8628196-REVA (QA TEST PROCEDURES FOR VLF_LF LOOP ANTENNA ASSEMBLY).pdf
PDF 581 KB Posted
- Attached to
- Very Low Frequency (VLF) Cross Loop Antennas Federal contract opportunity
- Solicitation number
- N66604-21-R-0270
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N6660421R0270.pdf | ||
| N6660421R0270 Exh. A CDRLs.pdf | ||
| N6660421R0270 Att. 1 GFP.pdf | ||
| 8628188-REV- (VLF_LF LOOP ANTENNA ASSEMBLY).pdf | ||
| 8628192-REV- (ANTENNA FRAME ASSEMBLY).PDF | ||
| 8628195-REV- (PLUG LIFTING INSERT).PDF | ||
| 8628199-REVA (VLF_LOOP ANTENNA ASSEMBLY OUTLINE AND INSTALLATION).pdf | ||
| 8628189-REV- (BLOCK SUPPORT).pdf | ||
| 8628190-REV- (ANTENNA ELEMENT ASSEMBLY).pdf | ||
| 8628191-REV- (INSERT LIFTING).pdf | ||
| 8628194-REV- (FERRITE BAR).PDF |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPROVED FOR PRE-PRODUCTION
DISTRIBUTION STATEMENT D: Distribution authorized to the Department of Defense and DOD contractors only; contains information which is critical technology; June 2008. Other requests shall be referred to Naval Undersea Warfare Center, Division Newport, Newport, RI Code 3433.
EXPORT CONTROL WARNING NOTICE:
WARNING: This document contains technical data whose export is restricted by the Arms Export
Control Act (Title 22 U.S.C. Sec 2751 et seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C., App 2401 et seq. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25
DWG NO.
8628196
SHEET
REV.
A
AIS:8628196 Rev A (WORD2016)
REVISIONS
ZONE REV DESCRIPTION DATE APPROVED
REVISED PER NOR-
8628196-REV-
2020-01-10 C. SHAW
UNLESS OTHERWISE
SPECIFIED
NAVAL UNDERSEA WARFARE CENTER
DIVISION NEWPORT
NEWPORT, RI 02841-1708
DIMENSIONS ARE IN
INCHES.
TOLERANCES ARE:
N/A
APPROVALS DATE
DRAWN BY
P. Gilles 2019-
07-18 QA Test Procedures for the
VLF/LF Loop Antenna Assembly
MACHINED SURFACE
FINISH TO BE: N/A
CHECKED
I. Wheeler 2019-
07-18
MACHINED FILLET
RADII TO BE: N/A
ACCEPTED
D. Glinka 2019-10-22
SIZE
CAGE CODE
53711
REV
A
BREAK ALL EDGES:
N/A
APPROVED
D. Portofee 2019-10-22
DO NOT SCALE
DRAWING
CONTRACT NUMBER
SCALE
NONE
SHEET 1 OF 15
WARNING:
THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT IS
RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C., SECTION
2751, ET SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED
(TITLE 50, U.S.C., APP 2401., ET SEQ.). VIOLATIONS OF THESE EXPORT LAWS
ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE IN
ACCORDANCE WITH OPNAVINST 5510.161.
DISTRIBUTION STATEMENT D:
Distribution authorized to the Department of Defense and U.S. DoD contractors only.
Critical Technology 18 July 2019. Other requests shall be referred to NUWCDIVNPT Code
3493 Donald Portofee.
DESTRUCTION NOTICE:
FOR UNCLASSIFIED, LIMITED DISTRIBUTION DOCUMENTS, DESTROY BY ANY
METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR
RECONSTRUCTION OF THE DOCUMENT.
WARNING:
This document contains technical data whose export is restricted by the Arms Export
Control Act (Title 22, U. S. C. Sec. 2751 et seq.) or the Export Administration Act of 1979, as amended, Title 50, U. S. C., App 2401 et seq. Violation of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive
5230.25.
