FINAL RFP Amendment 002 for Review 10.30.2020.docx

DOCX document 1 MB Posted

Attached to
Center Administrative Support Services (CASS II) - RFP Amendment P00003 Federal contract opportunity
Solicitation number
80MSFC20R0009
Issued by
National Aeronautics and Space Administration Marshall Space Flight Center

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

80MSCF20P0045

National Aeronautics and Space Administration

George C. Marshall Space Flight Center Marshall Space Flight Center, AL 35812

MSFC Center Administrative Support Services (CASS II)

Request for Proposal

RFP Number: 80MSFC20R0009

TABLE OF CONTENTS

SECTION A - Solicitation/Contract Form SECTION B - Supplies or Services and Prices/Costs SECTION C - Description/Specifications/Statement of Work SECTION D - Packaging and Marking SECTION E - Inspection and Acceptance SECTION F - Deliveries or Performance SECTION G - Contract Administration Data SECTION H - Special Contract Requirements SECTION I - Contract Clauses SECTION J - List of Attachments SECTION K - Representations, Certifications, and Other Statements of Offerors or Respondents SECTION L - Instructions, Conditions, and Notices to Offerors or Respondents SECTION M - Evaluation Factors for Award

80MSFC20R0009

SECTION A - SOLICITATION/CONTRACT FORM

A.1 Standard Form 1449 – Commercial Items Solicitation RFP

See attached file - (SF 1449 with continuation sheet) A-1 Amendment 002

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

1852.216-78 FIRM FIXED PRICE (DEC 1988)

The total firm fixed price of this contract is $ To Be Proposed (TBP).

(End of clause)

MSFC 52.216-90 IDIQ CONTRACT VALUE BY PERIOD OF PERFORMANCE (MAY 2017)

The maximum potential not-to-exceed (NTE) value of the indefinite-delivery, indefinite- quantity (IDIQ) component of this contract including Options, is $2,500,000. The NTE value shall not be exceeded without the prior written approval of the Contracting Officer.

The values for each period of performance are set forth below:

PERIOD OF PERFORMANCE
MINIMUM VALUE
MAXIMUM VALUE
Base Contract
4/01/2021 – 3/31/2022
$0
$500,000
Option 1
4/01/2022 – 3/31/2023
$0
$500,000
Option 2
4/01/2023 – 3/31/2024
$0
$500,000
Option 3
4/01/2024 – 3/31/2025
$0
$500,000
Option 4
4/01/2025 – 3/31/2026
$0
$500,000

(End of clause)

MSFC 52.216-91 SUPPLIES AND/OR SERVICES TO BE PROVIDED AND TYPE OF CONTRACT (JUN 2017)

(a) The contractor shall provide all resources (except as may be expressly stated in the contract as furnished by the Government) necessary to perform and/or deliver the services in accordance with Attachment J-1, Performance Work Statement.

(b) This is a firm-fixed-price (FFP) mission services type contract with a FFP, indefinite- delivery, indefinite-quantity (IDIQ) component. The purpose of this contract is to acquire a broad range of administrative support services for MSFC and MAF. This contract provides two methods for the acquisition of these services:

(1) FFP mission services work that can be identified in advance, both in sufficient detail and quantities, is identified in Attachment J-1, Performance Work Statement, Section 1.0, Introduction, through Section 4.0, Training, and Attachment J-11, Minimum Required Staffing Levels, for which the price has been negotiated. The negotiated contract value, including the values negotiated for each option period, includes all costs necessary to perform and/or deliver the services required for this contract effort.

B-1

(2) Work that cannot be sufficiently identified or quantified in advance, but which is within the general scope of this contract, is identified as IDIQ. IDIQ includes all support identified in Attachment J-1, PWS, Section 6.0, IDIQ. IDIQ work may be authorized by the Government Contracting Officer (CO) as FFP task orders (TOs), using the labor rates and prices in Attachment J-4, IDIQ Rate and Price Schedules. The Government may order IDIQ service in accordance with the procedures set forth in NFS Clause 1852.216-80, Task Ordering Procedure, Alternate II.

MSFC 52.216-92 MATRIX OF CONTRACT LINE ITEMS (CLINs) (OCT 2017)

The current total contract value is as specified below. To separately track the components of the value, separate CLINs have been established as follows:

CLIN
DESCRIPTION
VALUE
OPTION STATUS
001
Base Period4/01/2021 – 3/31/2022
$ TBP
N/A
002
Option 14/01/2022 – 3/31/2023
$ TBP
Unexercised
003
Option 24/01/2023 – 3/31/2024
$ TBP
Unexercised
004
Option 34/01/2024 – 3/31/2025
$ TBP
Unexercised
005
Option 44/01/2025 – 3/31/2026
$ TBP
Unexercised

Travel and Training

006
Base Period4/01/2021 – 3/31/2022
$20,000
N/A
007
Option 14/01/2022 – 3/31/2023
$20,000
Unexercised
008
Option 24/01/2023 – 3/31/2024
$20,000
Unexercised
009
Option 34/01/2024 – 3/31/2025
$20,000
Unexercised
010
Option 44/01/2025 – 3/31/2026
$20,000
Unexercised
IDIQ
Not-to-Exceed

(NTE)

011
Base Period4/01/2021 – 3/31/2022
$ TBD
N/A
012
Option 14/01/2022 – 3/31/2023
$ TBD
Unexercised
013
Option 24/01/2023 – 3/31/2024
$ TBD
Unexercised
014
Option 34/01/2024 – 3/31/2025
$ TBD
Unexercised
015
Option 44/01/2025 – 3/31/2026
$ TBD
Unexercised
Total Value of Base and All Exercised Options
$ TBP (populate base period only CLINS 001 & 006)

NOTE: All task orders awarded will be reflected in Attachment J-5, Task Order (TO) Summary.

