A02_24B0009 Wapp Bid Schedule Jan 3 Protected.xlsx

XLSX spreadsheet 87 KB Posted

Attached to
Solicitation for Wappapello Lake Facility Infrastructure Construction & Maintenance IDIQ
Solicitation number
W912P924B0009
Issued by

About this file

This document outlines a solicitation for an indefinite delivery/indefinite quantity construction contract to provide facility infrastructure construction and maintenance services at Wappapello Lake Project in Missouri. Services include earthwork, borrow operations, concrete work, drainage structures maintenance, utilities maintenance, grounds maintenance, and more. The contract has a total estimated value of $0 with five one-year ordering periods and an optional six-month extension. Bids are due on February 5, 2024 and will be evaluated for price alone using sealed bidding procedures. The award will be a single-award IDIQ to the responsible bidder offering the lowest price. Payment will be made by EFT.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Base

BID SCHEDULE - BASE YEAR - ORDERING PERIOD 1

FACILITY INFRASTRUCTURE CONSTRUCTION AND MAINTENANCE IDIQ

ORDERING PERIOD DURATION: 1 MAR 2024 - 28 FEB 2025

BASE YEAR - ORDERING PERIOD 1
Pre-Priced Line ItemDescriptionEstimated
QuantityUOMUnit PriceEstimated
AmountTechnical

