Att_E_533_instructions.pdf

PDF 9 KB Posted

Attached to
Supra Thermal Ion Sensor (STIS) Instrument Federal contract opportunity
Solicitation number
80GSFC19R0033
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

This document outlines financial management reporting requirements for a contract to develop a Supra Thermal Ion Sensor instrument. The contractor must submit NASA Form 533 reports on a monthly and quarterly basis detailing direct labor hours, costs, overhead expenses, other direct costs including subcontracts and materials, general and administrative expenses, total estimated cost, fixed fee, schedule incentives, and total cost-plus-fixed-fee. The reports must include a separate 533 for each level 3 element of the statement of work and provide a variance narrative for variances exceeding 5% to the total direct labor hours and total estimated cost from the prior reporting period. Distribution of the reports is also specified.

The related federal contract opportunity is a solicitation by NASA Goddard Space Flight Center for the Supra Thermal Ion Sensor instrument to support the Space Weather Follow On mission. Deliverables include one flight model, one engineering development unit, flight harnesses, and spares. The scope of work covers design, analysis, development, fabrication, integration, testing, calibration, evaluation, launch support, and mission operations handover. The contract type will be cost-plus-incentive-fee. Small business goals include 6% total, with targets for small disadvantaged, women-owned, HUBZone, veteran-owned, and service-disabled veteran-owned small businesses. The NAICS code is 336414 and size standard is 1,250 employees. Proposals are due 45 days following release of the request for proposal anticipated in fall 2019.

Attachment E 533 Instructions

View the file

Other files for this federal contract opportunity

Other files attached to Supra Thermal Ion Sensor (STIS) Instrument, newest first.
File Type Posted
STIS Questions and Responses 1-24-20.(additional).pdf PDF
STIS Questions and Responses 1-24-20.pdf PDF
STIS Questions and Responses 12-19-19.pdf PDF
Att B_Amend 003_changes identified_L1-STISSPEC-0002_Ver0.2.pdf PDF
Att C_Amend 003_changes identified_L1-STISCDRL-0003_Ver0.2 .pdf PDF
Att A_Amend 003_changes identified__L1-STISSOW-0001_Ver0.2.pdf PDF
STIS Questions and Responses 12-11-19.pdf PDF
STIS SF33 Amend 003.pdf PDF
STIS SF30 Amend 003.pdf PDF
Att B_Amend 003_L1-STISSPEC-0002_Ver0.2 12-6-19-sign.pdf PDF
Att A_Amend 003_-L1-STISSOW-0001_Ver0.2-signed.pdf PDF
Att C_Amend 003_L1-STISCDRL-0003_Ver0.2-signed.pdf PDF
STIS Amendment 003 continuation page.pdf PDF
STIS RFP Cover letter Amend 003.pdf PDF
STIS_SF30_Amend_002_(003).pdf PDF
STIS_Questions_and_Responses_Amendment_002_Final.pdf PDF
STIS_SF33_Amendment_002_Final.pdf PDF
STIS_Sections_L_and_M_Amendment_002_Final.pdf PDF
RFP_80GSFC19R0033_Amd_001.pdf PDF
Amd_1_SF30.pdf PDF
Att_A_422-L1-STISSOW-0001_Ver0.1_-_Signed.pdf PDF
1RFP_80GSFC19R0033.pdf PDF
Att_K_IT_Security_Applicable_Documents_List.pdf PDF
Att_C_422-L1-STISCDRL-0003_Ver0.1(1)_-_Signed.pdf PDF
Exhibit_1_SB_SC_Goals.pdf PDF
Att_B_422-L1-STISSPEC-0002_Ver0.1_-_Signed.pdf PDF
SF33.pdf PDF
Encl_1_STIS_QASP.pdf PDF
RFP_Cover_Letter.pdf PDF
Att_D_422-L1-IMAR-0004_Ver0.1_-_Signed.pdf PDF
Encl_2_IT_Security_Management_Plan_Template.pdf PDF
Encl_3_PastPerfQues.pdf PDF
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT E

FINANCIAL MANAGEMENT REPORTING

REQUIREMENTS

SUPRA THERMAL ION SENSOR (STIS)

RFP 80GSFC19R0033R

CONTRACT TBD

Contract TBD Attachment E

(06/2014) 2

FINANCIAL MANAGEMENT REPORTING REQUIREMENTS

Financial Management Reports shall be submitted by the Contractor on the NASA 533 series reports, in accordance with the instructions on the reverse of the forms, NASA Procedural Requirements NPR 9501.2E entitled "NASA Contractor Financial Management Reporting,” dated May 27, 2011, and additional instructions issued by the Contracting Officer.

a. Level of Detail

The Contractor’s 533 Reports shall contain a summary of total contract costs, as well as a separate 533 Report for each Work Breakdown Structure (WBS) Level 3 element of the Statement of Work. The reports shall contain a breakdown of hours and costs by the elements of cost categories listed in Section d below.

b. Variance Narrative Reporting

In accordance with Section 3.6 of NPR 9501.2, the Contractor shall include a narrative explanation for variances exceeding plus or minus 5 percent (+/- 5]%) between the Total Direct Labor Hours (prime and subcontractors) and/or Total Estimated Cost amount shown in the prior month and the Actual Total Direct Labor Hours and/or Actual Total Cost amount shown in the current month at WBS Level 3. (For example, the Total Estimated Cost amount shown for June in column 8a in the May NF 533M and the Actual June Total Cost amount shown in column 7a in the June NF 533M.)

Each variance narrative shall explain the: (1) reason for the variance, (2) impact(s) on the Core baseline and/or each individual task order, and (3) specific corrective action(s) being taken or to be taken.

c. Distribution

The Contractor shall distribute 533 reports to each addressee indicated in the contract clause entitled, "Financial Management Reporting." The Contractor shall submit an initial report in the NF 533Q format within 30 working days after contract award.

After the initial report, the NF 533M reports shall be distributed not later than the tenth (10th) working day following the close of the contractors' monthly accounting period.

The 533Q reports shall be distributed not later than the fifteenth (15th) day of the month preceding the quarter being reported. The NF 533M need not be submitted in months in which an NF 533Q is submitted.

d. Reporting Requirements

Each individual report shall, at a minimum, provide cost data by the following elements of cost categories:

Contract TBD Attachment E

(06/2014) 3

1. Prime Direct Labor Hours:

Total Prime Direct Labor Hours

2. Subcontractor Direct Labor Hours:

Subcontractor A Direct Labor Hours

Subcontractor B Direct Labor Hours

Subcontractor C Direct Labor Hours

Total Subcontractors Direct Labor Hours

3. Total Prime and Subcontractors Direct Labor Hours

4. Prime Direct Labor Costs:

Total Prime Direct Labor Costs

5. Prime Overhead Expense

6. Other Direct Costs (ODCs):

a. Subcontracts (list separately, Subcontractor A, B, C, etc.)

b. Material

c. Travel

d. Other (specify)

Total ODCs

7. Subtotal (Direct Labor, Overhead & ODCs)

8. G&A Expense

9. Total Estimated Cost

10. Fixed Fee

11. Schedule Incentive

12. Total Cost-Plus-Fixed-Fee (CPFF)