B-2 Amendment 002

MSFC 52.227-91 DATA REQUIREMENTS (JUN 2017)

(a) The contractor shall furnish all data identified and described in the data requirements list (DRL) of the data procurement document (DPD) which is attached to this contract. All expenses associated therewith are included in the estimated cost or firm fixed price of this contract, or any associated task orders if applicable.

(b) The Government reserves the right to delay the delivery of any or all data requirements descriptions (DRDs) specified in the DRL and such right may be exercised at no increase to the estimated cost or firm fixed price of this contract or any associated task orders.

(c) Nothing contained in this clause shall relieve the contractor from delivering data that is not identified and described in the DRL/DPD, but required under another section of this contract.

(d) To the extent that data required to be delivered under a DRD is also required to be delivered under another section of the contract, the requirements established by both the DRD and such other contract section shall apply. In the event of a conflict between the data requirements of the DPD and another contract section, the specific contract section will take precedence.

(End of clause)

MSFC 52.232-92 GOVERNMENT ESTIMATED COSTS (JULY 2017)

Category
Base Period
Option 1
Option 2
Option 3
Option 4
Total
Travel and Training
$20,000
$20,000
$20,000
$20,000
$20,000
$100,000

(a) The total estimated cost or price of this contract includes the above Government-estimated costs for the base period and all options. Fee or profit will not be paid for these expenses. Only actual costs plus the applied burden rates as specified elsewhere in the contract will be reimbursed. The contractor shall obtain approval from the Contracting Officer (CO) and the Contracting Officer’s representative (COR) at least five (5) business days prior to the incurrence of travel or training expenses.

(b) Travel shall be performed in compliance with the Federal Travel Regulations (FTR). Actual expenses exceeding the FTR’s will not be reimbursed by the Government.

(c) Labor associated with these costs is reflected in the estimated cost or price of this contract and therefore is not a reimbursable expense.

(d) These cost elements shall be invoiced on a separate line item in all invoices in which these costs are incurred and the contractor shall maintain complete backup documentation to support these invoiced elements. Any unused materials, travel, and/or training value in any contract period may be rolled-over for utilization during a subsequent contract period at the discretion of the Government, provided that the total value established for all option periods is not exceeded.

B-4

(e) The Government reserves the right to reduce the contract value during, or at the conclusion of, the contract period of performance in recognition of any unused value for these items.

(End of Clause)

MSFC 52.237-92 DEDUCTIONS FOR FAILURE TO MEET ACCEPTABLE PERFORMANCE LEVELS (JUN 2017)

(a) The contractor’s performance will be evaluated on a semi-annual basis. The Government will apply deductions for failure to meet acceptable performance levels (APLs) utilizing the methodology and required performance levels specified in Attachment J-3, Performance Requirements Summary.

(b) The Government will hold recurring performance evaluation meetings (PEMs) with the contractor, based on a schedule determined by the Contracting Officer (CO), to discuss performance against the established standards and any associated deductions, if applicable. More frequent meetings may be held if determined necessary by the CO.

(c) The contractor shall apply any required deductions for failure to meet APLs on the next invoice/voucher submitted following the period being evaluated.

(d) Notwithstanding the foregoing, the Government’s rights under this clause to reduce fee or contract value for less than optimal performance is in addition to the rights of the Government prescribed in Clauses 52.246-4 Inspection of Services-Fixed Price and 52.249-8 Default (Fixed-Price Supply and Service).

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

MSFC 52.211-93 DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK/PERFORMANCE WORK STATEMENT (MAY 2019)

The Description/Specifications/Statement of Work/Performance Work Statement is located at Attachment J-1.

C-1

SECTION D - PACKAGING AND MARKING

1852.245-74 IDENTIFICATION AND MARKING OF GOVERNMENT EQUIPMENT (JAN 2011)

(a) The Contractor shall identify all equipment to be delivered to the Government using NASA Technical Handbook (NASA-HDBK) 6003, Application of Data Matrix Identification Symbols to Aerospace Parts Using Direct Part Marking Methods/Techniques, and NASA Standard (NASA-STD) 6002, Applying Data Matrix Identification Symbols on Aerospace Parts or through the use of commercial marking techniques that: (1) are sufficiently durable to remain intact through the typical lifespan of the property: and, (2) contain the data and data format required by the standards. This requirement includes deliverable equipment listed in the schedule and other equipment when no longer required for contract performance and NASA directs physical transfer to NASA or a third party. The Contractor shall identify property in both machine and human readable form unless the use of a machine readable-only format is approved by the NASA Industrial Property Officer.

(b) Equipment shall be marked in a location that will be human readable, without disassembly or movement of the equipment, when the items are placed in service unless such placement would have a deleterious effect on safety or on the item’s operation.

(c) Concurrent with equipment delivery or transfer, the Contractor shall provide the following data in an electronic spreadsheet format:

(1) Item Description.

(2) Unique Identification Number (License Tag).

(3) Unit Price.

(4) An explanation of the data used to make the unique identification number.

(d) For equipment no longer needed for contract performance and physically transferred under paragraph (a) of this clause, the following additional data is required:

(1) Date originally placed in service.