Section

1Concrete Slab: 4-inch200SF$0.0003 30 00
2Concrete Slab: 6-inch200SF$0.0003 30 00
3Concrete Slab: 8-inch100SF$0.0003 30 00
4Concrete Slab: 10-inch100SF$0.0003 30 00
5Concrete Ditch: 4-inch200SF$0.0003 30 00
6Concrete Curb & Gutter1000LF$0.0003 30 00
7Concrete Barrier Curbs1000LF$0.0003 30 00
8Concrete Mountable Curbs1000LF$0.0003 30 00
9Reinforcement500LB$0.0003 30 00
10Miscellaneous Concrete WorkTBDTBD03 30 00.99
11Clearing and Grubbing: Light5000SY$0.0031 00 00
12Clearing and Grubbing: Heavy5000SY$0.0031 00 00
13Fill Material1000CY$0.0031 00 00
14Earthwork - Berm Construction2000CY$0.0031 00 00
15Earthwork - Light Field/Site Grading2000CY$0.0031 00 00
16Earthwork - Heavy Field/Site Grading2000CY$0.0031 00 00
17Earthwork - Slough Construction2000CY$0.0031 00 00
18Earthwork - Pavement Subgrade1000CY$0.0031 00 00
19Excess Earthwork Disposal200CY$0.0031 00 00
20Top Soil800CY$0.0031 00 00
21Geotextile Installation - Woven100SY$0.0031 05 19.13
22Geotextile Installation - Non Woven100SY$0.0031 05 19.13
23Concrete Removal200CY$0.0032 00 00
24Concrete Removal Structures & Foundations200CY$0.0032 00 00
25Asphalt Removal200CY$0.0032 00 00
26Removal of Aggregates200CY$0.0032 00 00
27Disposal of Misc.500LB$0.0032 00 00
28Right of Way Clearing50MILE$0.0032 00 00
29Tree TrimmingTBDJOB32 00 00
29aTree Trimming Low20HR$0.0032 00 00
29bTree Trimming High20HR$0.0032 00 00
30Tree Removal - Light10EA$0.0032 00 00
31Tree Removal - Heavy10EA$0.0032 00 00
32Stump Removal - Light10EA$0.0032 00 00
33Stump Removal - Heavy10EA$0.0032 00 00
34Landscape Timbers Installation50LF$0.0032 00 00
35Landscape Timber Removal20LF$0.0032 00 00
36Sand Supply100TN$0.0032 00 00
37Beach Sand Supply & Install200TN$0.0032 00 00
38Redman Creek Beach - Maintenance1JB$0.0032 00 00
39Rockwood Beach - Maintenance1JB$0.0032 00 00
40Peoples Creek Beach - Maintenance1JB$0.0032 00 00
41Greenville Berm Notch Construction1JB$0.0032 00 00
42Greenville Berm Notch Removal1JB$0.0032 00 00
4312" Dia Pump Mob & Demob1JB$0.0032 00 00
4412" Dia Pump & Piping - Weekly3WK$0.0032 00 00
4512" Dia Pump & Piping - Monthly1MO$0.0032 00 00
46Entrance Gate - Double Arm Installation2EA$0.0032 00 00
47Entrance Gate - Single Arm Installation2EA$0.0032 00 00
48Entrance Gate - Double Arm Replacement2EA$0.0032 00 00
49Entrance Gate - Single Arm Replacement2EA$0.0032 00 00
50Entrance Gate - Painting Double Arm5EA$0.0032 00 00
51Entrance Gate - Painting Single Arm5EA$0.0032 00 00
52Bicyle Trail Gate Fabrication & Installation2EA$0.0032 00 00
53Bicyle Trail Gate Fabrication & Replacement1EA$0.0032 00 00
54Concrete Dome Post Installation5EA$0.0032 00 00
55Engineered Wood Chip - Supply10CY$0.0032 00 00
56Engineered Wood Chip - Supply and Placement20CY$0.0032 00 00
57Hardwood Landscape Mulch - Supply10CY$0.0032 00 00
58Hardwood Landscape Mulch - Supply & Placement20CY$0.0032 00 00
59Decorative Boulder Supply and Placement3EA$0.0032 00 00
60Sign Removal, Post Replacement, and Sign Installation Double 4" x 4"10EA$0.0032 00 00
61Sign Removal, Post Replacement, and Sign Installation Double 6" x 6"10EA$0.0032 00 00
62Painting300SQ$0.0032 00 00
63Seamless Epoxy Coatings - Flooring100SF$0.0032 00 00
64Seamless Epoxy Coatings - Walls & Ceiling100SF$0.0032 00 00
65Pavement Raising Portland Cement200LB$0.0032 01 29.62
66Stockpiling - Crushed Stone100TN$0.0032 22 30
67Stockpiling - Gravel100TN$0.0032 22 30
68Stockpiling - Fine Aggregates100TN$0.0032 22 30
69Stockpiling - Drainage Aggregate10TN$0.0032 22 30
70Stockpiling - Type 1 or 5 Aggregate100TN$0.0032 22 30
71Stockpiling - Quarry Run Limestone100TN$0.0032 22 30
72Stockpiling - Limestone500TN$0.0032 22 30
73Placement - Crushed Stone200TN$0.0032 22 30
74Placement - Gravel200TN$0.0032 22 30
75Placement - Fine Aggregates50TN$0.0032 22 30
76Placement - Drainage Aggregate10TN$0.0032 22 30
77Placement - Type 1 or 5 Aggregate1000TN$0.0032 22 30
78Placement - Quarry Run Limestone100TN$0.0032 22 30
79Placement - Limestone1000TN$0.0032 22 30
80Stockpiling - USACE 3" Bedding500TN$0.0032 22 40
81Stockpiling - USACE 50lb Rip Rap500TN$0.0032 22 40
82Stockpiling - USACE 90lb Rip Rap500TN$0.0032 22 40
83Stockpiling - USACE 140lb Rip Rap500TN$0.0032 22 40
84Stockpiling - USACE 400lb Rip Rap500TN$0.0032 22 40
85Stockpiling - USACE 650lb Rip Rap500TN$0.0032 22 40
86Stockpiling - USACE 1000lb Rip Rap500TN$0.0032 22 40
87Placement - USACE 3" Bedding1000TN$0.0032 22 40
88Placement - USACE 50lb Rip Rap1000TN$0.0032 22 40
89Placement - USACE 90lb Rip Rap1000TN$0.0032 22 40
90Placement - USACE 140lb Rip Rap1000TN$0.0032 22 40
91Placement - USACE 400lb Rip Rap1000TN$0.0032 22 40
92Placement - USACE 650lb Rip Rap1000TN$0.0032 22 40
93Placement - USACE 1000lb Rip Rap1000TN$0.0032 22 40
94Patching150SY$0.0032 25 15
95Road Widening150SY$0.0032 25 15
96Asphaltic Concrete Surface2000TN$0.0032 25 15
97Seal Coat1000SY$0.0032 25 15
98Crack Fill/Sealing500GL$0.0032 25 15
99Scrub Seal500SY$0.0032 25 15
100Bituminous Fog Sealing500SY$0.0032 25 15
101Guardrail Replacement200LF$0.0032 25 15
102Guardrail Installation100LF$0.0032 25 15
103Traffic Striping50000LF$0.0032 25 15
104Parking Area Traffic Striping Layout3000LF$0.0032 25 15
105Traffic Marking Arrows3EA$0.0032 25 15
106Traffic Marking Disable Symbol70EA$0.0032 25 15
107Traffic Marking No Parking4EA$0.0032 25 15
108Traffic Marking 5 Minute Parking5EA$0.0032 25 15
109Traffic Marking 10 Minute Parking5EA$0.0032 25 15
110Traffic Marking Tie-Down Only5EA$0.0032 25 15
111Parking Block Removal and Reinstallation50EA$0.0032 25 15
112Parking Block Replacement10EA$0.0032 25 15
113Parking Block Installation10EA$0.0032 25 15
114Establishment of Turf - Large Scale20ACRE$0.0032 29 35
115Establishment of Turf - Small Scale100SY$0.0032 29 35
116Road Bore Drill Setup and Staging1JOB$0.0033 05 23.13
117Road Bore Sleeve 2-inch Dia. HDPE30LF$0.0033 05 23.13
118Road Bore Sleeve 3-inch Dia. HDPE30LF$0.0033 05 23.13
119Road Bore Sleeve 4-inch Dia. HDPE30LF$0.0033 05 23.13
120Road Bore Sleeve 6-inch Dia. HDPE30LF$0.0033 05 23.13
121Road Bore Sleeve 8-inch Dia. HDPE30LF$0.0033 05 23.13
122Frost Proof Yard Hydrant Replacement5EA$0.0033 11 00
123Frost Proof Yard Hydrant Installation5EA$0.0033 11 00
124Water Valve Replacement - 1" curb stop ball valve2EA$0.0033 11 00
125Water Valve Replacement - 1.5" curb stop ball valve2EA$0.0033 11 00
126Water Valve Replacement - 2" square nut ball valve2EA$0.0033 11 00
127Water Valve Replacement - 3" square nut ball valve2EA$0.0033 11 00
128Water Valve Replacement - 4" square nut ball valve2EA$0.0033 11 00
1293/4 Inch Water Line Tap2EA$0.0033 11 00
1301 Inch Water Line Tap2EA$0.0033 11 00
1311-1/2 Inch Water Line Tap2EA$0.0033 11 00
1322 Inch Water Line Tap2EA$0.0033 11 00
1333 Inch Water Line Tap2EA$0.0033 11 00
1344 Inch Water Line Tap2EA$0.0033 11 00
1356 Inch Water Line Tap2EA$0.0033 11 00
1363/4 Inch Water Line Installation100LF$0.0033 11 00
1371 Inch Water Line Installation100LF$0.0033 11 00
1381-1/2 Inch Water Line Installation100LF$0.0033 11 00
1392 Inch Water Line Installation100LF$0.0033 11 00
1402-1/2 Inch Water Line Installation100LF$0.0033 11 00
1413 Inch Water Line Installation100LF$0.0033 11 00
1424 Inch Water Line Installation50LF$0.0033 11 00
1436 Inch Water Line Installation50LF$0.0033 11 00
144Sewer Line Tap 2-5 Feet Deep2EA$0.0033 11 00
145Sewer Line Tap 5.1-10 Feet Deep2EA$0.0033 11 00
146Sewer Line Tap 10.1-15 Feet Deep1EA$0.0033 11 00
1474 Inch Dia. Gravity Sewer Install 0-4 Feet Deep100LF$0.0033 11 00
1484 Inch Dia. Gravity Sewer Install 4.1-10 Feet Deep50LF$0.0033 11 00
1494 Inch Dia. Gravity Sewer Install 10.1-15 Feet Deep20LF$0.0033 11 00
1506 Inch Dia. Gravity Sewer Install 0-4 Feet Deep100LF$0.0033 11 00
1516 Inch Dia. Gravity Sewer Install 4.1-10 Feet Deep50LF$0.0033 11 00
1526 Inch Dia. Gravity Sewer Install 10.1-15 Feet Deep20LF$0.0033 11 00
1538 Inch Dia. Gravity Sewer Install 0-4 Feet Deep100LF$0.0033 11 00
1548 Inch Dia. Gravity Sewer Install 4.1-10 Feet Deep50LF$0.0033 11 00
1558 Inch Dia. Gravity Sewer Install 10.1-15 Feet Deep20LF$0.0033 11 00
1562 Inch Dia. Pressure Sewer Force Main Install50LF$0.0033 11 00
1573 Inch Dia. Pressure Sewer Force Main Install50LF$0.0033 11 00
1584 Inch Dia. Pressure Sewer Force Main Install50LF$0.0033 11 00
1596 Inch Dia. Pressure Sewer Force Main Install20LF$0.0033 11 00
160Manhole Install 1-4 Feet Deep2EA$0.0033 11 00
161Manhole Install 4.1-10 Feet Deep2EA$0.0033 11 00
162Manhole Install 10.1-15 Feet Deep2EA$0.0033 11 00
163CMP 12 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
164CMP 12 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
165CMP 12 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
166CMP 18 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
167CMP 18 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
168CMP 18 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
169CMP 24 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
170CMP 24 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
171CMP 24 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
172CMP 30 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
173CMP 30 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
174CMP 30 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
175CMP 36 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
176CMP 36 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
177CMP 36 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
178CMP 48 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
179CMP 48 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
180CMP 48 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
181CMP 12 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
182CMP 12 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
183CMP 12 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
184CMP 18 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
185CMP 18 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
186CMP 18 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
187CMP 24 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
188CMP 24 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
189CMP 24 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
190CMP 30 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
191CMP 30 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
192CMP 30 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
193CMP 36 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
194CMP 36 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
195CMP 36 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
196CMP 48 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
197CMP 48 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
198CMP 48 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
19912 Inch Dia. End Section Replace4EA$0.0033 40 00
20018 Inch Dia. End Section Replace4EA$0.0033 40 00
20124 Inch Dia. End Section Replace4EA$0.0033 40 00
20230 Inch Dia. End Section Replace4EA$0.0033 40 00
20336 Inch Dia. End Section Replace4EA$0.0033 40 00
20412 Inch Dia. End Section New Install4EA$0.0033 40 00
20518 Inch Dia. End Section New Install4EA$0.0033 40 00
20624 Inch Dia. End Section New Install4EA$0.0033 40 00
20730 Inch Dia. End Section New Install4EA$0.0033 40 00
20836 Inch Dia. End Section New Install4EA$0.0033 40 00
209EQUIPMENT RENTAL WITH OPERATORTBDJOB32 40 00
209aTrack-Type Bulldozers 90HP w/OP100HR$0.0032 40 00
209bTrack-Type Bulldozers 190HP w/OP100HR$0.0032 40 00
209cMotor Grader w/OP100HR$0.0032 40 00
209dBackhoe 60HP w/OP100HR$0.0032 40 00
209eBackhoe 95HP w/OP100HR$0.0032 40 00
209fRubber Tire Front End Loader 120HP w/OP100HR$0.0032 40 00
209gRubber Tire Front End Loader 275HP w/OP100HR$0.0032 40 00
209hDump Truck (Tandem) w/OP100HR$0.0032 40 00
209iDump Truck (Single) w/OP100HR$0.0032 40 00
209jSemi-Tractor Trailer w/OP100HR$0.0032 40 00
209kBucket Truck w/OP.100HR$0.0032 40 00
209lTruck Crane w/OP100HR$0.0032 40 00
209mMini-Excavator w/OP100HR$0.0032 40 00
209nExcavator 50hp w/OP100HR$0.0032 40 00
209oExcavator 155hp w/OP100HR$0.0032 40 00
209pExcavator 242hp w/OP100HR$0.0032 40 00
209qWalk behind Concrete Saw w/OP100HR$0.0032 40 00
209rSelf-propelled Drum Vibrating Roller w/OP100HR$0.0032 40 00
209sSelf-propelled Sheepsfoot Roller w/OP100HR$0.0032 40 00
209tSkid Steer Loader w/OP100HR$0.0032 40 00
209uTractor with Boom Mower w/OP100HR$0.0032 40 00
209vSmall Tractor w/OP100HR$0.0032 40 00
209wLarge Tractor w/OP100HR$0.0032 40 00
209xTractor & Pan w/OP100HR$0.0032 40 00
209yAsphalt Miller w/OP100HR$0.0032 40 00
210Rental of Miscellaneous Equipment with OperatorTBDTBD32 40 00
211SPECIALTY EQUIPMENTTBDJOB32 40 00
211aPortable Diesel Air Compressor100HR$0.0032 40 00
211bTrailer Mounted Concrete Pump100HR$0.0032 40 00
211cTrencher100HR$0.0032 40 00
211dLight Towers100HR$0.0032 40 00
211eChainsaw100HR$0.0032 40 00
211fPower Washer100HR$0.0032 40 00
211gHand Operated Electric Power Jack Hammer100HR$0.0032 40 00
211hHand Operated Air Powered Jack Hammer100HR$0.0032 40 00
211iHand Operated Air Powered Chipping Hammer100HR$0.0032 40 00
211jVibratory Plate Tamper100HR$0.0032 40 00
211kHand Operated Power Cutoff Saw100HR$0.0032 40 00
211lHand Operated Power Hammer Drill w/Bits100HR$0.0032 40 00
211mHand Operated Air Powered Core Drill w/Bits100HR$0.0032 40 00
211nConcrete Saw100HR$0.0032 40 00
212Rental of Miscellaneous Equipment without OperatorTBDTBD32 40 00
213LABOR SUPPORTTBDJOB32 40 00
213aSurveyor100HR$0.0032 40 00
213bGeneral Engineer100HR$0.0032 40 00
213cDrafter/CADD Technician100HR$0.0032 40 00
213dPlumber100HR$0.0032 40 00
213eElectrician100HR$0.0032 40 00
213fHVAC Technician100HR$0.0032 40 00
213gLaborer100HR$0.0032 40 00
213hIron Worker100HR$0.0032 40 00
213iCarpenter100HR$0.0032 40 00
213jCement Mason100HR$0.0032 40 00
213kWelder Type I with Welding Equipment100HR$0.0032 40 00
213lWelder Type II with Welding Equipment100HR$0.0032 40 00
214Procurement and Delivery of Miscellaneous MaterialsTBDTBD32 40 00
TOTAL ORDERING PERIOD 1$0.00

BID SCHEDULE - ORDERING PERIOD 2

FACILITY INFRASTRUCTURE CONSTRUCTION AND MAINTENANCE IDIQ

ORDERING PERIOD DURATION: 1 MAR 2025 - 28 FEB 2026

ORDERING PERIOD 2
Pre-Priced Line ItemDescriptionEstimated
QuantityUOMUnit PriceEstimated
AmountTechnical

Section

1Concrete Slab: 4-inch200SF$0.0003 30 00
2Concrete Slab: 6-inch200SF$0.0003 30 00
3Concrete Slab: 8-inch100SF$0.0003 30 00
4Concrete Slab: 10-inch100SF$0.0003 30 00
5Concrete Ditch: 4-inch200SF$0.0003 30 00
6Concrete Curb & Gutter1000LF$0.0003 30 00
7Concrete Barrier Curbs1000LF$0.0003 30 00
8Concrete Mountable Curbs1000LF$0.0003 30 00
9Reinforcement500LB$0.0003 30 00
10Miscellaneous Concrete WorkTBDTBD03 30 00.99
11Clearing and Grubbing: Light5000SY$0.0031 00 00
12Clearing and Grubbing: Heavy5000SY$0.0031 00 00
13Fill Material1000CY$0.0031 00 00
14Earthwork - Berm Construction2000CY$0.0031 00 00
15Earthwork - Light Field/Site Grading2000CY$0.0031 00 00
16Earthwork - Heavy Field/Site Grading2000CY$0.0031 00 00
17Earthwork - Slough Construction2000CY$0.0031 00 00
18Earthwork - Pavement Subgrade1000CY$0.0031 00 00
19Excess Earthwork Disposal200CY$0.0031 00 00
20Top Soil800CY$0.0031 00 00
21Geotextile Installation - Woven100SY$0.0031 05 19.13
22Geotextile Installation - Non Woven100SY$0.0031 05 19.13
23Concrete Removal200CY$0.0032 00 00
24Concrete Removal Structures & Foundations200CY$0.0032 00 00
25Asphalt Removal200CY$0.0032 00 00
26Removal of Aggregates200CY$0.0032 00 00
27Disposal of Misc.500LB$0.0032 00 00
28Right of Way Clearing50MILE$0.0032 00 00
29Tree TrimmingTBDJOB32 00 00
29aTree Trimming Low20HR$0.0032 00 00
29bTree Trimming High20HR$0.0032 00 00
30Tree Removal - Light10EA$0.0032 00 00
31Tree Removal - Heavy10EA$0.0032 00 00
32Stump Removal - Light10EA$0.0032 00 00
33Stump Removal - Heavy10EA$0.0032 00 00
34Landscape Timbers Installation50LF$0.0032 00 00
35Landscape Timber Removal20LF$0.0032 00 00
36Sand Supply100TN$0.0032 00 00
37Beach Sand Supply & Install200TN$0.0032 00 00
38Redman Creek Beach - Maintenance1JB$0.0032 00 00
39Rockwood Beach - Maintenance1JB$0.0032 00 00
40Peoples Creek Beach - Maintenance1JB$0.0032 00 00
41Greenville Berm Notch Construction1JB$0.0032 00 00
42Greenville Berm Notch Removal1JB$0.0032 00 00
4312" Dia Pump Mob & Demob1JB$0.0032 00 00
4412" Dia Pump & Piping - Weekly3WK$0.0032 00 00
4512" Dia Pump & Piping - Monthly1MO$0.0032 00 00
46Entrance Gate - Double Arm Installation2EA$0.0032 00 00
47Entrance Gate - Single Arm Installation2EA$0.0032 00 00
48Entrance Gate - Double Arm Replacement2EA$0.0032 00 00
49Entrance Gate - Single Arm Replacement2EA$0.0032 00 00
50Entrance Gate - Painting Double Arm5EA$0.0032 00 00
51Entrance Gate - Painting Single Arm5EA$0.0032 00 00
52Bicyle Trail Gate Fabrication & Installation2EA$0.0032 00 00
53Bicyle Trail Gate Fabrication & Replacement1EA$0.0032 00 00
54Concrete Dome Post Installation5EA$0.0032 00 00
55Engineered Wood Chip - Supply10CY$0.0032 00 00
56Engineered Wood Chip - Supply and Placement20CY$0.0032 00 00
57Hardwood Landscape Mulch - Supply10CY$0.0032 00 00
58Hardwood Landscape Mulch - Supply & Placement20CY$0.0032 00 00
59Decorative Boulder Supply and Placement3EA$0.0032 00 00
60Sign Removal, Post Replacement, and Sign Installation Double 4" x 4"10EA$0.0032 00 00
61Sign Removal, Post Replacement, and Sign Installation Double 6" x 6"10EA$0.0032 00 00
62Painting300SQ$0.0032 00 00
63Seamless Epoxy Coatings - Flooring100SF$0.0032 00 00
64Seamless Epoxy Coatings - Walls & Ceiling100SF$0.0032 00 00
65Pavement Raising Portland Cement200LB$0.0032 01 29.62
66Stockpiling - Crushed Stone100TN$0.0032 22 30
67Stockpiling - Gravel100TN$0.0032 22 30
68Stockpiling - Fine Aggregates100TN$0.0032 22 30
69Stockpiling - Drainage Aggregate10TN$0.0032 22 30
70Stockpiling - Type 1 or 5 Aggregate100TN$0.0032 22 30
71Stockpiling - Quarry Run Limestone100TN$0.0032 22 30
72Stockpiling - Limestone500TN$0.0032 22 30
73Placement - Crushed Stone200TN$0.0032 22 30
74Placement - Gravel200TN$0.0032 22 30
75Placement - Fine Aggregates50TN$0.0032 22 30
76Placement - Drainage Aggregate10TN$0.0032 22 30
77Placement - Type 1 or 5 Aggregate1000TN$0.0032 22 30
78Placement - Quarry Run Limestone100TN$0.0032 22 30
79Placement - Limestone1000TN$0.0032 22 30
80Stockpiling - USACE 3" Bedding500TN$0.0032 22 40
81Stockpiling - USACE 50lb Rip Rap500TN$0.0032 22 40
82Stockpiling - USACE 90lb Rip Rap500TN$0.0032 22 40
83Stockpiling - USACE 140lb Rip Rap500TN$0.0032 22 40
84Stockpiling - USACE 400lb Rip Rap500TN$0.0032 22 40
85Stockpiling - USACE 650lb Rip Rap500TN$0.0032 22 40
86Stockpiling - USACE 1000lb Rip Rap500TN$0.0032 22 40
87Placement - USACE 3" Bedding1000TN$0.0032 22 40
88Placement - USACE 50lb Rip Rap1000TN$0.0032 22 40
89Placement - USACE 90lb Rip Rap1000TN$0.0032 22 40
90Placement - USACE 140lb Rip Rap1000TN$0.0032 22 40
91Placement - USACE 400lb Rip Rap1000TN$0.0032 22 40
92Placement - USACE 650lb Rip Rap1000TN$0.0032 22 40
93Placement - USACE 1000lb Rip Rap1000TN$0.0032 22 40
94Patching150SY$0.0032 25 15
95Road Widening150SY$0.0032 25 15
96Asphaltic Concrete Surface2000TN$0.0032 25 15
97Seal Coat1000SY$0.0032 25 15
98Crack Fill/Sealing500GL$0.0032 25 15
99Scrub Seal500SY$0.0032 25 15
100Bituminous Fog Sealing500SY$0.0032 25 15
101Guardrail Replacement200LF$0.0032 25 15
102Guardrail Installation100LF$0.0032 25 15
103Traffic Striping50000LF$0.0032 25 15
104Parking Area Traffic Striping Layout3000LF$0.0032 25 15
105Traffic Marking Arrows3EA$0.0032 25 15
106Traffic Marking Disable Symbol70EA$0.0032 25 15
107Traffic Marking No Parking4EA$0.0032 25 15
108Traffic Marking 5 Minute Parking5EA$0.0032 25 15
109Traffic Marking 10 Minute Parking5EA$0.0032 25 15
110Traffic Marking Tie-Down Only5EA$0.0032 25 15
111Parking Block Removal and Reinstallation50EA$0.0032 25 15
112Parking Block Replacement10EA$0.0032 25 15
113Parking Block Installation10EA$0.0032 25 15
114Establishment of Turf - Large Scale20ACRE$0.0032 29 35
115Establishment of Turf - Small Scale100SY$0.0032 29 35
116Road Bore Drill Setup and Staging1JOB$0.0033 05 23.13
117Road Bore Sleeve 2-inch Dia. HDPE30LF$0.0033 05 23.13
118Road Bore Sleeve 3-inch Dia. HDPE30LF$0.0033 05 23.13
119Road Bore Sleeve 4-inch Dia. HDPE30LF$0.0033 05 23.13
120Road Bore Sleeve 6-inch Dia. HDPE30LF$0.0033 05 23.13
121Road Bore Sleeve 8-inch Dia. HDPE30LF$0.0033 05 23.13
122Frost Proof Yard Hydrant Replacement5EA$0.0033 11 00
123Frost Proof Yard Hydrant Installation5EA$0.0033 11 00
124Water Valve Replacement - 1" curb stop ball valve2EA$0.0033 11 00
125Water Valve Replacement - 1.5" curb stop ball valve2EA$0.0033 11 00
126Water Valve Replacement - 2" square nut ball valve2EA$0.0033 11 00
127Water Valve Replacement - 3" square nut ball valve2EA$0.0033 11 00
128Water Valve Replacement - 4" square nut ball valve2EA$0.0033 11 00
1293/4 Inch Water Line Tap2EA$0.0033 11 00
1301 Inch Water Line Tap2EA$0.0033 11 00
1311-1/2 Inch Water Line Tap2EA$0.0033 11 00
1322 Inch Water Line Tap2EA$0.0033 11 00
1333 Inch Water Line Tap2EA$0.0033 11 00
1344 Inch Water Line Tap2EA$0.0033 11 00
1356 Inch Water Line Tap2EA$0.0033 11 00
1363/4 Inch Water Line Installation100LF$0.0033 11 00
1371 Inch Water Line Installation100LF$0.0033 11 00
1381-1/2 Inch Water Line Installation100LF$0.0033 11 00
1392 Inch Water Line Installation100LF$0.0033 11 00
1402-1/2 Inch Water Line Installation100LF$0.0033 11 00
1413 Inch Water Line Installation100LF$0.0033 11 00
1424 Inch Water Line Installation50LF$0.0033 11 00
1436 Inch Water Line Installation50LF$0.0033 11 00
144Sewer Line Tap 2-5 Feet Deep2EA$0.0033 11 00
145Sewer Line Tap 5.1-10 Feet Deep2EA$0.0033 11 00
146Sewer Line Tap 10.1-15 Feet Deep1EA$0.0033 11 00
1474 Inch Dia. Gravity Sewer Install 0-4 Feet Deep100LF$0.0033 11 00
1484 Inch Dia. Gravity Sewer Install 4.1-10 Feet Deep50LF$0.0033 11 00
1494 Inch Dia. Gravity Sewer Install 10.1-15 Feet Deep20LF$0.0033 11 00
1506 Inch Dia. Gravity Sewer Install 0-4 Feet Deep100LF$0.0033 11 00
1516 Inch Dia. Gravity Sewer Install 4.1-10 Feet Deep50LF$0.0033 11 00
1526 Inch Dia. Gravity Sewer Install 10.1-15 Feet Deep20LF$0.0033 11 00
1538 Inch Dia. Gravity Sewer Install 0-4 Feet Deep100LF$0.0033 11 00
1548 Inch Dia. Gravity Sewer Install 4.1-10 Feet Deep50LF$0.0033 11 00
1558 Inch Dia. Gravity Sewer Install 10.1-15 Feet Deep20LF$0.0033 11 00
1562 Inch Dia. Pressure Sewer Force Main Install50LF$0.0033 11 00
1573 Inch Dia. Pressure Sewer Force Main Install50LF$0.0033 11 00
1584 Inch Dia. Pressure Sewer Force Main Install50LF$0.0033 11 00
1596 Inch Dia. Pressure Sewer Force Main Install20LF$0.0033 11 00
160Manhole Install 1-4 Feet Deep2EA$0.0033 11 00
161Manhole Install 4.1-10 Feet Deep2EA$0.0033 11 00
162Manhole Install 10.1-15 Feet Deep2EA$0.0033 11 00
163CMP 12 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
164CMP 12 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
165CMP 12 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
166CMP 18 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
167CMP 18 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
168CMP 18 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
169CMP 24 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
170CMP 24 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
171CMP 24 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
172CMP 30 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
173CMP 30 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
174CMP 30 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
175CMP 36 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
176CMP 36 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
177CMP 36 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
178CMP 48 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
179CMP 48 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
180CMP 48 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
181CMP 12 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
182CMP 12 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
183CMP 12 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
184CMP 18 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
185CMP 18 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
186CMP 18 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
187CMP 24 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
188CMP 24 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
189CMP 24 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
190CMP 30 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
191CMP 30 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
192CMP 30 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
193CMP 36 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
194CMP 36 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
195CMP 36 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
196CMP 48 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
197CMP 48 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
198CMP 48 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
19912 Inch Dia. End Section Replace4EA$0.0033 40 00
20018 Inch Dia. End Section Replace4EA$0.0033 40 00
20124 Inch Dia. End Section Replace4EA$0.0033 40 00
20230 Inch Dia. End Section Replace4EA$0.0033 40 00
20336 Inch Dia. End Section Replace4EA$0.0033 40 00
20412 Inch Dia. End Section New Install4EA$0.0033 40 00
20518 Inch Dia. End Section New Install4EA$0.0033 40 00
20624 Inch Dia. End Section New Install4EA$0.0033 40 00
20730 Inch Dia. End Section New Install4EA$0.0033 40 00
20836 Inch Dia. End Section New Install4EA$0.0033 40 00
209EQUIPMENT RENTAL WITH OPERATORTBDJOB32 40 00
209aTrack-Type Bulldozers 90HP w/OP100HR$0.0032 40 00
209bTrack-Type Bulldozers 190HP w/OP100HR$0.0032 40 00
209cMotor Grader w/OP100HR$0.0032 40 00
209dBackhoe 60HP w/OP100HR$0.0032 40 00
209eBackhoe 95HP w/OP100HR$0.0032 40 00
209fRubber Tire Front End Loader 120HP w/OP100HR$0.0032 40 00
209gRubber Tire Front End Loader 275HP w/OP100HR$0.0032 40 00
209hDump Truck (Tandem) w/OP100HR$0.0032 40 00
209iDump Truck (Single) w/OP100HR$0.0032 40 00
209jSemi-Tractor Trailer w/OP100HR$0.0032 40 00
209kBucket Truck w/OP.100HR$0.0032 40 00
209lTruck Crane w/OP100HR$0.0032 40 00
209mMini-Excavator w/OP100HR$0.0032 40 00
209nExcavator 50hp w/OP100HR$0.0032 40 00
209oExcavator 155hp w/OP100HR$0.0032 40 00
209pExcavator 242hp w/OP100HR$0.0032 40 00
209qWalk behind Concrete Saw w/OP100HR$0.0032 40 00
209rSelf-propelled Drum Vibrating Roller w/OP100HR$0.0032 40 00
209sSelf-propelled Sheepsfoot Roller w/OP100HR$0.0032 40 00
209tSkid Steer Loader w/OP100HR$0.0032 40 00
209uTractor with Boom Mower w/OP100HR$0.0032 40 00
209vSmall Tractor w/OP100HR$0.0032 40 00
209wLarge Tractor w/OP100HR$0.0032 40 00
209xTractor & Pan w/OP100HR$0.0032 40 00
209yAsphalt Miller w/OP100HR$0.0032 40 00
210Rental of Miscellaneous Equipment with OperatorTBDTBD32 40 00
211SPECIALTY EQUIPMENTTBDJOB32 40 00
211aPortable Diesel Air Compressor100HR$0.0032 40 00
211bTrailer Mounted Concrete Pump100HR$0.0032 40 00
211cTrencher100HR$0.0032 40 00
211dLight Towers100HR$0.0032 40 00
211eChainsaw100HR$0.0032 40 00
211fPower Washer100HR$0.0032 40 00
211gHand Operated Electric Power Jack Hammer100HR$0.0032 40 00
211hHand Operated Air Powered Jack Hammer100HR$0.0032 40 00
211iHand Operated Air Powered Chipping Hammer100HR$0.0032 40 00
211jVibratory Plate Tamper100HR$0.0032 40 00
211kHand Operated Power Cutoff Saw100HR$0.0032 40 00
211lHand Operated Power Hammer Drill w/Bits100HR$0.0032 40 00
211mHand Operated Air Powered Core Drill w/Bits100HR$0.0032 40 00
211nConcrete Saw100HR$0.0032 40 00
212Rental of Miscellaneous Equipment without OperatorTBDTBD32 40 00
213LABOR SUPPORTTBDJOB32 40 00
213aSurveyor100HR$0.0032 40 00
213bGeneral Engineer100HR$0.0032 40 00
213cDrafter/CADD Technician100HR$0.0032 40 00
213dPlumber100HR$0.0032 40 00
213eElectrician100HR$0.0032 40 00
213fHVAC Technician100HR$0.0032 40 00
213gLaborer100HR$0.0032 40 00
213hIron Worker100HR$0.0032 40 00
213iCarpenter100HR$0.0032 40 00
213jCement Mason100HR$0.0032 40 00
213kWelder Type I with Welding Equipment100HR$0.0032 40 00
213lWelder Type II with Welding Equipment100HR$0.0032 40 00
214Procurement and Delivery of Miscellaneous MaterialsTBDTBD32 40 00
TOTAL ORDERING PERIOD 2$0.00

BID SCHEDULE - ORDERING PERIOD 3

FACILITY INFRASTRUCTURE CONSTRUCTION AND MAINTENANCE IDIQ

ORDERING PERIOD DURATION: 1 MAR 2026 - 28 FEB 2027

ORDERING PERIOD 3
Pre-Priced Line ItemDescriptionEstimated
QuantityUOMUnit PriceEstimated
AmountTechnical

Section

1Concrete Slab: 4-inch200SF$0.0003 30 00
2Concrete Slab: 6-inch200SF$0.0003 30 00
3Concrete Slab: 8-inch100SF$0.0003 30 00
4Concrete Slab: 10-inch100SF$0.0003 30 00
5Concrete Ditch: 4-inch200SF$0.0003 30 00
6Concrete Curb & Gutter1000LF$0.0003 30 00
7Concrete Barrier Curbs1000LF$0.0003 30 00
8Concrete Mountable Curbs1000LF$0.0003 30 00
9Reinforcement500LB$0.0003 30 00
10Miscellaneous Concrete WorkTBDTBD03 30 00.99
11Clearing and Grubbing: Light5000SY$0.0031 00 00
12Clearing and Grubbing: Heavy5000SY$0.0031 00 00
13Fill Material1000CY$0.0031 00 00
14Earthwork - Berm Construction2000CY$0.0031 00 00
15Earthwork - Light Field/Site Grading2000CY$0.0031 00 00
16Earthwork - Heavy Field/Site Grading2000CY$0.0031 00 00
17Earthwork - Slough Construction2000CY$0.0031 00 00
18Earthwork - Pavement Subgrade1000CY$0.0031 00 00
19Excess Earthwork Disposal200CY$0.0031 00 00
20Top Soil800CY$0.0031 00 00
21Geotextile Installation - Woven100SY$0.0031 05 19.13
22Geotextile Installation - Non Woven100SY$0.0031 05 19.13
23Concrete Removal200CY$0.0032 00 00
24Concrete Removal Structures & Foundations200CY$0.0032 00 00
25Asphalt Removal200CY$0.0032 00 00
26Removal of Aggregates200CY$0.0032 00 00
27Disposal of Misc.500LB$0.0032 00 00
28Right of Way Clearing50MILE$0.0032 00 00
29Tree TrimmingTBDJOB32 00 00
29aTree Trimming Low20HR$0.0032 00 00
29bTree Trimming High20HR$0.0032 00 00
30Tree Removal - Light10EA$0.0032 00 00
31Tree Removal - Heavy10EA$0.0032 00 00
32Stump Removal - Light10EA$0.0032 00 00
33Stump Removal - Heavy10EA$0.0032 00 00
34Landscape Timbers Installation50LF$0.0032 00 00
35Landscape Timber Removal20LF$0.0032 00 00
36Sand Supply100TN$0.0032 00 00
37Beach Sand Supply & Install200TN$0.0032 00 00
38Redman Creek Beach - Maintenance1JB$0.0032 00 00
39Rockwood Beach - Maintenance1JB$0.0032 00 00
40Peoples Creek Beach - Maintenance1JB$0.0032 00 00
41Greenville Berm Notch Construction1JB$0.0032 00 00
42Greenville Berm Notch Removal1JB$0.0032 00 00
4312" Dia Pump Mob & Demob1JB$0.0032 00 00
4412" Dia Pump & Piping - Weekly3WK$0.0032 00 00
4512" Dia Pump & Piping - Monthly1MO$0.0032 00 00
46Entrance Gate - Double Arm Installation2EA$0.0032 00 00
47Entrance Gate - Single Arm Installation2EA$0.0032 00 00
48Entrance Gate - Double Arm Replacement2EA$0.0032 00 00
49Entrance Gate - Single Arm Replacement2EA$0.0032 00 00
50Entrance Gate - Painting Double Arm5EA$0.0032 00 00
51Entrance Gate - Painting Single Arm5EA$0.0032 00 00
52Bicyle Trail Gate Fabrication & Installation2EA$0.0032 00 00
53Bicyle Trail Gate Fabrication & Replacement1EA$0.0032 00 00
54Concrete Dome Post Installation5EA$0.0032 00 00
55Engineered Wood Chip - Supply10CY$0.0032 00 00
56Engineered Wood Chip - Supply and Placement20CY$0.0032 00 00
57Hardwood Landscape Mulch - Supply10CY$0.0032 00 00
58Hardwood Landscape Mulch - Supply & Placement20CY$0.0032 00 00
59Decorative Boulder Supply and Placement3EA$0.0032 00 00
60Sign Removal, Post Replacement, and Sign Installation Double 4" x 4"10EA$0.0032 00 00
61Sign Removal, Post Replacement, and Sign Installation Double 6" x 6"10EA$0.0032 00 00
62Painting300SQ$0.0032 00 00
63Seamless Epoxy Coatings - Flooring100SF$0.0032 00 00
64Seamless Epoxy Coatings - Walls & Ceiling100SF$0.0032 00 00
65Pavement Raising Portland Cement200LB$0.0032 01 29.62
66Stockpiling - Crushed Stone100TN$0.0032 22 30
67Stockpiling - Gravel100TN$0.0032 22 30
68Stockpiling - Fine Aggregates100TN$0.0032 22 30
69Stockpiling - Drainage Aggregate10TN$0.0032 22 30
70Stockpiling - Type 1 or 5 Aggregate100TN$0.0032 22 30
71Stockpiling - Quarry Run Limestone100TN$0.0032 22 30
72Stockpiling - Limestone500TN$0.0032 22 30
73Placement - Crushed Stone200TN$0.0032 22 30
74Placement - Gravel200TN$0.0032 22 30
75Placement - Fine Aggregates50TN$0.0032 22 30
76Placement - Drainage Aggregate10TN$0.0032 22 30
77Placement - Type 1 or 5 Aggregate1000TN$0.0032 22 30
78Placement - Quarry Run Limestone100TN$0.0032 22 30
79Placement - Limestone1000TN$0.0032 22 30
80Stockpiling - USACE 3" Bedding500TN$0.0032 22 40
81Stockpiling - USACE 50lb Rip Rap500TN$0.0032 22 40
82Stockpiling - USACE 90lb Rip Rap500TN$0.0032 22 40
83Stockpiling - USACE 140lb Rip Rap500TN$0.0032 22 40
84Stockpiling - USACE 400lb Rip Rap500TN$0.0032 22 40
85Stockpiling - USACE 650lb Rip Rap500TN$0.0032 22 40
86Stockpiling - USACE 1000lb Rip Rap500TN$0.0032 22 40
87Placement - USACE 3" Bedding1000TN$0.0032 22 40
88Placement - USACE 50lb Rip Rap1000TN$0.0032 22 40
89Placement - USACE 90lb Rip Rap1000TN$0.0032 22 40
90Placement - USACE 140lb Rip Rap1000TN$0.0032 22 40
91Placement - USACE 400lb Rip Rap1000TN$0.0032 22 40
92Placement - USACE 650lb Rip Rap1000TN$0.0032 22 40
93Placement - USACE 1000lb Rip Rap1000TN$0.0032 22 40
94Patching150SY$0.0032 25 15
95Road Widening150SY$0.0032 25 15
96Asphaltic Concrete Surface2000TN$0.0032 25 15
97Seal Coat1000SY$0.0032 25 15
98Crack Fill/Sealing500GL$0.0032 25 15
99Scrub Seal500SY$0.0032 25 15
100Bituminous Fog Sealing500SY$0.0032 25 15
101Guardrail Replacement200LF$0.0032 25 15
102Guardrail Installation100LF$0.0032 25 15
103Traffic Striping50000LF$0.0032 25 15
104Parking Area Traffic Striping Layout3000LF$0.0032 25 15
105Traffic Marking Arrows3EA$0.0032 25 15
106Traffic Marking Disable Symbol70EA$0.0032 25 15
107Traffic Marking No Parking4EA$0.0032 25 15
108Traffic Marking 5 Minute Parking5EA$0.0032 25 15
109Traffic Marking 10 Minute Parking5EA$0.0032 25 15
110Traffic Marking Tie-Down Only5EA$0.0032 25 15
111Parking Block Removal and Reinstallation50EA$0.0032 25 15
112Parking Block Replacement10EA$0.0032 25 15
113Parking Block Installation10EA$0.0032 25 15
114Establishment of Turf - Large Scale20ACRE$0.0032 29 35
115Establishment of Turf - Small Scale100SY$0.0032 29 35
116Road Bore Drill Setup and Staging1JOB$0.0033 05 23.13
117Road Bore Sleeve 2-inch Dia. HDPE30LF$0.0033 05 23.13
118Road Bore Sleeve 3-inch Dia. HDPE30LF$0.0033 05 23.13
119Road Bore Sleeve 4-inch Dia. HDPE30LF$0.0033 05 23.13
120Road Bore Sleeve 6-inch Dia. HDPE30LF$0.0033 05 23.13
121Road Bore Sleeve 8-inch Dia. HDPE30LF$0.0033 05 23.13
122Frost Proof Yard Hydrant Replacement5EA$0.0033 11 00
123Frost Proof Yard Hydrant Installation5EA$0.0033 11 00
124Water Valve Replacement - 1" curb stop ball valve2EA$0.0033 11 00
125Water Valve Replacement - 1.5" curb stop ball valve2EA$0.0033 11 00
126Water Valve Replacement - 2" square nut ball valve2EA$0.0033 11 00
127Water Valve Replacement - 3" square nut ball valve2EA$0.0033 11 00
128Water Valve Replacement - 4" square nut ball valve2EA$0.0033 11 00
1293/4 Inch Water Line Tap2EA$0.0033 11 00
1301 Inch Water Line Tap2EA$0.0033 11 00
1311-1/2 Inch Water Line Tap2EA$0.0033 11 00
1322 Inch Water Line Tap2EA$0.0033 11 00
1333 Inch Water Line Tap2EA$0.0033 11 00
1344 Inch Water Line Tap2EA$0.0033 11 00
1356 Inch Water Line Tap2EA$0.0033 11 00
1363/4 Inch Water Line Installation100LF$0.0033 11 00
1371 Inch Water Line Installation100LF$0.0033 11 00
1381-1/2 Inch Water Line Installation100LF$0.0033 11 00
1392 Inch Water Line Installation100LF$0.0033 11 00
1402-1/2 Inch Water Line Installation100LF$0.0033 11 00
1413 Inch Water Line Installation100LF$0.0033 11 00
1424 Inch Water Line Installation50LF$0.0033 11 00
1436 Inch Water Line Installation50LF$0.0033 11 00
144Sewer Line Tap 2-5 Feet Deep2EA$0.0033 11 00
145Sewer Line Tap 5.1-10 Feet Deep2EA$0.0033 11 00
146Sewer Line Tap 10.1-15 Feet Deep1EA$0.0033 11 00
1474 Inch Dia. Gravity Sewer Install 0-4 Feet Deep100LF$0.0033 11 00
1484 Inch Dia. Gravity Sewer Install 4.1-10 Feet Deep50LF$0.0033 11 00
1494 Inch Dia. Gravity Sewer Install 10.1-15 Feet Deep20LF$0.0033 11 00
1506 Inch Dia. Gravity Sewer Install 0-4 Feet Deep100LF$0.0033 11 00
1516 Inch Dia. Gravity Sewer Install 4.1-10 Feet Deep50LF$0.0033 11 00
1526 Inch Dia. Gravity Sewer Install 10.1-15 Feet Deep20LF$0.0033 11 00
1538 Inch Dia. Gravity Sewer Install 0-4 Feet Deep100LF$0.0033 11 00
1548 Inch Dia. Gravity Sewer Install 4.1-10 Feet Deep50LF$0.0033 11 00
1558 Inch Dia. Gravity Sewer Install 10.1-15 Feet Deep20LF$0.0033 11 00
1562 Inch Dia. Pressure Sewer Force Main Install50LF$0.0033 11 00
1573 Inch Dia. Pressure Sewer Force Main Install50LF$0.0033 11 00
1584 Inch Dia. Pressure Sewer Force Main Install50LF$0.0033 11 00
1596 Inch Dia. Pressure Sewer Force Main Install20LF$0.0033 11 00
160Manhole Install 1-4 Feet Deep2EA$0.0033 11 00
161Manhole Install 4.1-10 Feet Deep2EA$0.0033 11 00
162Manhole Install 10.1-15 Feet Deep2EA$0.0033 11 00
163CMP 12 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
164CMP 12 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
165CMP 12 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
166CMP 18 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
167CMP 18 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
168CMP 18 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
169CMP 24 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
170CMP 24 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
171CMP 24 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
172CMP 30 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
173CMP 30 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
174CMP 30 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
175CMP 36 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
176CMP 36 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
177CMP 36 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
178CMP 48 Inch Dia. Pipe Replace, 0-4.9 Ft Depth20LF$0.0033 40 00
179CMP 48 Inch Dia. Pipe Replace, 5-9.9 Ft Depth20LF$0.0033 40 00
180CMP 48 Inch Dia. Pipe Replace, 10-15 Ft Depth20LF$0.0033 40 00
181CMP 12 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
182CMP 12 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
183CMP 12 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
184CMP 18 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
185CMP 18 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
186CMP 18 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
187CMP 24 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
188CMP 24 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
189CMP 24 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
190CMP 30 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
191CMP 30 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
192CMP 30 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
193CMP 36 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
194CMP 36 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
195CMP 36 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
196CMP 48 Inch Dia. Pipe New Install, 0-4.9 Ft Depth20LF$0.0033 40 00
197CMP 48 Inch Dia. Pipe New Install, 5-9.9 Ft Depth20LF$0.0033 40 00
198CMP 48 Inch Dia. Pipe New Install, 10-15 Ft Depth20LF$0.0033 40 00
19912 Inch Dia. End Section Replace4EA$0.0033 40 00
20018 Inch Dia. End Section Replace4EA$0.0033 40 00
20124 Inch Dia. End Section Replace4EA$0.0033 40 00
20230 Inch Dia. End Section Replace4EA$0.0033 40 00
20336 Inch Dia. End Section Replace4EA$0.0033 40 00
20412 Inch Dia. End Section New Install4EA$0.0033 40 00
20518 Inch Dia. End Section New Install4EA$0.0033 40 00
20624 Inch Dia. End Section New Install4EA$0.0033 40 00
20730 Inch Dia. End Section New Install4EA$0.0033 40 00
20836 Inch Dia. End Section New Install4EA$0.0033 40 00
209EQUIPMENT RENTAL WITH OPERATORTBDJOB32 40 00
209aTrack-Type Bulldozers 90HP w/OP100HR$0.0032 40 00
209bTrack-Type Bulldozers 190HP w/OP100HR$0.0032 40 00
209cMotor Grader w/OP100HR$0.0032 40 00
209dBackhoe 60HP w/OP100HR$0.0032 40 00
209eBackhoe 95HP w/OP100HR$0.0032 40 00
209fRubber Tire Front End Loader 120HP w/OP100HR$0.0032 40 00
209gRubber Tire Front End Loader 275HP w/OP100HR$0.0032 40 00
209hDump Truck (Tandem) w/OP100HR$0.0032 40 00
209iDump Truck (Single) w/OP100HR$0.0032 40 00
209jSemi-Tractor Trailer w/OP100HR$0.0032 40 00
209kBucket Truck w/OP.100HR$0.0032 40 00
209lTruck Crane w/OP100HR$0.0032 40 00
209mMini-Excavator w/OP100HR$0.0032 40 00
209nExcavator 50hp w/OP100HR$0.0032 40 00
209oExcavator 155hp w/OP100HR$0.0032 40 00
209pExcavator 242hp w/OP100HR$0.0032 40 00
209qWalk behind Concrete Saw w/OP100HR$0.0032 40 00
209rSelf-propelled Drum Vibrating Roller w/OP100HR$0.0032 40 00
209sSelf-propelled Sheepsfoot Roller w/OP100HR$0.0032 40 00
209tSkid Steer Loader w/OP100HR$0.0032 40 00
209uTractor with Boom Mower w/OP100HR$0.0032 40 00
209vSmall Tractor w/OP100HR$0.0032 40 00
209wLarge Tractor w/OP100HR$0.0032 40 00
209xTractor & Pan w/OP100HR$0.0032 40 00
209yAsphalt Miller w/OP100HR$0.0032 40 00
210Rental of Miscellaneous Equipment with OperatorTBDTBD32 40 00
211SPECIALTY EQUIPMENTTBDJOB32 40 00
211aPortable Diesel Air Compressor100HR$0.0032 40 00
211bTrailer Mounted Concrete Pump100HR$0.0032 40 00
211cTrencher100HR$0.0032 40 00
211dLight Towers100HR$0.0032 40 00
211eChainsaw100HR$0.0032 40 00
211fPower Washer100HR$0.0032 40 00
211gHand Operated Electric Power Jack Hammer100HR$0.0032 40 00
211hHand Operated Air Powered Jack Hammer100HR$0.0032 40 00
211iHand Operated Air Powered Chipping Hammer100HR$0.0032 40 00
211jVibratory Plate Tamper100HR$0.0032 40 00
211kHand Operated Power Cutoff Saw100HR$0.0032 40 00
211lHand Operated Power Hammer Drill w/Bits100HR$0.0032 40 00
211mHand Operated Air Powered Core Drill w/Bits100HR$0.0032 40 00
211nConcrete Saw100HR$0.0032 40 00
212Rental of Miscellaneous Equipment without OperatorTBDTBD32 40 00
213LABOR SUPPORTTBDJOB32 40 00
213aSurveyor100HR$0.0032 40 00
213bGeneral Engineer100HR$0.0032 40 00
213cDrafter/CADD Technician100HR$0.0032 40 00
213dPlumber100HR$0.0032 40 00
213eElectrician100HR$0.0032 40 00
213fHVAC Technician100HR$0.0032 40 00
213gLaborer100HR$0.0032 40 00
213hIron Worker100HR$0.0032 40 00
213iCarpenter100HR$0.0032 40 00
213jCement Mason100HR$0.0032 40 00
213kWelder Type I with Welding Equipment100HR$0.0032 40 00
213lWelder Type II with Welding Equipment100HR$0.0032 40 00
214Procurement and Delivery of Miscellaneous MaterialsTBDTBD32 40 00
TOTAL ORDERING PERIOD 3$0.00

BID SCHEDULE - ORDERING PERIOD 4

FACILITY INFRASTRUCTURE CONSTRUCTION AND MAINTENANCE IDIQ

ORDERING PERIOD DURATION: 1 MAR 2027 - 29 FEB 2028

ORDERING PERIOD 4
Pre-Priced Line ItemDescriptionEstimated
QuantityUOMUnit PriceEstimated
AmountTechnical

Section

1Concrete Slab: 4-inch200SF$0.0003 30 00
2Concrete Slab: 6-inch200SF$0.0003 30 00
3Concrete Slab: 8-inch100SF$0.0003 30 00
4Concrete Slab: 10-inch100SF$0.0003 30 00
5Concrete Ditch: 4-inch200SF$0.0003 30 00
6Concrete Curb & Gutter1000LF$0.0003 30 00
7Concrete Barrier Curbs1000LF$0.0003 30 00
8Concrete Mountable Curbs1000LF$0.0003 30 00
9Reinforcement500LB$0.0003 30 00
10Miscellaneous Concrete WorkTBDTBD03 30 00.99
11Clearing and Grubbing: Light5000SY$0.0031 00 00
12Clearing and Grubbing: Heavy5000SY$0.0031 00 00
13Fill Material1000CY$0.0031 00 00
14Earthwork - Berm Construction2000CY$0.0031 00 00
15Earthwork - Light Field/Site Grading2000CY$0.0031 00 00
16Earthwork - Heavy Field/Site Grading2000CY$0.0031 00 00
17Earthwork - Slough Construction2000CY$0.0031 00 00
18Earthwork - Pavement Subgrade1000CY$0.0031 00 00
19Excess Earthwork Disposal200CY$0.0031 00 00
20Top Soil800CY$0.0031 00 00
21Geotextile Installation - Woven100SY$0.0031 05 19.13
22Geotextile Installation - Non Woven100SY$0.0031 05 19.13
23Concrete Removal200CY$0.0032 00 00
24Concrete Removal Structures & Foundations200CY$0.0032 00 00
25Asphalt Removal200CY$0.0032 00 00
26Removal of Aggregates200CY$0.0032 00 00
27Disposal of Misc.500LB$0.0032 00 00
28Right of Way Clearing50MILE$0.0032 00 00
29Tree TrimmingTBDJOB32 00 00
29aTree Trimming Low20HR$0.0032 00 00
29bTree Trimming High20HR$0.0032 00 00
30Tree Removal - Light10EA$0.0032 00 00
31Tree Removal - Heavy10EA$0.0032 00 00
32Stump Removal - Light10EA$0.0032 00 00
33Stump Removal - Heavy10EA$0.0032 00 00
34Landscape Timbers Installation50LF$0.0032 00 00
35Landscape Timber Removal20LF$0.0032 00 00
36Sand Supply100TN$0.0032 00 00
37Beach Sand Supply & Install200TN$0.0032 00 00
38Redman Creek Beach - Maintenance1JB$0.0032 00 00
39Rockwood Beach - Maintenance1JB$0.0032 00 00
40Peoples Creek Beach - Maintenance1JB$0.0032 00 00
41Greenville Berm Notch Construction1JB$0.0032 00 00
42Greenville Berm Notch Removal1JB$0.0032 00 00
4312" Dia Pump Mob & Demob1JB$0.0032 00 00
4412" Dia Pump & Piping - Weekly3WK$0.0032 00 00
4512" Dia Pump & Piping - Monthly1MO$0.0032 00 00
46Entrance Gate - Double Arm Installation2EA$0.0032 00 00
47Entrance Gate - Single Arm Installation2EA$0.0032 00 00
48Entrance Gate - Double Arm Replacement2EA$0.0032 00 00

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .