Amendment_1_Questions_and_Answers_0001.docx

DOCX document 16 KB Posted

Attached to
GRTE-JENNY LAKE ONE-WAY MICRO SURFACING Federal contract opportunity
Solicitation number
140P1423R0014
Issued by
Department of the Interior National Park Service Intermountain Region

About this file

This document contains questions and answers regarding Amendment 1 for federal contract opportunity 140P1423R0014. The opportunity is for micro surfacing services on the one-way section of Jenny Lake in Grand Teton National Park. The questions and answers clarify that the initial vacuum sweeping should occur once the treated areas have cured, while the second sweeping and painting can be done two weeks to one month after application. The contracting officer confirms that if done correctly, the sweeping should not damage the paint. Additionally, the period of performance cannot be postponed to September as requested by the contractor.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers – 140P1423R0014 - Grand Teton Jenny Lake One-way Micro Surfacing - Amendment 1

1. Reviewing the micro surface process, and the SOW, the SOW states to vacuum sweep one day after application and sweep two weeks to one month after placement.

Correct, based on the STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS FP-14 Section 409 - Micro Surfacing. Perform the initial sweep once the treated areas have cured. Perform a second sweep two weeks to one month after application.

2. The SOW gives no specific timing of paint/striping application. Other technical guidance provides a range from one hour after application of the micro surface up to 14 days.

Perform the initial vacuum sweep after treated areas have cured. "Allow treated areas to cure completely before opening to traffic. Cure is complete when clear water can be pressed out of the placed mix with a piece of paper without discoloring the paper." Apply paint after the initial vacuum sweep.

3. The contractor believes the sweeping, two weeks after the application micro surface and painting, would damage the paint and reduce the quality of the end product.

If the micro-surfacing and paint are applied correctly, the sweeping should not damage the paint. This is the process the FHWA uses for micro-surfacing application.

4. Is it possible to perform this project in September?

There is no flexibility to postpone to September. The POP in the RFP is modified to reflect award and preconstruction activities. On site contract performance may be 6/20-23 or 6/26-30.