(2) Item condition.

(e) The data required in paragraphs (c) and (d) of this clause shall be delivered to the NASA center receiving activity listed below:

Marshall Space Flight Center AS41/Cynthia Davis Industrial Property Officer Huntsville, AL 35812

D-1

(f) The contractor shall include the substance of this clause, including this paragraph (f), in all subcontracts that require delivery of equipment.

D-2

SECTION E - INSPECTION AND ACCEPTANCE

52.246-4 INSPECTION OF SERVICES--FIXED-PRICE (AUG 1996)

1852.246-71 GOVERNMENT CONTRACT QUALITY ASSURANCE FUNCTIONS (OCT

1988)

In accordance with the inspection clause of this contract, the Government intends to perform the following functions at the locations indicated:

Item
Quality Assurance Location
Function
All Services
See MSFC 52.237-91, Place of Performance
Inspection/Acceptance

E-1

SECTION F - DELIVERIES OR PERFORMANCE

52.242-15 STOP-WORK ORDER (AUG 1989)

52.242-17 GOVERNMENT DELAY OF WORK (APR 1984) MSFC 52.211-94 PERIOD OF PERFORMANCE (MAY 2017) The period of performance for this contract is from 04/01/2021 through 03/31/2022.

(End of clause)

MSFC 52.237-91 PLACE OF PERFORMANCE (JUL 2018)

The Contractor shall perform the work under this contract at Marshall Space Flight Center (MSFC) and Michoud Assembly Facility (MAF), and at such other locations as may be approved in writing by the Contracting Officer.

F-1

SECTION G - CONTRACT ADMINISTRATION DATA

1852.245-75 PROPERTY MANAGEMENT CHANGES (JAN 2011)

1852.245-71 INSTALLATION—ACCOUNTABLE GOVERNMENT PROPERTY (JUN

2018)

(a) The Government property described in paragraph (c) of this clause may be made available to the Contractor on a no-charge basis for use in performance of this contract. This property shall be utilized only within the physical confines of the NASA installation that provided the property unless authorized by the Contracting Officer under (b)(1)(iv). Under this clause, the Government retains accountability for, and title to, the property, and the Contractor shall comply with the following:

NASA Procedural Requirements (NPR) 4100.1, NASA Materials Inventory Management Manual;

NPR 4200.1, NASA Equipment Management Procedural Requirements; NPR 4300.1, NASA Personal Property Disposal Procedural Requirements;

Property not recorded in NASA property systems must be managed in accordance with the requirements of the clause at FAR 52.245-1, as incorporated in this contract.

The Contractor shall establish and adhere to a system of written procedures to assure continued, effective management control and compliance with these user responsibilities. In accordance with FAR 52.245-1(h)(1) the contractor shall be liable for property lost, damaged, destroyed or stolen by the contractor or their employees when determined responsible by a NASA Property Survey Board, in accordance with the NASA guidance in this clause.

(b)(1) The official accountable recordkeeping, financial control, and reporting of the property subject to this clause shall be retained by the Government and accomplished within NASA management information systems prescribed by the installation Supply and Equipment Management Officer (SEMO) and Financial Management Officer. If this contract provides for the Contractor to acquire property, title to which will vest in the Government, the following additional procedures apply:

(i) The Contractor’s purchase order shall require the vendor to deliver the property to the installation central receiving area.

(ii) The Contractor shall furnish a copy of each purchase order, prior to delivery by the vendor, to the installation central receiving area.

(iii) The Contractor shall establish a record for Government titled property as required by FAR 52.245-1, as incorporated in this contract, and shall maintain that record until accountability is accepted by the Government.

G-6

(iv) Contractor use of Government property at an off-site location and off-site subcontractor use requires advance approval of the Contracting Officer and notification of the Industrial Property Officer. The property shall be considered Government furnished and the Contractor shall assume accountability and financial reporting responsibility. The Contractor shall establish records and property control procedures and maintain the property in accordance with the requirements of FAR 52.245-1, Government Property (as incorporated in this contract), until its return to the installation. NASA Procedural Requirements related to property loans shall not apply to offsite use of property by contractors.

(2) After transfer of accountability to the Government, the Contractor shall continue to maintain such internal records as are necessary to execute the user responsibilities identified in paragraph (a) of this clause and document the acquisition, billing, and disposition of the property. These records and supporting documentation shall be made available, upon request, to the SEMO and any other authorized representatives of the Contracting Officer.

(c) The following property and services are provided if checked:

[X]
(1) Office space, work area space, and utilities. Government telephones are available for official purposes only.
[X]
(2) Office furniture.
[X]
(3) Property listed in Attachment J-7

(i) If the Contractor acquires property, title to which vests in the Government pursuant to other provisions of this contract, this property also shall become accountable to the Government upon its entry into Government records.

(ii) The Contractor shall not bring to the installation for use under this contract any property owned or leased by the Contractor, or other property that the Contractor is accountable for under any other Government contract, without the Contracting Officer’s prior written approval.

[ ]
(4) Supplies from stores stock.
[ ]
(5) Publications and blank forms stocked by the installation.
[X]
(6) Safety and fire protection for Contractor personnel and facilities.
[X]
(7) Installation service facilities: See Attachment J-7
[X]
(8) Medical treatment of a first-aid nature for Contractor personnel injuries or illnesses sustained during on-site duty.
[X]
(9) Cafeteria privileges for Contractor employees during normal operating hours.
[X]
(10) Building maintenance for facilities occupied by Contractor personnel.
[X]
(11) Moving and hauling for office moves, movement of large equipment, and delivery of supplies. Moving services may be provided on-site, as approved by the Contracting Officer.

