This document is a project manual for bridge and water control structure rehabilitation work at Seney National Wildlife Refuge. The project includes site preparation, erosion control, excavation, demolition, concrete construction and repair, guardrail installation, stoplog replacement, road surfacing, grading, signage, riprap placement, and site restoration. Key tasks involve mobilization and demobilization, site work and water control, site construction, bridge and wall repair/replacement, concrete patching and coating, epoxy injection, and equitable adjustments for material quantities that vary more than 15% from estimates. The contract was awarded by the U.S. Fish and Wildlife Service with a notice to proceed by January 2022, pending permit and clearance approvals. The project manual provides construction specifications and requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140F0821R0008_Amd_0002.pdf | ||
| Question_and_Answer_Document_AE_0002.pdf | ||
| Sol_140F0821R0008_Amd_0001.pdf | ||
| 11_Price_Schedule.pdf | ||
| 7_Plans_C-B.pdf | ||
| 3_Plans_F-E.pdf | ||
| 1_Plans_BidPct_WCS_E-D.pdf | ||
| Sol_140F0821R0008.pdf | ||
| 9_General_Location_Maps.pdf | ||
| 6_Specs_E-C.pdf | ||
| 4_Specs_F-E.pdf | ||
| 2_Specs_BidPct_WCS_E-D.pdf | ||
| 10_Wage_Rates.pdf | ||
| 5_Plans_E-C.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
©Stanley Consultants, Inc. 2021
Project Manual for
Bridge/Water Control Structure Rehabilitation (WCS C-B)
Seney National Wildlife Refuge Schoolcraft County, Michigan Contract No. 140F0318D0021 Task Order No. 140F0221F0014
United States Department of the Interior Fish and Wildlife Service, Region 3
June 2021
©Stanley Consultants, Inc. 2021
Project Manual for
Bridge/Water Control Structure Rehabilitation (WCS C-B)
Seney National Wildlife Refuge Schoolcraft County, Michigan Contract No. 140F0318D0021 Task Order No. 140F0221F0014
Fish and Wildlife Service, Region 3
Issued for Bid June 2021
Page J - 1
PART III, SECTION J
LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
INVITATION NO. 301817BXXX
INDEX
TECHNICAL PROVISIONS/SPECIFICATIONS
DIVISION 1 - GENERAL REQUIREMENTS
SECTION 01100 SUMMARY OF THE WORK
PRECONSTRUCTION SAFETY CHECKLIST
SECTION 01310 PROJECT COORDINATION
IMPLEMENTING AND ENFORCING MASK-WEARING
REQUIREMENTS FOR VISITORS
UPDATED MASK GUIDANCE FOR FEDERAL EMPLOYEES AND
BUILDINGS
SECTION 01330 SUBMITTALS
TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA,
MATERIAL SAMPLES, OR MANUFACTURER’S
CERTIFICATES OF COMPLIANCE FOR APPROVAL
SECTION 01420 DEFINITIONS AND STANDARDS
SECTION 01 45 33 STORM WATER POLLUTION PREVENTION PLAN
OWNER CERTIFICATION STORM WATER POLLUTION
PREVENTION PLAN
CONTRACTOR CERTIFICATION OF STORM WATER
POLLUTION PREVENTION PLAN
STORMWATER DISCHARGE FROM CONSTRUCTION
ACTIVITIES
SECTION 01 57 13 TEMPORARY EROSION AND SEDIMENT CONTROLSECTION
SECTION 01770 PROJECT CLOSEOUT
DIVISION 02 – EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 01 30-17 CONCRETE REHABILITATION
03 15 16 EXPANSION JOINTS AND WATERSTOPS
03 20 00 CONCRETE REINFORCING
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 05 - METALS
05 50 00 METAL FABRICATIONS
DIVISION 09 - FINISHES
09 90 00 PAINTING AND COATING
DIVISION 10 - SPECIALTIES
10 14 69 STAFF GAGES
DIVISION 31 - EARTHWORK
31 23 00 EXCAVATION AND FILL
31 35 19-16 GEOTEXTILE SLOPE PROTECTION
DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION
35 43 37 RIPRAP SCOUR PROTECTION
DIVISION 43 – PROCESS GAS AND LIQUID HANDLING,
PURIFICATION, AND STORAGE EQUIPMENT
43 26 26-13 STOPLOGS AND TIMBERS
ATTACHMENTS
SUBMITTAL REGISTER
NORTH SHOW POOL GEOTECHNICAL REPORT, SENEY, MI
DIVISION 1 SECTION 01100
GENERAL REQUIREMENTS SUMMARY OF THE WORK
01100-1
PART 1 - GENERAL
1.1 Project Title: Seney National Wildlife Refuge Bridge/Water
Control Structure (WCS) Rehabilitation.