UNCLASSIFIED//FOR OFFICIAL USE ONLY
SHEET
NEWPORT, RI 02841-1708
SIZE CAGE
CODE
DWG NO. REV.
A 53711 8628196 A
SCALE
NONE
QA Test Procedures for the VLF/LF Loop
Antenna Assembly
SHEET
OF
Table 1. Reference Documents
NO. DOCUMENT ID TITLE
1 8628188 ANTENNA ASSEMBLY
SHEET
NEWPORT, RI 02841-1708
SIZE CAGE
CODE
DWG NO. REV.
A 53711 8628196 A
SCALE
NONE
QA Test Procedures for the VLF/LF Loop
Antenna Assembly
SHEET
Table 2. Sheet Index
SHT DESCRIPTION
1 Cover
2 References
3 Index
4 General Notes
5 Instruments and Materials List
6-10 QA Test Procedures
11 Signature Page
SHEET
NEWPORT, RI 02841-1708
SIZE CAGE
CODE
DWG NO. REV.
A 53711 8628196 A
SCALE
NONE
QA Test Procedures for the VLF/LF Loop
Antenna Assembly
SHEET
GENERAL NOTES
1. This QA test procedure is for use with VLF/LF Loop Antenna, manufactured from drawing 8628188.
For all antenna assembly item callouts in this procedure, refer to 8628188 and related drawings.
2. The manufacturer has the discretion to choose the meter(s) used for making the measurements described herein as long as they meet the precision/accuracy requirements of 0.001/5% for resistance and 10H/1% for inductance.
3. Inductance is to be measured at a test frequency of 10 kHz.
4. Resistance is to be measured at DC if possible or the lowest available frequency not to exceed 1 kHz.
5. Ensure that the meter(s) used herein are allowed to warm up for the time recommended by the manufacturer for the most accurate results.
6. When performing the electrical verification tests, all metal and substances with relative magnetic permeability >1 must be kept a minimum of four (4) feet away from the antenna to prevent interference with test readings.
7. Record meter(s) descriptions and settings and other misc. hardware used for the testing conducted herein in the tables contained on sheet 5.
8. Equipment needed for testing:
• Inductance meter and test leads
• Resistance meter and test leads
• F/A and ATH Start and Finish pins o Contact, heavy duty, crimp, pin, 8AWG o Harting P/N: 09320006109
• F/A and ATH Start and Finish sockets o Contact, heavy duty, crimp, socket, 8AWG o Harting P/N: 09320006209
• Compass
• 1.5 VDC battery and test leads
9. The QA tests contained in this drawing are intended to identify a construction that is not capable of satisfying final ANTENNA ASSEMBLY quality assurance testing before and after the construction is encapsulated with potting material. If any QA test fails, refer to the NAVSEA 8628188 assembly drawings to verify that there were no assembly mistakes.
SHEET
NEWPORT, RI 02841-1708
SIZE CAGE
CODE
DWG NO. REV.
A 53711 8628196 A
SCALE
NONE
QA Test Procedures for the VLF/LF Loop
Antenna Assembly
SHEET
Table 3. Meter #1 Description and Settings
Parameter DESCRIPTION/DOCUMENT NUMBER
Model
Manufacturer
Serial Number
Calibration Date
Measurement Type
Test Frequency
Test Signal Level(s)
Measurement Mode
Range Setting
Measurement Rate
Table 4. Meter #2 Description and Settings (if applicable)
Parameter DESCRIPTION/DOCUMENT NUMBER
Model
Manufacturer
Serial Number
Calibration Date
Measurement Type
Test Frequency
Test Signal Level(s)
Measurement Mode
Range Setting
Measurement Rate
Table 5. Misc. Test Hardware
No. CAGE ITEM QTY DESCRIPTION/DOCUMENT NUMBER
SHEET
NEWPORT, RI 02841-1708
SIZE CAGE
CODE
DWG NO. REV.
A 53711 8628196 A
SCALE
NONE
QA Test Procedures for the VLF/LF Loop
Antenna Assembly
SHEET
QUALITY ASSURANCE (QA) TEST PROCEDURES
Introduction: QA test procedures shall be conducted as part of the fabrication of the Loop Antenna
Assembly as called out on NAVSEA drawing 8628188. The testing involves three tests described herein, Inductance, Continuity and Polarity, which shall be conducted upon satisfaction of certain prerequisites. Testing Part 1 shall be conducted per Table 8 upon satisfaction of prerequisites of Table
5. Testing Part 2 shall be conducted per Table 9 upon satisfaction of the prerequisites of Table 6.
Testing Part 3 shall be conducted per Table 7 upon satisfaction of the prerequisites of Table 10.
Table 5 - Prerequisites to Conducting Testing Part 1 of Table 8
1. Ferrite bars have been epoxied into a square frame.
2. Ferrite square frame is within the Support Block (drawing 8628189)
3. Litz wire has been routed per the drawing
4. Litz wire ends have been cut to the proper length
5. Litz wire ends have been solder/burned in the solder pot
6. Antenna assembly has not been encapsulated
Table 6 - Prerequisites to Conducting Testing Part 2 of Table 9
1. Prerequisites of Table 5 are met
2. Jumper Wires and Litz wires have been connected together
3. Heat shrink has been installed over Jumper Wire to Litz wire connection
4. Jumper Wires have been soldered to the antenna connector
Table 7 - Prerequisites to Conducting Testing Part 3 of Table 10
1. Prerequisites of Table 6 are met
2. Fully assembled antenna assembly is encapsulated
3. Urethane has fully cured
SHEET
NEWPORT, RI 02841-1708
SIZE CAGE
CODE
DWG NO. REV.
A 53711 8628196 A
SCALE
NONE
QA Test Procedures for the VLF/LF Loop
Antenna Assembly
SHEET
Table 8 - Tests Required for Testing Part 1
1. Inductance P1 Test
2. Continuity P1 Test
Table 9 - Tests Required for Testing Part 2
1. Inductance P2 Test
2. Continuity P2 Test
3. Polarity P2 Test
Table 10 - Tests Required for Testing Part 3
1. Inductance P3 Test
2. Continuity P3 Test
3. Polarity P3 Test
Inductance P1 Test Procedure
1. Identify the Litz wire ends for the F/A and ATH loops.
2. Connect the Inductance meter test leads to the soldered ends of the Litz wires of the F/A loop.
3. Set the meter test level to its lowest level.
4. Record the meter test level and inductance reading in Table 11 below in the F/A channel column.
5. Increase the test level two times if possible (not to exceed 1 Volt) and repeat step 4.
6. Repeat steps 4 and 5 at least one more time if possible.
7. Move the Inductance meter test leads to the soldered ends of the Litz wires of the ATH loop.
8. Repeat steps 3 through 6, recording the data in the ATH column.
9. Indicate Pass or Fail in Table 11 for the F/A and ATH channels if the measured inductance meets the required tolerance.
SHEET
NEWPORT, RI 02841-1708
SIZE CAGE
CODE
DWG NO. REV.
A 53711 8628196 A
SCALE
NONE
QA Test Procedures for the VLF/LF Loop
Antenna Assembly
SHEET
Table 11 - Inductance P1 Test Readings
Loop Channel F/A ATH
Test Level (V)
Measured Inductance (H)
Requirement(H) 680 H < Inductance < 900 H
Pass/Fail?
Continuity P1 Test Procedure
1. Identify the Litz wire ends for the F/A and ATH loops.
2. Connect the resistance meter test leads to the soldered ends of the Litz wires of the F/A loop.
3. Record the resistance reading in Table 12 below in the F/A channel column.
4. Move the resistance meter test leads to the soldered ends of the Litz wires of the ATH loop.
5. Record the resistance reading in Table 12 below in the ATH channel column.
6. Indicate Pass or Fail in Table 12 for the F/A and ATH channels if the measured resistance meets the
Table 12 - Continuity P1 Test - Resistance Readings
Loop Channel F/A ATH
Measured Resistance ()
Requirement () < 0.070
Inductance P2 Test Procedure
1. Identify the F/A and ATH start and Finish pins as described in Table 13 below:
SHEET
NEWPORT, RI 02841-1708
SIZE CAGE
CODE
DWG NO. REV.
A 53711 8628196 A
SCALE
NONE
QA Test Procedures for the VLF/LF Loop
Antenna Assembly
SHEET
Table 13 - Antenna Connector Pin Description
F/A Channel ATH Channel
Start Finish Start Finish
Pin 1 Pin 3 Pin 2 Pin 4
2. Insert mating sockets into the F/A Start and Stop pins to provide additional clearance for test lead connections. Do NOT connect anything except mating sockets to the antenna connector’s pins.
3. Connect the Inductance meter test leads to the mating sockets connected to the antenna F/A Start and
Finish pins.
4. Set the meter test level to its lowest level.
5. Record the meter test level and inductance reading in Table 14 below in the F/A channel column.
6. Increase the test two times level if possible (not to exceed 1 Volt) and repeat step 5.
7. Repeat steps 5 and 6 at least one more time if possible.
8. Move the mating sockets with test leads attached to the ATH channel Start and Finish pins.
9. Repeat steps 4 through 7, recording the data in the ATH column.
10. Indicate Pass or Fail in Table 14 for the F/A and ATH channels if the measured inductance meets the required tolerance.
Table 14 - Inductance P2 Test Readings
Loop Channel F/A ATH
Test Level (V)
Measured Inductance (H)
Continuity P2 Test Procedure
1. Identify the F/A and ATH start and Finish pins as described in Table 13.
SHEET
NEWPORT, RI 02841-1708
SIZE CAGE
CODE
DWG NO. REV.
A 53711 8628196 A
SCALE
NONE
QA Test Procedures for the VLF/LF Loop
Antenna Assembly
SHEET
2. Insert mating sockets into the F/A Start and Stop pins to provide additional clearance for test lead connections. Do NOT connect anything except mating sockets to the antenna connector’s pins.
3. Connect the resistance meter test leads to the mating sockets connected to the antenna F/A Start and
Finish pins.
4. Record the resistance reading in Table 15 below in the F/A channel column
5. Move the mating sockets with test leads attached to the ATH channel Start and Finish pins.
6. Record the resistance reading in Table 15 below in the ATH column.
7. Indicate Pass or Fail in Table 15 for the F/A and ATH channels if the measured resistance meets the
Table 15 - Continuity P2 Test - Resistance Readings
Measured Resistance ()
Polarity P2 Test Procedure
1. Place the compass at the center of the VLF Loop Antenna Assembly.
2. Connect the 1.5 VDC battery terminals to the F/A start and finish pins as described in the Table 16 for the first of the four compass direction tests.
3. Draw the direction of the compass needle deflection in Table 16 and record the pass/fail determination.
4. Repeat steps 1-3 for the remaining three compass direction tests.
SHEET
NEWPORT, RI 02841-1708
SIZE CAGE
CODE
DWG NO. REV.
A 53711 8628196 A
SCALE
NONE
QA Test Procedures for the VLF/LF Loop
Antenna Assembly
SHEET
Table 16 - Pin Settings and Compass Needle Orientation
Pin
No.
Description Battery
Polarity
Required Compass
Needle Direction
Observed Compass
Needle Direction
(relative to FWD)
Required =
Observed? Yes=Pass, No=Fail
1 F/A Start + Loop Antenna
FW
D
Compass
3 F/A Finish -
1 F/A Start - Loop Antenna
FW
3 F/A Finish +
2 ATH Start + Loop Antenna
FW
4 ATH Finish -
2 ATH Start -
Loop Antenna
FW
4 ATH Finish +
Inductance P3 Test Procedure
1. Identify the F/A and ATH start and Finish pins as described in Table 17 below:
Table 17 - Antenna Connector Pin Description
F/A Channel ATH Channel
Start Finish Start Finish
Pin 1 Pin 3 Pin 2 Pin 4
2. Insert mating sockets into the F/A Start and Stop pins to provide additional clearance for test lead connections. Do NOT connect anything except mating sockets to the antenna connector’s pins.
SHEET
NEWPORT, RI 02841-1708
SIZE CAGE
CODE
DWG NO. REV.
A 53711 8628196 A
SCALE
NONE
QA Test Procedures for the VLF/LF Loop
Antenna Assembly
SHEET
3. Connect the Inductance meter test leads to the mating sockets connected to the antenna F/A Start and
Finish pins.
4. Set the meter test level to its lowest level.
5. Record the meter test level and inductance reading in Table 18 below in the F/A channel column.
6. Increase the test level two times if possible (not to exceed 1 Volt) and repeat step 5.
7. Repeat steps 5 and 6 at least one more time if possible.
8. Move the mating sockets with test leads attached to the ATH channel Start and Finish pins.
9. Repeat steps 4 through 7, recording the data in the ATH column.
10. Indicate Pass or Fail in Table 18 for the F/A and ATH channels if the measured inductance meets the required tolerance.
Table 18 - Inductance P3 Test Readings
Loop Channel F/A ATH
Test Level (V)
Measured Inductance (H)
Continuity P3 Test Procedure
1. Identify the F/A and ATH start and Finish pins as described in Table 13.
2. Insert mating sockets into the F/A Start and Stop pins to provide additional clearance for test lead connections. Do NOT connect anything except mating sockets to the antenna connector’s pins.
3. Connect the resistance meter test leads to the mating sockets connected to the antenna F/A Start and
Finish pins.
4. Record the resistance reading in Table 19 below in the F/A channel column
5. Move the mating sockets with test leads attached to the ATH channel Start and Finish pins.
6. Record the resistance reading in Table 19 below in the ATH column.
SHEET
NEWPORT, RI 02841-1708
SIZE CAGE
CODE
DWG NO. REV.
A 53711 8628196 A
SCALE
NONE
QA Test Procedures for the VLF/LF Loop
Antenna Assembly
SHEET
7. Indicate Pass or Fail in Table 19 for the F/A and ATH channels if the measured resistance meets the
Table 19 - Continuity P3 Test - Resistance Readings
Measured Resistance ()
Polarity P3 Test Procedure
1. Place the compass at the center of the VLF Loop Antenna Assembly.
2. Connect the 1.5 VDC battery terminals to the F/A start and finish pins as described in the Table 20 for the first of the four compass direction tests.
3. Draw the direction of the compass needle deflection in Table 20 and record the pass/fail determination.
4. Repeat steps 1-3 for the remaining three compass direction tests.
SHEET
NEWPORT, RI 02841-1708
SIZE CAGE
CODE
DWG NO. REV.
A 53711 8628196 A
SCALE
NONE
QA Test Procedures for the VLF/LF Loop
Antenna Assembly
SHEET
Table 20 - Pin Settings and Compass Needle Orientation
Pin
No.
Description Battery
Polarity
Required Compass
Needle Direction
Observed Compass
Needle Direction
(relative to FWD)
Required =
Observed? Yes=Pass, No=Fail
1 F/A Start + Loop Antenna
FW
3 F/A Finish -
1 F/A Start - Loop Antenna
FW
3 F/A Finish +
2 ATH Start + Loop Antenna
FW
4 ATH Finish -
2 ATH Start -
Loop Antenna
FW
4 ATH Finish +
Notes:
SHEET
NEWPORT, RI 02841-1708
SIZE CAGE
CODE
DWG NO. REV.
A 53711 8628196 A
SCALE
NONE
QA Test Procedures for the VLF/LF Loop
Antenna Assembly
SHEET
I certify that I conducted the measurements contained in this test procedure and recorded the actual measurement values and observations.
Print Name: ______________________________
Signature: ______________________________ Date: ____________________
I certify that I witnessed the measurements contained in this test procedure and the recording of the actual measurement values and observations.
Print Name: ______________________________
Signature: ______________________________ Date: ___________________