1852.232-80 SUBMISSION OF VOUCHERS/INVOICES FOR PAYMENT (APR 2018)

(a) The designated payment office is the NASA Shared Services Center (NSSC) located at FMD Accounts Payable, Bldg. 1111, Jerry Hlass Road, Stennis Space Center, MS 39529.

(b) Except for classified vouchers, the Contractor shall submit all vouchers and invoices using the steps described at NSSC’s Vendor Payment information web site at: https://www.nssc.nasa.gov/vendorpayment. Please contact the NSSC Customer Contact Center at 1-877-NSSC123 (1-877-677-2123) with any additional questions or comments.

(c) Payment requests.

(1) The payment periods are stipulated in the payment clause(s) contained in this contract.

(2) Vouchers submitted under cost type contracts and invoices submitted under fixed-price contracts shall include the items delineated in FAR 32.905(b) supported by relevant back- up documentation. Back-up documentation shall include at a minimum, the following information:

(i) Vouchers.

(A) Breakdown of billed labor costs and associated contractor generated supporting documentation for billed direct labor costs to include rates used and number of hours incurred.

(B) Breakdown of billed other direct costs (ODCs) and associated contractor generated supporting documentation for billed ODCs.

(C) Indirect rate(s) used to calculate the amount of billed indirect expenses.

(D) Progress reports, as required.

(ii) Invoices.

(A) Description of goods and services delivered as part of the contract’s terms and conditions, including the dates of delivery/performance.

(B) Progress reports, as required.

(C) Date goods and services were performed.

(iii) Fee vouchers.

(A) Listing of all provisionally billed fee by period or date earned since contract award.

(B) A reconciliation of all billed and earned fee.

(C) A clear explanation of the fee calculations.

(d) Non-electronic payment requests. The Contractor may submit a non-electronic voucher/invoice using the steps for non-electronic payment requests described at https://www.nssc.nasa.gov/vendorpayment, when any of the following conditions are met:

(1) The Contracting Officer administering the contract for payment has determined, in writing, that electronic submission would be unduly burdensome to the Contractor.

(2) The contract includes provisions allowing the contractor to submit vouchers or invoices using the steps for non-electronic payment. In such instances the Contractor agrees to submit non-electronic payment requests using the method or methods specified in Section G of the contract.

(e) Improper vouchers/invoices. The NSSC Payment Office will notify the contractor of any apparent error, defect, or impropriety in a voucher/invoice within seven calendar days of receipt by the NSSC Payment Office. Inquiries regarding requests for payment should be directed to the NSSC as specified in paragraph (b) of this section.

(f) Other payment clauses. In addition to the requirements of this clause, the Contractor shall meet the requirements of the appropriate payment clauses in this contract when submitting payment requests.

(g) In the event that amounts are withheld from payment in accordance with provisions of this contract, a separate payment request for the amount withheld will be required before payment for that amount may be made.

1852.245-76 LIST OF GOVERNMENT PROPERTY FURNISHED PURSUANT TO FAR

52.245-1 (JAN 2011)

For performance of work under this contract, the Government will make available Government property identified in Attachment J-7 of this contract on a no charge-for-use basis pursuant to the clause at FAR 52.245-1, Government Property, as incorporated in this contract. The Contractor shall use this property in the performance of this contract at Marshall Space Flight Center (MSFC) and Michoud Assembly Facility (MAF) and at other location(s) as may be approved by the Contracting Officer. Under FAR 52.245-1, the Contractor is accountable for the identified property.

(End of clause)

1852.245-82 OCCUPANCY MANAGEMENT REQUIREMENTS (SEP 2017)

(a) In addition to the requirements of the clause at FAR 52.245-1, Government Property, as included in this contract, the Contractor shall comply with the following in performance of work in and around Government real property:

(1) NPD 8800.14, Policy for Real Estate Management.

(2) NPR 8831.2, Facilities Maintenance and Operations Management.

(b) The Contractor shall obtain the written approval of the Contracting Officer before installing or removing Contractor-owned property onto or into any Government real property or when movement of Contractor-owned property may damage or destroy Government-owned property. The Contractor shall restore damaged property to its original condition at the Contractor’s expense.

(c) The Contractor shall not acquire, construct or install any fixed improvement or structural alterations in Government buildings or other real property without the advance, written approval of the Contracting Officer. Fixed improvement or structural alterations, as used herein, means any alteration or improvement in the nature of the building or other real property that, after completion, cannot be removed without substantial loss of value or damage to the premises. Title to such property shall vest in the Government.

(d) The Contractor shall report any real property or any portion thereof when it is no longer required for performance under the contract, as directed by the Contracting Officer.

(End of clause)

MSFC 52.204-91 SECURITY AND BADGING REQUIREMENTS (NOV 2016)

Performance of this contract will require access to facilities, information technology systems, and other resources at the Marshall Space Flight Center and/or the Michoud Assembly Facility. To obtain and maintain access, the Contractor shall comply with the applicable requirements from the latest revision of (1) NPR 1600.1, “NASA Security Program Procedural Requirements,”

(2) NPR 1600.4, “Identity and Credential Management,” (3) Marshall Procedural Requirements (MPR) 1600.1, “MSFC Security Program Procedural Requirements,” (4) MPR 1600.4, “MSFC Identity, Credential, and Access Management,” and (5) NASA Advisory Implementing Instruction (NAII) 1600.4, “Foreign National Access Management.”

SECTION H - SPECIAL CONTRACT REQUIREMENTS

1852.208-81 RESTRICTIONS ON PRINTING AND DUPLICATING (NOV 2004)

1852.223-75 MAJOR BREACH OF SAFETY OR SECURITY (FEB 2002) ALTERNATE I (FEB 2006)

1852.223-70 SAFETY AND HEALTH MEASURES AND MISHAP REPORTING (DEC

2015)

(a) Safety is the freedom from those conditions that can cause death, injury, occupational illness, damage to or loss of equipment or property, or damage to the environment. NASA’s safety priority is to protect: (1) the public, (2) astronauts and pilots, (3) the NASA workforce (including contractor employees working on NASA contracts), and (4) high-value equipment and property.

(b) The Contractor shall take all reasonable safety and occupational health measures in performing this contract. The Contractor shall maintain an effective worksite safety and health program with organized and systematic methods to—

(1) Comply with Federal, State, and local safety and occupational health laws and with the safety and occupational health requirements of this contract;

(2) Describe and assign the responsibilities of managers, supervisors, and employees;

(3) Inspect regularly for and identify, evaluate, prevent, and control hazards;

(4) Orient and train employees to eliminate or avoid hazards; and

(5) Periodically review the program’s effectiveness. Authorized Government representatives shall have access to and the right to examine the work site and related records under this Contract in order to determine the adequacy of the Contractor’s safety and occupational health measures.

(c) The Contractor shall take, or cause to be taken, any other safety, and occupational health measures the Contracting Officer may reasonably direct. To the extent that the Contractor may be entitled to an equitable adjustment for those measures under the terms and conditions of this contract, the equitable adjustment shall be determined pursuant to the procedures of the changes clause of this contract; provided, that no adjustment shall be made under this Safety and Health clause for any change for which an equitable adjustment is expressly provided under any other clause of the contract.

(d) The Contractor shall immediately notify the Contracting Officer or a designee any Type A, B, C, or D Mishap, or close calls as defined in NPR 8621.1, Mishap and Close Call Reporting, Investigating, and Recordkeeping. In addition, service contractors (excluding construction contracts) shall provide quarterly reports specifying lost-time frequency rate, H-2 number of lost-time injuries, exposure, and accident/incident dollar losses as specified in the contract Schedule.

(e) The Contractor shall cooperate with any Government-authorized investigation of Type A, B, C, or D Mishaps, or Close Calls reported pursuant to paragraph (d) of this clause by providing access to employees; and relevant information in the possession of the Contractor regarding the mishap or close call.

(f)(1) The Contracting Officer may notify the Contractor of any noncompliance with this clause and specify corrective actions to be taken. When the Contracting Officer becomes aware of noncompliance that may pose a serious or imminent danger to safety and health of the public, astronauts and pilots, the NASA workforce (including contractor employees working on NASA contracts), or high value mission critical equipment or property, the Contracting Officer will notify the Contractor orally, with written confirmation. The Contractor shall promptly take any necessary corrective action.

(2) If the Contractor fails or refuses to institute prompt corrective action in accordance with subparagraph (f)(1) of this clause, the Contracting Officer may—

(i) Invoke the stop-work order clause in this contract;

(ii) Require the Contractor to remove and replace Contractor or subcontractor personnel who fail to comply with or violate applicable requirements of this clause;

(iii) Record the Contractor’s failure to comply in the appropriate databases of past performance; and

(iv) Consider the Contractor’s failure to comply in any responsibility determination or evaluation of past performance.

(g) The Contractor shall insert the substance of this clause, including this paragraph (g) in all subcontracts above the simplified acquisition threshold when the work will be conducted completely or partly on federally controlled facilities.

(End of clause)

1852.223-72 SAFETY AND HEALTH (SHORT FORM) (JUL 2015)

(a) Safety is the freedom from those conditions that can cause death, injury, occupational illness; damage to or loss of equipment or property, or damage to the environment. NASA is committed to protecting the safety and health of the public, our team members, and those assets that the Nation entrusts to the Agency.

(b) The Contractor shall have a documented, comprehensive and effective health and safety program with a proactive process to identify, assess, and control hazards and take all reasonable safety and occupational health measures consistent with standard industry practice in performing this contract.

(c) The Contractor shall insert the substance of this clause, including this paragraph (c) in subcontracts that exceed the simplified acquisition threshold where work will be conducted completely or partly on Federally-controlled facilities.

(End of clause)

1852.225-70 EXPORT LICENSES (FEB 2000)

(a) The Contractor shall comply with all U.S. export control laws and regulations, including the International Traffic in Arms Regulations (ITAR), 22 CFR parts 120-130, and the Export Administration Regulations (EAR), 15 CFR parts 730-799, in the performance of this contract. In the absence of available license exemptions/exceptions, the Contractor shall be responsible for obtaining the appropriate licenses or other approvals, if required, for exports of hardware, technical data, and software, or for the provision of technical assistance.

(b) The Contractor shall be responsible for obtaining export licenses, if required, before utilizing foreign persons in the performance of this contract, including instances where the work is to be performed on-site at MSFC and MAF, where the foreign person will have access to export- controlled technical data or software.

(c) The Contractor shall be responsible for all regulatory record keeping requirements associated with the use of licenses and license exemptions/exceptions.

(d) The Contractor shall be responsible for ensuring that the provisions of this clause apply to its subcontractors.

(End of clause)

1852.232-77 LIMITATION OF FUNDS (FIXED-PRICE CONTRACT) (MAR 1989)

(a) Of the total price of items CLINs 001, 006, and 011, the sum of $TBD is presently available for payment and allotted to this contract. It is anticipated that from time to time additional funds will be allocated to the contract in accordance with the following schedule, until the total price of said items is allotted:

SCHEDULE FOR ALLOTMENT OF FUNDS

Date
Amounts
TBD
$TBD

(b) The Contractor agrees to perform or have performed work on the items specified in paragraph (a) of this clause up to the point at which, if this contract is terminated pursuant to the Termination for Convenience of the Government clause of this contract, the total amount payable by the Government (including amounts payable for subcontracts and settlement costs) pursuant to paragraphs (f) and (g) of that clause would, in the exercise of reasonable judgment by the Contractor, approximate the total amount at the time allotted to the contract. The Contractor is not obligated to continue performance of the work beyond that point. The Government is not obligated in any event to pay or reimburse the Contractor more than the amount from time to time allotted to the contract, anything to the contrary in the Termination for Convenience of the Government clause notwithstanding.

(c)(1) It is contemplated that funds presently allotted to this contract will cover the work to be performed until TBD.

(2) If funds allotted are considered by the Contractor to be inadequate to cover the work to be performed until that date, or an agreed date substituted for it, the Contractor shall notify the Contracting Officer in writing when within the next 60 days the work will reach a point at which, if the contract is terminated pursuant to the Termination for Convenience of the Government clause of this contract, the total amount payable by the Government (including amounts payable for subcontracts and settlement costs) pursuant to paragraphs

(f) and (g) of that clause will approximate 75 percent of the total amount then allotted to the contract.

(3)(i) The notice shall state the estimate when the point referred to in paragraph (c)(2) of this clause will be reached and the estimated amount of additional funds required to continue performance to the date specified in paragraph (c)(1) of this clause, or an agreed date substituted for it.

(ii) The Contractor shall, 60 days in advance of the date specified in paragraph (c)(1) of this clause, or an agreed date substituted for it, advise the Contracting Officer in writing as to the estimated amount of additional funds required for the timely performance of the contract for a further period as may be specified in the contract or otherwise agreed to by the parties.

(4) If, after the notification referred to in paragraph (c)(3)(ii) of this clause, additional funds are not allotted by the date specified in paragraph (c)(1) of this clause, or an agreed date substituted for it, the Contracting Officer shall, upon the Contractor’s written request, terminate this contract on that date or on the date set forth in the request, whichever is later, pursuant to the Termination for Convenience of the Government clause.

(d) When additional funds are allotted from time to time for continued performance of the work under this contract, the parties shall agree on the applicable period of contract performance to be covered by these funds. The provisions of paragraphs (b) and (c) of this clause shall apply to these additional allotted funds and the substituted date pertaining to them, and the contract shall be modified accordingly.

(e) If, solely by reason of the Government’s failure to allot additional funds in amounts sufficient for the timely performance of this contract, the Contractor incurs additional costs or is delayed in the performance of the work under this contract, and if additional funds are allotted, an equitable adjustment shall be made in the price or prices (including appropriate target, billing, and ceiling prices where applicable) of the items to be delivered, or in the time of delivery, or both.

(f) The Government may at any time before termination, and, with the consent of the Contractor, after notice of termination, allot additional funds for this contract.

(g) The provisions of this clause with respect to termination shall in no way be deemed to limit the rights of the Government under the default clause of this contract. The provisions of this Limitation of Funds clause are limited to the work on and allotment of funds for the items set forth in paragraph (a) of this clause. This clause shall become inoperative upon the allotment of funds for the total price of said work except for rights and obligations then existing under this clause.

(h) Nothing in this clause shall affect the right of the Government to terminate this contract pursuant to the Termination for Convenience of the Government clause of this contract.

(End of clause)

1852.235-71 KEY PERSONNEL AND FACILITIES (MAR 1989)

(a) The personnel and/or facilities listed below are considered essential to the work being performed under this contract. Before removing, replacing, or diverting any of the listed or specified personnel or facilities, the Contractor shall (1) notify the Contracting Officer reasonably in advance and (2) submit justification (including proposed substitutions) in sufficient detail to permit evaluation of the impact on this contract.

(b) The Contractor shall make no diversion without the Contracting Officer’s written consent; provided that the Contracting Officer may ratify in writing the proposed change, and that ratification shall constitute the Contracting Officer’s consent required by this clause.

(c) The list of personnel and/or facilities (shown below or as specified in the contract Schedule) may, with the consent of the contracting parties, be amended from time to time during the course of the contract to add or delete personnel and/or facilities.

Name
Position
To be completed during Phase-in
Program Manager

1852.242-72 DENIED ACCESS TO NASA FACILITIES (OCT 2015)

(a)(1) The performance of this contract requires contractor employees of the prime contractor or any subcontractor, affiliate, partner, joint venture, or team member with which the contractor is associated, including consultants engaged by any of these entities, to have access to, physical entry into, and to the extent authorized, mobility within, a NASA facility.

(2) NASA may close and or deny contractor access to a NASA facility for a portion of a business day or longer due to any one of the following events:

(i) Federal public holidays for federal employees in accordance with 5 U.S.C. 6103.

(ii) Fires, floods, earthquakes, unusually severe weather to include snowstorms, tornadoes and hurricanes.

(iii) Occupational safety or health hazards.

(iv) Non-appropriation of funds by Congress.

(v) Any other reason.

(3) In such events, the contractor employees may be denied access to a NASA facility, in part or in whole, to perform work required by the contract. Contractor personnel already present at a NASA facility during such events may be required to leave the facility.

(b) In all instances where contractor employees are denied access or required to vacate a NASA facility, in part or in whole, the contractor shall be responsible to ensure contractor personnel working under the contract comply. If the circumstances permit, the Contracting Officer will provide direction to the contractor, which could include continuing on-site performance during the NASA facility closure period. In the absence of such direction, the contractor shall exercise sound judgment to minimize unnecessary contract costs and performance impacts by, for example, performing required work off-site if possible or reassigning personnel to other activities if appropriate.

(c) The contractor shall be responsible for monitoring the local radio, television stations, NASA Web sites, other communications channels, for example Contracting Officer notification, that the NASA facility is accessible. Once accessible the contractor shall resume contract performance as required by the contract.

(d) For the period that NASA facilities were not accessible to contractor employees, the Contracting Officer may—

(1) Adjust the contract performance or delivery schedule for a period equivalent to the period the NASA facility was not accessible;

(2) Forego the work;

(3) Reschedule the work by mutual agreement of the parties; or

(4) Consider properly documented requests for equitable adjustment, claim, or any other remedy pursuant to the terms and conditions of the contract.

(e) Notification procedures of a NASA facility closure, including contractor denial of access, as follows:

(1) The contractor shall be responsible for monitoring the local radio, television stations, NASA Web sites, other communications channels, for example Contracting Officer notification, for announcement of a NASA facility closure to include denial of access to the NASA facility. The contractor shall be responsible for notification of its employees of the NASA facility closure to include denial of access to the NASA facility. The dismissal of NASA employees in accordance with statute and regulations providing for such dismissals shall not, in itself, equate to a NASA facility closure in which contractor employees are denied access. Moreover, the leave status of NASA employees shall not be conveyed or imputed to contractor personnel. Accordingly, unless a NASA facility is closed and the contractor is denied access to the facility, the contractor shall continue performance in accordance with the contract.

(2) NASA’s Emergency Notification System (ENS). ENS is a NASA-wide Emergency Notification and Accountability System that provides NASA the ability to send messages, both Agency-related and/or Center-related, in the event of an emergency or emerging situation at a NASA facility. Notification is provided via multiple communication devices, e.g. Email, text, cellular, and home/office numbers. The ENS provides the capability to respond to notifications and provide the safety status. Contractor employees may register for these notifications at the ENS Web site:

http://www.hq.nasa.gov/office/ops/nasaonly/ENSinformation.html

(End of clause)

MSFC 52.209-92 DISCLOSURE OF ORGANIZATIONAL CONFLICT OF INTEREST (OCI) AFTER CONTRACT AWARD (MAY 2017)

(a) If the Contractor identifies an actual or potential organizational conflict of interest that has not already been adequately disclosed and resolved (or waived in accordance with FAR 9.503), the Contractor shall make a prompt and full disclosure in writing to the Contracting Officer. This disclosure shall include a description of the action the Contractor has taken or proposes to take in order or resolve the conflict. This reporting requirement also includes subcontractors’ actual or potential organizational conflicts of interest not adequately disclosed and resolved prior to award.

(b) Organizational Conflict of Interest Plan. If there is an OCI plan in the contract, the Contractor shall periodically update the plan, based on changes such as changes to the legal entity, the overall structure of the organization, subcontractor arrangements, contractor management, ownership, ownership relationships or modification of the work scope.

MSFC 52.209-94 RESOLUTION OF ORGANIZATIONAL CONFLICTS OF INTEREST (MAY 2017)

(a) The Organizational Conflict of Interest (OCI) Plan and its obligations (which includes any appended resolution strategies related to identified OCIs), are hereby incorporated in the contract by reference.

(b) Changes. (1) Either the Contractor or the Government may propose changes to the OCI Plan. Such changes are subject to the mutual agreement of the parties and will become effective only upon incorporating the change into the plan by contract amendment.

(2) In the event that the Government and the Contractor cannot agree upon a mutually acceptable change, the Government reserves the right to make a unilateral change to the OCI Plan as necessary, with the approval of the head of the contracting activity, subject to Contractor appeal as provided in the Disputes clause.

(c) Violation. The Contractor shall report any violation of the OCI Plan, whether by its own personnel or those of the Government or other contractors, to the Contracting Officer. This report shall include a description of the violation and the actions the Contractor has taken or proposes to take to mitigate and avoid repetition of the violation. After conducting such further inquiries and discussions as may be necessary, the Contracting Officer and the Contractor shall agree on appropriate corrective action, if any, or the Contracting Officer shall direct corrective action.

(d) Breach. Any breach of the above restrictions or any nondisclosure or misrepresentation of any relevant facts required regarding OCI to be disclosed may result in termination of this contract for default or other remedies as may be available under law or regulation.

(e) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (e), in subcontracts where the work includes or may include tasks related to the OCI. The terms “Contractor” and “Contracting Officer” shall be appropriately modified to reflect the change in parties and to preserve the Government’s rights.

