Question 36: 2. Page 57, letter d in the Past Performance Factor description. What matrix is being referenced here: “Complete the incorporated matrix as part of your response.”

Response 36: The Matrix has been posted as an attachment to this Amendment

Question 37: Page 58, letter g in the Past Performance Factor description. Is there information missing after letter “g”? What should come after “the following” in this sentence: “For all work performed during the past three years, offerors shall provide the following:”

Response 37: Requirement “g” is deleted.

Question 38: Page 59, Subcontracting Arrangement Information, (a): Please clarify what the “primary and vital requirements for the contract” are. Also, if a prime/subcontractor teaming arrangement is to be used, does the Government have a preference on the split of the responsibilities between the prime and subcontractor? The questions in this and other sections of the RFP imply that the Government does have preferences for teaming responsibilities that have not been explicitly stated.

Response 38: Subcontracting Arrangement Information is used to determine compliance with Small Business Size and Affiliation with respect to ostensible subcontracting.