1.2 Work Under These Specifications
A. Contractor shall furnish materials, labor and equipment for Work described below. Measurement and payment shall be as defined below. Project shall include site preparation, erosion control, excavation, dewatering, demolition, concrete construction and repair, guardrail repair and installation, stoplog replacement, gravel roadway surfacing, embankment and channel grading, signage, riprap placement, and site restoration. Summary of work below is not all inclusive, and Contractor shall perform all the required work that is in the contract documents.
I-1: Mobilization and Demobilization.
This item includes mobilizing and demobilizing all equipment and personnel necessary to construct the work as outlined on the Drawings and specified herein. Mobilization shall include site preparation and demobilization shall include site cleanup. All permits, bonds, and similar items are to be included in this item. Payment for this item will be by lump sum.
I-2: Site Work and Control of Water.
This item includes dewatering the work area, managing water level and flows past the work site, additional miscellaneous site work, installing and maintaining temporary erosion control, developing site access, and repairing disturbed areas as outlined on the Drawings and as specified herein. Work will require cofferdams and diversion of water. Coordinate with Refuge regarding water level control during construction period. Payment for this item will be lump sum.
01100-2
I-3: Site Construction.
This item includes providing all materials, equipment and labor for grading embankment slopes and channel, constructing a gravel road on the embankment, and placing riprap on the channel banks upstream and downstream of the structure. Work includes but is not limited to excavation of channel banks, placing earthen and granular fill, placement of geotextile and gravel road surfacing, and placement of geotextile and riprap. Payment for this item will be lump sum.
I-4: Bridge and Wall Repair/Replacement.
This item includes providing all materials, equipment and labor for removal of existing bridge features, stoplogs, guardrail; partial/complete removal of concrete piers, abutment walls, and bulkhead walls;
construction/repair of bridge features, concrete piers and bulkhead wall; reinforced concrete overlay of the existing concrete slab, installation of guardrails, repair of stoplog slots, and providing new wood stoplogs and lifting poles. Work includes but is not limited to structure removal, placement of reinforced concrete, fabricating and installing guardrail and stoplogs, replacing/repairing the staff gage, bridge deck joint repairs and silt excavations.
Payment for this item will be lump sum.
I-5: Concrete Patch (Thick Patch).
This item includes providing all materials, equipment and labor for repairing degraded portions of the existing concrete surfaces of bridge pier walls, upstream headwalls, and bottom slab with a concrete patch greater than four (4) inches thick. Work includes but is not limited to locating repair areas, cutting away degraded portions of surface concrete, removing deteriorated concrete, abrasive blasting reinforcing steel, splicing reinforcing steel, 01100-3 prepping wall surfaces for repair, repairing walls/slab by placement of cement mortar patches.
Payment for this item will be lump sum for the estimated repair area. The Contractor will be responsible for measuring the repair area which will be verified by the Government or its representative.
If the actual repair area differs from the estimated repair area by more than fifteen percent (15%) an equitable adjustment in the contract price shall be made upon demand of either party.
I-6: Polymer-Cement Mortar Patch (Thin Patch).
This item includes providing all materials, equipment and labor for repairing degraded portions of the existing concrete surfaces of bridge pier walls, upstream headwalls, and bottom slab with a thin concrete patch approximately two (2) inches thick.
Work includes but is not limited to locating repair areas, cutting away degraded portions of surface concrete, removing deteriorated concrete, prepping surface for repair, repairing walls/slab by placement of cement mortar patches. Payment for this item will be lump sum for the estimated repair area. The Contractor will be responsible for measuring the repair area which will be verified by the Government or its representative. If the actual repair area differs from the estimated repair area by more than fifteen percent (15%) an equitable adjustment in the contract price shall be made upon demand of either party.
I-7: Polymer-Cement Mortar Coat.
This item includes providing all materials, equipment and labor for surficial repair of degraded portions of the existing concrete surfaces of bridge pier walls, upstream headwalls, and bottom slab with a polymer-cement mortar coating. Work includes but is not limited to locating repair areas, cutting away degraded portions of surface concrete, prepping surfaces for repair and repairing walls/slab by
01100-4 placement of a polymer-cement mortar coating.
Payment for this item will be lump sum for the estimated repair area. The Contractor will be responsible for measuring the repair area which will be verified by the Government or its representative.
If the actual repair area differs from the estimated repair area by more than fifteen percent (15%) an equitable adjustment in the contract price shall be made upon demand of either party.
I-8: Epoxy Resin Injection.
This item includes providing all materials, equipment and labor for injecting epoxy resin in areas of concrete cracks. Work includes but is not limited to locating areas requiring injection, drilling injection ports, and injecting epoxy resin. Payment for this item will be lump sum for the estimated repair area. The Contractor will be responsible for measuring the repair area which will be verified by the Government or its representative. If the actual repair area differs from the estimated repair area by more than fifteen percent (15%) an equitable adjustment in the contract price shall be made upon demand of either party.
Equitable Adjustment in the Contract Price.
Equitable adjustment in the contract price will only apply to Items 5, 6, 7 and 8. If the actual quantity of Items 5, 6, 7, or 8 in this contract varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price for that item shall be made upon demand of either party. The unit of measurement will be the square foot. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the
01100-5
Contracting Officer within 10 business days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgement of the Contracting Officer, is justified.
B. All required Quality Control testing shall be performed and paid for by the Contractor. The Contractor shall hire an Independent Third-Party Testing Agency to perform all required Quality Control testing as well as any Inspections required per permit authorities.
C. Contractor shall obtain and pay for all required construction permits.
D. Reference drawings provided are for reference only. It is the contractor’s responsibility to verify site conditions prior to placing a bid.
E. The Government retains the right to limit any additional work proposed by the Construction Contractor (e.g. additional concrete repairs proposed by the Contractor’s Independent Third Party Test Agency/ Inspector that may be included in their Concrete Condition Survey/Concrete Repair Plan, etc.)
under the unit price items, or elsewhere in the plans/ specifications, contained in the project.
1.3 Location And Inspection Of Site
A. The work site is located at Seney National Wildlife Refuge, Schoolcraft County, Michigan.
The mailing address is:
1674 Refuge Entrance Rd
Seney, MI 49883
01100-6
The Contracting Officer may be contacted for further information at Justine_pasiecnik@fws.gov and (413) 253-8287. The preferred method of contact is email.
B. Site Contact: Sara Siekierski, Refuge Manager, telephone (906)630-2015.
C. All prospective bidders/quoters, contractors, sub-contractors, and related persons are encouraged to visit the site(s) of the proposed Work any time after March 15th and assess the location(s) and extent of the Work prior to submitting bids/quotes. Persons may inspect the site by contacting the Refuge Manager.
1.4 Specifications and Drawings for Construction
A. The successful bidder will be provided, upon request, up to 5 sets of additional full-size prints of the contract drawings as necessary for execution of this contract. These drawings will be provided at no additional cost to the successful bidder/quoter.
B. Exact location of all affected utilities shall be the responsibility of Contractor. Drawings may not completely show all utilities. Site verification is required in addition to contacting any local authorities and utility companies to determine exact locations of utilities.
C. In case of difference between drawings and specifications, the specifications shall govern.
1.5 Work Not Included In This Contract
A. All items indicated "NIC" on drawings or in specifications are items not included in this contract.
B. Work in place is generally shown as "Existing" on the
Contract Drawings.
mailto:Justine_pasiecnik@fws.gov
01100-7
C. Work to be performed under other contracts and not included as part of this contract is generally shown as "By Others" on the Contract Drawings.
1.6 Items Provided By The Government
A. Work to be accomplished by the Government or manufactured items to be provided by the Government are generally shown as "By Government" on the Contract Drawings.
1. Unless specifically provided herein, no materials or equipment shall be furnished by the Government under this Contract.
1.7 Engineering Services:
A. The Government has established a baseline and a benchmark for this project. The drawings relate the project to the baseline and benchmark. From this baseline and benchmark the Contractor shall furnish and place all stakes, marks, and templates required for the performance and completion of the work. Any baseline monuments or benchmarks disturbed or removed during construction shall be reset by the Contractor at their expense.
1.8 Temporary Facilities
A. Maintain and restore all government roads, service areas and utilities used to pre-construction condition.
B. Temporary toilet facilities must be provided.
1.9 Site Access and Right of Way
A. The construction access limits on Government property will be established by the Government and the Contractor shall be responsible for complying with these limits and governing all work accordingly. All temporary access roads shall be removed following work
01100-8 completion unless directed otherwise by the Contracting Officer.
B. All bidders are reminded that they are responsible for contacting the local entity such as township, county, or state having jurisdiction in the project vicinity to ensure bidders/quoters are aware of any requirements of the local entity. These requirements are between the entity and the bidder. Load limits and other restrictions shall be obeyed. If the Contractor proposes to cross private property, permission must be obtained from the owner to use private property or roads in the conduct of the Work.
C. Work scheduled on Saturdays, Sundays, Federal Holidays or other than normal working hours shall be approved in advance by the Government.
1.10 POOL LEVELS DURING CONSTRUCTION
A. Contractor shall contact the Refuge for typically-maintained normal summer pool elevation from Mid-April to Mid-September.
B. Cofferdams/sheetpiling will be necessary upstream and downstream of the Structure to fully dewater.
Contractor shall coordinate with Refuge for cofferdam phasing and bypassing flows during construction.
C. The Contractor shall maintain dewater conditions during construction within cofferdam areas. Provide dewatering systems as necessary to perform all work.
D. The Contractor shall coordinate the maintenance of the pool elevation with the Refuge. The Refuge may assign the Contractor the responsibility of maintaining pool levels using the Structure or other pool water control structures during construction.
01100-9
E. The Contractor shall coordinate all water control structure operations with the Refuge. All water control structure operations are subject to approval from the Refuge.
F. If project work below the normal summer pool elevation extends into the summer pool season (Mid-April to Mid- September), the Contractor shall provide adequate cofferdam/sheet piling systems so the normal summer pool elevation can be maintained and project work can continue.
G. Contractor shall have the capability to keep site runoff out of construction area and safely pass flows downstream for rain events of less than 2.5 inches in 24 hours.
H. Contractor shall design and submit emergency action plans for rain events of more than 2.5 inches in 24 hours that meet the following requirements:
1. Signed and Sealed by a professional engineer registered in the State of Michigan.
2. Provided to the Government for review a minimum of fourteen (14) calendar days prior to the start of construction for review and potential revision.
3. Contractor shall allow for at least one (1) foot of freeboard below top of upper pool embankments and passage of flow without damaging new and existing structures, existing embankments, or downstream structures.
4. Can be implemented within 24 hours.
I. If the Pool Elevation reaches 703.5 ft, the Contractor shall contact the Refuge and Regional Dam Safety Officer immediately. The elevation is based off existing staff gages on the Refuge (Mean Sea Level datum, MSL).
01100-10
J. The Regional Dam Safety Officer contact information is:
Matthew Spielbauer, P.E.
Matthew_spielbauer@fws.gov
(email is preferred method of contact)
(612) 713-5269
K. Contractor shall maintain the upper pool level for the structure as indicated below in the duration of construction.
(MSL, ft) March
Pool 15 1 15 1 15 1 15 1 15 1 15 1 15 1 15 1 15 A - 1 693.6 693.6 693.6 693.1 693.1 693.1 692.6 692.6 692.1 692.1 692.1 692.6 692.6 693.1 693.1 693.6 693.6 B - 1 699.0 699.0 699.0 698.5 698.5 698.5 698.0 698.0 697.5 697.5 697.5 698.0 698.0 698.5 698.5 699.0 699.0 C - 1 702.3 702.3 702.3 701.8 701.8 701.8 701.3 701.3 700.8 700.8 700.8 701.3 701.3 701.8 701.8 702.3 702.3 D - 1 704.9 704.9 704.9 704.4 704.4 704.4 703.9 703.9 703.4 703.4 703.4 703.9 703.9 704.4 704.4 704.9 704.9 E - 1 706.6 706.6 706.6 706.1 706.1 706.1 705.6 705.6 705.1 705.1 705.1 705.6 705.6 706.1 706.1 706.6 706.6 F - 1 708.9 708.9 708.9 708.4 708.4 708.4 707.9 707.9 707.4 707.4 707.4 707.9 707.9 708.4 708.4 708.9 708.9
August September October NovemberApril May June July
L. USFWS’s expectation is based on environmental compliance for avoiding take of nesting water birds.
The contractor shall allow passthrough for water levels that exceed the April 15 targeted pool elevation. Pass through should be sufficient to prevent the pool temporarily rising more than 4 inches above the targeted pool level April 15 - September 30.
Any construction outside of these dates shall ensure the pools do not exceed maximum dam capacity threatening dam safety or integrity and will contact refuge manager immediately.
In the event construction causes a significant and rapid loss of water in the pool (more than 6 inches within 24 hours), Contractor shall notify the Refuge of such situations. The contractor may be responsible for restoring pool levels if advisable by refuge manager (contingent on availability of water from surrounding pools and impact to existing nesting birds).
The pool elevations are the targeted spring water levels (MSL elevations) that we would typically manipulate the stoplogs to achieve. Once the pool has mailto:Matthew_spielbauer@fws.gov
01100-11 reached the March/April desired elevations, we set the stoplogs to maintain that elevation while allowing excess rain event volumes to flow downstream. During the summer the pools typically experience a decrease in water levels due to evapotranspiration (and some leakage and seepage), as much as 12 inches to 16 inches but sometimes less depending on weather. The Refuge anticipates this when determining the spring targets and allow the pool to fluctuate this way, and do not mitigate for this loss of water, nor would require the contractor.
M. Vertical Datum conversion is
MSL = NAVD 88 – 0.055 ft
1.11 Safety - In addition to FAR 52.236-13 Accident Prevention
A. Contractor shall fill out and submit the “Preconstruction Safety Checklist” to the Contracting Officer (CO) prior to beginning construction.
B. The contractor shall designate a safety officer to ensure a safe work site. The safety officer shall perform daily work site inspections to assure compliance with all safety regulations and standards.
C. The Contractor’s Safety Plan shall be available on-site. The Contractor shall provide Material Safety Data Sheets (MSDS) for all hazardous materials brought on-site. MSDS shall be made available in a conspicuous location.
D. All equipment and work activities shall comply with
OSHA Regulations and all accidents incidental to work performed under this contract shall be reported in accordance with OSHA reporting requirements.
Additionally, a copy of the accident report shall be provided to the Contracting Officer.
01100-12
E. The contractor shall provide and install barricades, signs, or other warning devices to delineate the construction area and restrict public access to the construction site. Follow Manual of Uniform Traffic Control Devices (MUTCD).
F. Provide at least one non-freezing-type fire extinguisher in each workshop and shed used for storage of materials on the premises. Place in location readily accessible to workers.
G. Provide at least one non-freezing-type fire extinguisher of the appropriate class for each group of workers performing flammable procedures.
H. Provide and maintain a basic first aid kit for use of workers.
(a) Provide first aid supply commensurate with size of project with items necessary for first aid treatment of all injuries. The first aid supply shall include items identified on MSDS (see paragraphs B and C of this section) in applicable locations.
(b) Advise all workers of the location of first aid supplies.
(c) Post telephone numbers of nearest hospital or ambulance service and fire station in conspicuous location. Coordinate with Refuge for location of signs. Advise all workers of location of telephone numbers.
(d) If work is between October 20 - May 15, when exterior gates to construction site are locked, advise workers to meet ambulance at locked gates.
I. Provide necessary Personnel Protective Equipment (PPE) as identified by MSDS and OSHA regulations. Provide documentation, workers have been trained in use of PPE prior to individual use.
01100-13
PART 2 – PRODUCTS AND EQUIPMENTS
A. Products used for the project that may contain invasive species/seeds, etc. shall be purchase locally, at minimum, from sources in Upper Peninsula of Michigan.
B. All equipments coming on site for construction shall be sanitized and free of invasive species/seeds, etc.
that may affect the Refuge biology.
PART 3 - EXECUTION
A. Construction under the “hot” or “cold” conditions shall follow requirements within respective Project Specifications at Contractor’s expense.
B. It is the Contractor’s responsibility to gain access to sites (including any associated costs) if Contactor elects to perform work during cold weather/snow season (e.g. plow roads themselves, heat work area, heat materials, opening/locking gates, etc.). Any and all cost associated with these items shall be included in the Construction Contractor’s Bid/Proposed Cost.
(END OF SECTION 01100)
PRECONSTRUCTION SAFETY CHECKLIST
PROJECT LOCATION:
PRECONSTRUCTION MEETING
DATE:
NAME AND ADDRESS OF
CO NT RACT OR :
NAME OF CONTRACTOR
SU PER INT EN DE NT /FO RE M AN
NAME OF SERVICE
CONTRACTING OFFICER:
NAM E O F C ON TR ACT OR ’S
COM PETEN T PERSO N (PER 29
CFR
PROPOSED CONSTRUCTION
STAR T D ATE:
PROJECT T ITLE: CONTRACT NUMBER:
The Fish and Wildlife Service (FWS) places safety and health as a top priority at all Service contracted construction sites (360 FW 4). The contractor has ultimate responsibility for safety during construction until final completion and acceptance of the project by FWS.
This checklist serves as an assurance tool/guide in assessing safety program preparations of the contractor, and is not all-inclusive. As tasks change and new risks and hazards are introduced, you may need to address additional safeguards and corrective measures.
The contractor and subcontractor(s) must comply with all Occupational Safety and Health Administration (OSHA) regulations applicable to the construction project, including requirements set forth w ithin solicitation provisions and contract clauses (e.g., FAR 52.236-13 “Accident Prevention” with Alternate I and Special Provisions). It is the responsibility of the contractor/subcontractor(s) to adhere to regulations found at 29 CFR 1910, 1926, and 1928. (See page 5 for Table of Contents of OSHA Construction Safety Standards.) Each contractor/subcontractor must initiate and maintain an effective safety program that provides adequate systematic policies, procedures, and practices to protect their employees from, and allow them to recognize, job-related safety and health hazards. The program must include provisions for the systematic identification, evaluation, and prevention/control of general work s ite hazards, specific job hazards, and potential hazards that may arise from foreseeable conditions, as well as providing a competent person to conduct frequent and regular inspections. The contractor must instruct each employee to recognize and avoid unsafe conditions and the regulations applicable to the work environm ent.
The contractor may use at its option the latest edition of the “Bureau of Reclamation Safety and Health Standards” manual and appedixes as a safety program implem entation guide for the duration of the contract. .
The contractor will address the following items prior to and/or during the Preconstruction Conference (the Contracting
Officer/Contracting Officer’s Representative will record these items):
1.
FAR 52.236-13, Accident Prevention, Alternate I and applicable safety provisions?
The contractor has read and understands his/her re spo nsibilities for compliance with contractual safety language -
NO ___YES ___
2. Has contractor prepared a Safety Plan that analyzes anticipated hazards of the project and indicates how the hazards will be controlled?
use, scaffolding, excavat
Contractor must identify specific procedures for controlling hazardous operations such as crane
NO ___ion/trenching, hot work/welding, etc,. ES ___ Y N/A
FWS Form 3-2199 09/01 Page 1 of 5
3. How will contractor/subcontractor address the four leading hazards of construction work: falls, struck by, caught in/between, and electr ical?