(End of clause)

MSFC 52.223-90 ASBESTOS MATERIAL (SEPT 2020)

During performance of this contract, Contractor personnel performing work in MSFC buildings may come in contact with materials containing asbestos. MSFC Buildings 4200 and 4663 are of special concern since they are known to contain a sprayed on fire insulation on or above the ceiling, usually located on the metal or concrete structure of the buildings. Examples of asbestos- containing material are floor tile, pipe and lagging insulation, exterior siding, roofing felt, and many other building materials. To facilitate communication, MSFC has established a website where the inventory of asbestos-containing material, their condition and approximate location are provided. The URL for this website is http://eeoh-portal.ndc.nasa.gov/asbestos. If the Contractor is unable to access this URL, they may contact the Contracting Officer or MSFC’s

Environmental Engineering and Occupational Health (EEOH) Office (organization code AS10) for assistance. Prior to performing tasks which may disturb building material containing asbestos or suspected asbestos, the Contractor shall notify MSFC’s EEOH Office for assistance. The Contractor shall also be responsible for ensuring that all Contractor personnel working onsite are made aware of and comply with the requirements of this clause.

MSFC 52.223-91 HAZARDOUS MATERIAL REPORTING (FEB 2016)

(a) If during the performance of this contract, the Contractor transports or accepts delivery of any hazardous materials (hazardous as defined under the latest version of Federal Standard No. 313, including revisions adopted during the term of the contract) on-site to Marshall Space Flight Center, the hazardous material shall be processed through MSFC Central Receiving to be bar-coded for inventory. Alternative receiving points may be designated if approval is granted in accordance with MWI 8550.5, “Hazardous Material Management.” Chemical containers shall be managed in accordance with the provisions of MWI 8550.5. The Contractor shall be responsible for ensuring that all Contractor/subcontractor personnel are made aware of and comply with this clause.

(b) Nothing contained in this clause shall relieve the Contractor from complying with applicable Federal, State, and local laws, codes, ordinances, and regulations (including the obtaining of licenses and permits) in connection with hazardous material; or with clauses regarding hazardous materials, which may be contained in the contract and/or order.

(End of clause)

MSFC 52.223-92 ENVIRONMENTAL - GENERAL CLAUSE (AUG 2010)

Contractors performing on-site shall comply with all applicable Environmental policies and procedures including, but not limited to, MPD 8500.1, “MSFC Environmental Management Policy” and MPR 8500.1, “MSFC Environmental Engineering and Occupational Health Program.” MSFC contractors performing on-site activities that could potentially impact the environment shall be responsible for following all established NASA/MSFC environmental procedures. These procedures and other applicable policies and procedures are available by contacting the NASA/MSFC Environmental Engineering & Occupational Health Office. Failure to comply with environmental policies and procedures, may result in damage to the environment, and could potentially result in regulatory penalties against NASA and/or the Contractor, and Contractor loss of access to NASA/MSFC facilities.

MSFC 52.223-95 PREVENTION OF AND RESPONSE TO THREATENING OR VIOLENT BEHAVIOR IN THE WORKPLACE (MAR 2017)

The Contractor shall comply with all applicable Contractor responsibilities set forth in Marshall Procedural Requirements (MPR) 1600.2, “Prevention of and Response to Threatening or Violent Behavior in the Workplace”.

(End of clause)

MSFC 52.223-96 MEDICAL SERVICES (SEP 2018)

Contractors with employees requiring NASA-specific and Occupational Health and Safety Association (OSHA) required medical certification health examinations may utilize the MSFC Medical Center’s service provider for such services; however, the Contractor is responsible for all associated costs and payments. The MSFC Medical Center’s service provider is located in Building 4249 and is generally open between 7:00 a.m. and 4:30 p.m., Monday through Thursday and 7:00 a.m. to 3:30 p.m. every other Friday (excluding Government holidays, Center-approved closures, early dismissals, or delayed openings), coinciding with the MSFC flexible work schedule. Contractors should utilize the MSFC emergency medical services system for any incident that occurs at MSFC and which requires emergency medical treatment by dialing 911. Additional emergency contact numbers are accessible from the MSFC “Safety, Health and Environmental - SHE” Web site located on the ExplorNet Web page https://nasa.sharepoint.com/sites/msfc_she/. Refer to MWI 1800.1, “MSFC Occupational Medicine” and MWI 3410.1, “Personnel Certification Program” for additional information.

(End of clause)

MSFC 52.223-97 MANDATORY AND REQUIRED TRAINING (NOV 2019)

All Contractor personnel performing work onsite at MSFC or MAF shall complete, in a timely manner, all applicable mandatory and required training courses listed below, as well as any other current or future training requirements specified in the Statement of Work, Performance Work Statement, Specifications, Applicable Documents (including NASA, MSFC and Organizational level directives), Data Requirements Descriptions, other contract clauses and/or the System for Administration, Training, and Educational Resources for NASA (SATERN). SATERN provides web-based access to many required training courses. Contractor employees may be provided access to SATERN. The Contractor shall maintain training records for each employee, documenting the completion of this and any other required training. A list of the mandatory and required training including their titles, delivery method, frequency and target audience is accessible from the MSFC ExplorNet Web page at: https://nasa.sharepoint.com/sites/msfcohr/SitePages/Mandatory-Training.aspx The content of the list and the training itself are subject to change without notice. Training for its employees and subcontractors shall be the responsibility of the Contractor. Some certification courses are offered to the Contractor on a limited space available basis, and MSFC makes no obligation to provide this training to Contractor personnel. MSFC Contractors may develop their own training for those courses not provided, or obtain it from a qualified outside vendor.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .