Extreme care shall be used when entering, leaving, or operating at the site. Contractor is to provide adequate barriers in work areas to protect public from injury.

3. Safety of visitors, staff, and workers is of the highest priority.

C. Site Use

1. Site Access and Parking: The COR will identify parking areas for Contractor’s vehicles on a case-by-case basis. Vehicles and trailers must be removed at the end of each work day unless arrangements between the Contractor and COR have been specifically coordinated in advance.

2. Field Office: The Contractor is not required nor authorized to provide or stage a field office or trailer in the performance of this contract.

3. Staging: Only upon approval by the COR may the Contractor be allowed a staging area for Contractor’s staging of equipment, tools, supplies, products, parts, materials, or other items used in the performance of this contract. The location of the staging area must be designated by the COR.

4. Lodging: Establishment of a camp within the Park will not be permitted.

D. Preservation of Natural Resources:

1. Confine all operations within the work limits of the project. Exercise special care to leave the natural surroundings undamaged. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government. Contractor will be responsible for all costs associated with restoration of the project area.

2. Do not remove, injure, or destroy trees or other plants without prior approval of the CO/COR. Consult with the CO/COR to remove agreed‐on roots and branches that interfere with construction.

3. Do not fasten ropes, cables, or guys to existing trees.

E. Equipment, Hauling, Traffic Control

1. Equipment Restrictions: Use only equipment that can safely negotiate work area and as authorized by the CO.

2. Hauling Restrictions: Contractor must comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the State load restrictions with such additional regulations as maybe imposed by the Park Superintendent.

Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve the Contractor of liability for damage which may result from moving material or equipment.

3. Traffic Control: If applicable by federal, state, or local regulation, the Contractor shall provide, erect, maintain and subsequently remove all traffic control devices required to gain access to the site and/or complete the work. The traffic controls shall be in accordance with the ‘Manual of Uniform Traffic Control Devices for Streets and Highways.’ Additional traffic control devices (other than government provided barriers) shall be supplied by Contractor with suitable supports of sufficient strength and stability.

Traffic control shall be considered incidental to the completion of the project and no separate payment shall be made for this work. The Contractor shall complete the project so as to minimize the disruption of traffic flow within the work area. The road may be closed a maximum of four days for the work.

F. Security

1. The security of Contractor’s materials, tools, equipment, and other properties remain the responsibility of the Contractor at all times. The Park will accept no responsibility and shall not be liable for Contractor’s properties left on site should they become lost, damaged or stolen at any time during the contract period.

2. Contractor shall comply with all security requirements as imposed by the Park, which may include but not limited to, Contractor’s and subcontractor’s personnel, drivers and vehicles being subject to checks for valid registration and wants/warrants. Individuals who do not pass the security check will not be authorized access to the site.

IV. POST AWARD

A. Accident Prevention / Safety

1. After contract award and before work begins, submit an Accident Prevention

Program/Safety Plan. At a minimum, the Program shall include:

a. Name of responsible individual to carry out the program.

b. Safety meetings

c. First aid procedures

d. Outline the hazards associated with the work and the methods proposed to ensure property protection and safety of the public, Park personnel, and Contractor’s employees.

e. Training, initial and continuing

f. Planning for possible emergency situations such as fires, explosions, spills and or/other emergency situations giving consideration to the nature of the work, site conditions, and degree of exposure of persons and property.

2. The Contractor shall designate and have a Safety Coordinator on site at all times while work is being performed to oversee the Contractor’s Accident Prevention Program/Safety Plan. This may be a responsibility of the Contractor’s Project Superintendent.

3. Comply with all applicable National Park Service regulations and directives pertaining to security, safety, occupational health, fire, traffic, and personnel clearances. The Park rules are located at www.nps.gov/grte. The CO can also provide if requested. Ensure subcontractors are briefed on the same and maintain documentation of such briefings.

4. All work is to be performed in accordance with applicable Federal, State, and local regulations, including requirements of OSHA, EPA, ADEQ, and county regulations that apply.

5. Install protective barriers to protect visitors and staff. The Contractor shall work with the CO/COR to avoid or minimize interruptions to general visitor access.

6. Protect all exterior surfaces and areas, including landscaping, walks, drives, all adjacent building surfaces and equipment and any labels and signage from project operations and damage by using drop cloths, shields, masking, templates, or other suitable protective means.

7. Take all necessary precautionary and safety measures to prevent fire hazards and spontaneous combustion and to protect the environment from hazard spills. Materials that constitute a fire and/or environmental hazard (paints, solvents, drop clothes, etc.)

shall be stored in suitable closed and rated containers or shall be removed from the site daily.

8. Dispose of contractor generated waste materials and other excess material outside the Park in accordance with federal, state, and local regulations.

9. During work stoppages (including overnights) and at completion of the project, clean work areas and properly dispose of all waste materials, debris, and supplies and store or remove equipment. Close and seal tightly partly used cans of materials including sealant and adhesive containers and store protected in well ventilated fire-safe area at moderate temperature. Do not leave materials where visitors could access when Contractor’s employees are absent from work area.

http://www.nps.gov/grte

B. Quality Assurance:

1. Contractor will be required to furnish a qualified individual who will be on site at all times while work is being performed to provide oversight of quality assurance. This individual can also be the Contractor’s Project Superintendent.

C. Post Award Conference: Within ten (10) calendar days after award of the contract and prior to the post award conference, the Contractor must provide and submit to the Contracting Officer for approval and acceptance, the following documents:

1. Certificate of Insurance

2. Alternate Payment Protection – Payment Bond or Irrevocable Letter of Credit

3. Accident Prevention Program/Safety Plan

4. Waste and Recycling Plan

5. Proposed Project Schedule

6. Letter designating your Project Superintendent, Alternate Site Superintendent, Safety

Supervisor and Quality Control Supervisor. Also provide a 24-hour number(s) where the designated Site Superintendent and Alternate can be contacted at any time.

7. From the Wage Determination of this contract, a list of the position classifications to be used in the performance of this contract.

8. List of subcontractors, if any, along with description of work each will be performing, and a completed and signed SF-1413 Form (Statement and Acknowledgment) for each subcontractor.

D. Progress Meetings: The Contracting Officer may schedule progress meetings with Contractor throughout the duration of the contract. These will be held telephonically or at a location designated by the Contracting Officer.

E. Submittals:

1. Submit to the CO for approval all items as required by the contract documents. Submittals to be transmitted utilizing the NPS Transmittal form that will be provided by the CO.

2. The CO reserves the right to require submittals in addition to those called for in the contract documents. No materials will be installed or used until submittals have been approved and signed by the CO.

3. Upon CO’s receipt of contractor’s submittal(s), CO will return to the Contractor for disposition within three (3) business days.

4. If Contractor’s submittal has been disapproved, Contractor shall have three (3) business days to resubmit

F. Inspections (Interim and Final):

1. Interim Inspection: The Government retains the right to inspect Contractor’s work at any time throughout contract performance. Contractor’s work will not be considered accepted by the Government until a final inspection has been conducted by the Government and the work and materials are found to be acceptable.

2. Final Inspection: When the work has been completed, the contractor shall notify the COR that the work ready for acceptance by the COR. All Contractor’s properties, equipment, tools and materials will be removed from the site and the site left in an acceptable condition immediately upon completion of the work.

V. WARRANTY

A. Contractor will provide the workmanship and materials warranty in accordance with the Warranty of Construction clause of the contract.

B. There shall be a maximum 72-hour response time by the Contractor on all warranty items and services under this contract identified as either defective, faulty, malfunctioning or inoperative after acceptance of the work. Should it be determined by the Contracting Officer that warranty items/services, if not corrected immediately would cause, or potentially cause, harm or injury to persons or properties, or have a negative impact on Park operations, a response time sooner than 72 hours will be required of the Contractor.

Bid Schedule

Task 1: Apply micro surfacing mix $

Task 2: Layout new pavement markings $

Task 3: Apply new pavement markings $

Task 4: Install removable flexible delineators and cups

Total $

SCOPE OF WORK
I. GENERAL
II. SPECIFICATIONS AND SCOPE
III. JOB CONDITIONS AND CONTRACTOR’S USE OF PREMISES
IV. POST AWARD
V. WARRANTY