4. The “Designated Competent Person” (responsible for the pro ject’s safety and health performance) is knowledgeable corrective measures?
in applicable OSHA regulations and capable of identifying existing/predictable hazards, and has the authority to prompt
YES ___ NO ___
5.
haza
Do contractor and subcon tractor em ployees know wha t to do in the event of an em erge ncy (e.g., injury, fire, accident, ESYrdous material spill, etc.) with regard to the following actions? NO
a. Notification of Departm ent, FW S Facility Manager, CO, COR, CI, etc.
b. Means of com munication with contact numbers (e.g., radio, cellular, pager, etc.).
c. Availability of first-aid/medically-trained contractor personnel with appropriate medical supplies.
d. Personnel (including subcontractors) knowledge of location for imm ediate aid (e.g., first-aid, etc.).
e. Evacuation routes, signals, and procedures are provided to all on-site personnel.
f. Safety and health information disseminated to all site personnel (e.g., contractor and subcontractor employees).
6.
(If no, skip to # 7)
a. Location and type of trailer (office or equipment).
b. Telephone hook-up.
c. Electrical hook-up.
d.
W ill a contractor/s ubc ontra ctor tra iler be broug ht on site and its hook-up/p lacem ent coord inated with COR /CI?
e. Propane used for heating?
f. Serve as first-aid station? YES
Vehicle parking arrang em ent (adequate space).
YES ___
___NO ___
NO ___
7. Is contractor aware that he/she must ensure construction area is clearly delineated and posted with appropriate warning signs (e .g., “Hard Hat Area”, “Construction Site – CLOSED”, rea C losed to Public”, etc.), and that instructional signs (e.g., designated parking area, etc.) and flagmen or barriers may be required? Yes No
Housekeeping - Is contractor/subcontractor aware that they must ensure that following acceptable housekeeping
NO
“A
8.
standards are practiced from project’s start to finish?
YES
a. Form/scrap lumber with protruding nails and all other debris shall be kept clear from work areas.
b. Combustible scrap and debris shall be removed at regular/frequent intervals.
c. Materials shall be stored with regard to their fire characteristics with effective fire protection and prevention measures used.
d. An enclosed chute shall be used whenever materials are dropped more than 20 feet to an exterior point of a building.
e. Aisles, exits, and passageways shall be kept clear and in good repair.
9.
Is contractor aware of following Environmental and Personal Controls standards? YES NO
a. Potable water provided.
b. Restroom facilities provided.
c. W ashing facility provided for employees engaged in operations involving harmful substances.
d. Intoxicating beverages, controlled substances, and/or firearms are not permitted under any circumstances on the construction site.
e. All activities in or around water bodies must be in compliance with regulations for worker safety, including personal flotation devices or buoyant work vests, lifelines, ring buoys and guardrails while working over or adjacent to water hazards, and from barges, boats, and/or launches.
FWS Form 3-2199 09/01 Page 2 of 5
10.
a. Confined Space.
b. Scaffolding.
c. Fall Protection.
d. Hazard Comm unication.
e. Lockout/Tagout.
f. Respiratory Protection.
g. First Aid.
Is contractor/subcontactor aware that following employee training considerations may need to be addressed?
YES NO
11. Contractor/subcontractor is responsible for requiring the wearing of appropriate personal protective equipment in all operations where there is an exposure to hazardous conditions or where the need is indicated for using such equipment to reduce the hazard to their employee(s). The contractor/subcontractor is also responsible for ensuring equipment may include the following: Discussed with contractor?
that personnel using protective equipment shall be trained and medically qualified to do so. Such personal protective
a. Eye and face protection (safety goggles, safety glasses, welding goggles, face shields, etc.).
b. Protective footwear (safety shoes, boots).
c. Protective gloves (leather, rubber, insulated).
d. Respirators (dust, half-face, full-face, etc.).
e. Hearing protection (ear plugs, muffs, etc.).
f. Coast Guard-approved PFD/buoyant vest.
g. Fall protection equipm ent.
12. Tools (hand, electric, pneumatic) Standards: Discussed with contractor?
a. Hand tools, power tools, and jacks are maintained in safe operating condition and used only for the purpose for which they were designed.
b. Electric power-operated tools must be either approved double-insulated, or be properly grounded (see Item
#13 “Electrical” for additional considerations).
13. Electrical Standards:
a. Ground Fault Circuit Interrupters (GFCIs) or an assured equipment-grounding conductor program must be used to protect employees from ground-fault hazards.
b. Electrical cords/insulation must be in good condition (not frayed or damaged).
c. All ground plugs must be on electrical cords, if so designed by the manufacturer.
d. W orkspace, walkways, and similar locations shall be kept clear of electrical cords.
e.
f.
All electrical extension cords must be of the three-wire type.
Contractor/subcontractor must determine need and implem ent an appropriate Lock-out/Tag-out program.
14. W ill motor vehicles, cranes, and/or heavy equipment be used? YES NO __ (If no, skip to #15)
a. Crane and derrick use must comply with applicable standards.
b. Rollover protection as required.
c. Back-up alarms or observer signals as required.
d. No crawler type vehicles are allowed on an improved road.
e. All utilities must be located prior to excavating soil.
15. Excavating and Trenching work? YES ___ NO ___ (If no, skip to #16)
a. All excavating/trenching must be in accordance with applicable safety standards.
b. All utilities must be located prior to excavating.
FWS Form 3-2199 09/01 Page 3 of 5
16. Elevated W ork? YES ___ NO ___ (If no, skip to #17) a.
Ladders and their use must conform to standards.
b. Aerial lift usage must meet applicable requirements.
c. Fall protection needs must be assessed per standards.
d. Scaffold work must conform to standards.
e. Stair design, construction, and use must meet applicable requirements.
f. Toeboards, when used to protect workers from falling objects, must be erected along the edge of the overhead walking/working surface.
g. Safety net use must comply with standards.
h. Railing must conform to standards.
17.
construction.
Contractor is aware of and understands the need to incorporate app licable requirem ents for concrete and m asonry
YES ___ NO ___ N/A ___
18. Contractor is aware of and understands the need to incorporate welding and cutting operations that com ply with etc.).
applicable safe ty requirem ents (e.g., compressed gas cylinders are protected from vehicle traffic, valve caps secured, 19.
paint
Contrac tor is aw are o f and understands the need to m anage hazard ous m aterials/waste appro priately (e.g., YES N/A
N/A ___ s, solvents, fuels, etc.) including the following: NO ___
a. Use and storage of flammable/combustible liquids.
b. Aboveground fuel storage tanks properly managed/contained.
c. Com pressed gases and cylinders managed correctly (e.g., secured and protected from damage, etc.).
d. Procedures for managing use, storage, and disposal of hazardous materials properly established.
e. Excess/waste product(s) and containers properly disposed of per environmental regulations.
f. Hazards of product use and the need for protective measures (e .g., personal protective equipment, etc.)
conveyed to employees.
g. Asbestos work conform s to applicable standards.
h. Exposure to toxic gases, vapors, fum es, dusts , and m ists managed correctly.
i. Lead, laser, and any other hazardous components managed per the applicable standard.
j. Contract employees must conduct hazardous waste operations work within the parameters of a written safety
& health plan.
20. Comments, notes, additional requirements:
The contractor has the ultimate responsibility for safety on the project site at all times until final completion and acceptance of the project.
The contractor’s signature below indicates the above information was discussed and understood.
Contractor signature: _________________________________________ Date: __________________________
Date: __________________________
Contracting Officer/Contracting Officer’s Representative
FWS Form 3-2199 09/01 Page 4 of 5
OSHA CONSTRUCTION SAFETY STANDARDS - 29 CFR 1926:
(Following standards can be accessed at http://www.osha.gov):
Subpart A (1926.1 - 1926.5) - General
Subpart B (1926.10 - 1926.16) - General Interpretations
Subpart C (1926.20 - 1926.35) - General Safety and Health Provisions
Subpart D (1926.50 - 1926.66) - Occupational Health and Environm ental Controls
Subpart E (1926.95 - 1926.107) - Personal Protective and Life Saving Equipment
Subpart F (1926.150 - 1926.155) - Fire Protection and Prevention
Subpart G (1926.200 - 1926.203) - Signs, Signals and Barricades
Subpart H (1926.250 - 1926.252) - Materials Handling, Storage, Use and Disposal
Subpart I (1926.300 - 1926.307) - Tools - Hand and Power
Subpart J (1926.350 - 1926.354) - W elding and Cutting
Subpart K (1926.400 - 1926.449) - Electrical
Subpart L (1926.450 - 1926.454) - Scaffolds
Subpart M (1926.500 - 1926.503) - Fall Protection
Subpart N (1926.550 - 1926.555) - Cranes, Derricks, Hoists, Elevators and Conveyors
Subpart O (1926. 600 - 1926.606) - Motor Vehicles, Mechanized Equipment and Marine Operations
Subpart P (1926.650 - 1926.652) - Excavations
Subpart Q ( 1926.700 - 1926.706) - Concrete and Masonry Construction
Subpart R (1926.750 - 1926.752) - Steel Erection
Subpart S (1926.800 - 1926.804) - Underground Construction, Caissons, Cofferdam s and Compressed Air
Subpart T (1926.850 - 1926.860) - Demolition
Subpart U (1926.900 - 1926.914) - Blasting and the Use of Explosives
Subpart V (1926.950 - 1926.960) - Power Transmission and Distribution
Subpart W (1926.1000-1926.1003)- Rollover Protective Structures; Overhead Protection
Subpart X (1926.1050 -1926.1060)- Stairways and Ladders
Subpart Y (1926.1071 -1926.1092)- Diving
Subpart Z (1926.1100 -1926.1152)- Toxic and Hazardous Substances
FWS Form 3-2199 09/01 Page 5 of 5
DIVISION 1 SECTION 01310
GENERAL REQUIREMENTS PROJECT COORDINATION
01310-1
1.1 Jobsite Administration - Superintendence, Subcontract
administration and Quality Control, including all Quality Control testing as specified herein, is the responsibility of the Contractor.
A. Final decisions relative to items in conflict shall be made by the Contracting Officer.
B. At the request of the Government or the Government’s Inspector, the Contractor shall provide all requested material samples for testing purposes. The Government may test earthwork and concrete placed for this project to independently verify the Contractors testing results. This will not relieve the Contractor of any or all Testing Requirements noted in the project documentation.
C. The Contractor shall notify the Contracting Officer’s
Representative (COR) and the Government’s Inspector ten (10) business days prior to anticipated date of completion of demolitions, any concrete placement, fill placement or earthwork requiring material/field density testing.
D. If a Quality Control/Quality Assurance test that the
Government Inspector/Tester performs reflects that the material tested does not met the requirements as defined in the project documents, the Contractor shall pay for all expenses that are required for the Government to retest the material until it is in accordance with the project documents.
E. All costs incurred by the Contractor in order to comply with these requirements shall be considered incidental to the Contract Cost.
F. The Government shall have the authority to temporarily suspend the Work for such time as necessary because of the failure on the part of the Contractor to perform any of the provisions of the Contract. No extension of
01310-2 contract performance time will be permitted until the Government determines that the deficiencies in performance, which caused the temporary suspension, have been corrected.
G. The Government may suspend the work by written order for such period or periods as are necessary because of extended unsuitable weather and/or for such other conditions as may be unfavorable for the prosecution of work. Upon suspension, the work shall be put in satisfactory condition and properly protected, as directed by the Government. In all cases of suspension of construction operations, the work shall not be resumed until permitted by written order of the Government.
H. The Contractor shall have responsible superintendence on site during all project operations. Contractor shall notify Government of any changes of superintendents.
I. Contractor is responsible for all surveying required by Contract Documents, Drawings, and construction.
J. The Contractor shall notify the COR at least ten (10) working days prior to the anticipated date of completion of all Work specified herein. Upon completion of the Work, the COR shall proceed with the final inspection which shall be completed as promptly as practicable. The time required for such inspection and for performing any corrective Work shall be included in the contract performance time.
K. Contractor is required to adhere to the Directorate
Memorandum, Implementing and Enforcing Mask‐Wearing Requirements for Visitors (attached) and coordinated with the Refuge for any later updates.
L. The Government is in the process of obtaining the
State Dam Safety Permit, NEPA Documentation, and SHPO Clearances. These permits/clearances are anticipated to be completed/received before January 2022. Onsite
01310-3 field work can not start until the Refuge Manager obtains these permits/clearances and the Government provides written notice of such to the Contractor.
1.2 Modification/Change Order procedures
A. In the event of the need for a Change Order, the Contractor will receive a letter requesting a price quote for proposed changes to the Contract.
B. For evaluation purposes, the Contractor's quote shall be broken down to show the quantities and costs of labor and materials for each proposed category of Work included with the change, along with the total cost for Contractor's overhead, profit, and bond for the proposed changes.
C. All Contract time extensions required as a result of a proposed change must be justified and supported in detail at the time of the proposal.
1.3 Traffic Control
A. The WCS/Bridge shall be closed to public access or passage for the duration of construction for the bridge.
B. The roads to/from the WCS/Bridge should be accessible to Refuge personnel and equipment for maintenance purposes. Passage through the WCS/Bridge could depend on stage of construction and shall be in safe manner.
C. The Contractor shall coordinate with the Refuge/County
Staff on impacts to traffic during construction.
D. The Contractor shall coordinate with the Government for necessary road closures during construction.
E. The Contractor shall coordinate with the Refuge for wildlife nesting season and locations in order to minimize disturbance to wildlife.
01310-4
F. The Contractor shall provide all required safety measures for road closures and directions for detours.
1.4 Preconstruction Conference
A. Soon after award of the Contract and prior to commencing construction, the Contractor and any subcontractors shall attend a preconstruction conference with representatives of the Government.
Timely notification of the meeting will be given to the Contractor. Time, date, and place of the conference will be determined by the Contracting Officer. Requirements pertaining to Contract administration, construction operations and the project schedule will be discussed. The project schedule shall be in accordance with Section 01330.
B. The Preconstruction Safety Checklist shall be submitted for review during this conference.
1.5 Progress Meetings
A. Periodic general project meetings will be conducted with a representative of the Contractor at the project site or by telephone by the Government's representative for the purpose of coordinating, expediting, and assessing the work progress.
B. The Contractor shall provide reports of progress on the project, discuss the work schedule for the coming period and present all conflicts, discrepancies or other difficulties for resolution. A record of discussions and decisions will be prepared by the Government and distributed to those attending and others affected.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (not Applicable)
(END OF SECTION 01310)
FISH AND WILDLIFE SERVICE
Washington D.C. 20240
In Reply Refer To:
FWS/DIR/074249
Memorandum
To:
From:
Subject:
U.S. Fish and Wildlife Service Directorate
Martha Williams, