9_Bid_B08_Sheet_Replace_Roofing_and_Gutter_Systems_Rocky_Knob_Maintenance_Buildings_20240117.pdf

PDF 105 KB Posted

Attached to
Blue Ridge REPLACE ROOFING & GUTTER SYSTEM Federal contract opportunity
Solicitation number
140P5324R0008
Issued by
Department of the Interior National Park Service Southeast Region

About this file

This bid schedule outlines work required to replace asphalt shingle roofs and gutters on seven maintenance buildings located at the Rocky Knob Maintenance Yard for the Blue Ridge Parkway. Option 1 specifies removing and disposing of existing roofing materials before installing new 30-year architectural shingles, underlayment, flashing, drip edges, ridge caps, roof vents, vent collars, and snow guards. Option 2 involves removing and replacing approximately 984 linear feet of gutters and downspouts on five buildings, replacing any damaged siding, and installing gutter guards. Pricing is to be provided separately for each option. The related federal contract opportunity on the Blue Ridge Parkway seeks bids to perform the roofing and gutter replacement work described in the bid schedule. The soliciting agency is the National Park Service Southeast Region within the Department of the Interior.

View the file

Other files for this federal contract opportunity

Other files attached to Blue Ridge REPLACE ROOFING & GUTTER SYSTEM, newest first.
File Type Posted
Sol_140P5324R0008_Amd_0003.pdf PDF
Sol_140P5324R0008_Amd_0002.pdf PDF
B09_Vendor_question_0002.pdf PDF
Sol_140P5324R0008_Amd_0001.pdf PDF
B878_Photo_0001.png PNG image
B965_photo_0001.png PNG image
Revised_Areil_Photo_1_23_24_0001.png PNG image
B005_photo_0001.png PNG image
A05_SOW.pdf PDF
Sol_140P5324R0008.pdf PDF
B03_Davis_Bacon_DOL.pdf PDF
B08_SF_1442_attchment_1.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID SCHEDULE

REMOVE/REPLACE ASPHALT SHINGLE ROOF AND GUTTERS ON ROCKY KNOB

MAINTENANCE YARD BUILDINGS (B002, B003, B004, B005, B086, B878, B965)

Option 1: REMOVE/REPLACE ASPHALT SHINGLE ROOF BUILDINGS (B002, B003, B004, B005, B086, B878, B965)

Option 1 Work

1. Remove and dispose of the existing asphalt shingle roof(s) and roofing underlayment off site

2. Protect the building structures and contents from weather and other potentially damaging elements

3. Inspect the existing roof supports (rafters) and fascia boards, replace damaged facia boards

4. Repair or replace in kind as necessary damaged roof supports (rafters), decking, sheathing revealed by inspection

5. Replace in kind all existing flashing

6. Install new 30 pound asphalt saturated roofing underlayment;

7. Install new dark gray 30 year architectural shingles with interlocking tabs

8. Install new drip edges around the entire perimeter of the roof

9. Install full length ridge cap(s) roof vent system

10. Flash Chimney(s)

11. Install new waterproof vent collars

12. Replace/Install Snow Guards on B004 and B086

Total: $

Option 2: REMOVE/REPLACE GUTTERS ON ROCKY KNOB MAINTENANCE YARD

BUILDINGS AND INSTALL GUTTER GUARDS (B002, B003, B004, B005, B086)

Option 2 Work

1. Remove and replace approximately 984 linear feet of gutter and associated downspouts on buildings B002, B003, B004, B005, B086

2. Replace any damaged siding behind the gutters on B002 and B003 before new gutters are installed, siding must be in-kind to match with remainder of building siding

3. Install gutter guards on all gutters

Total: $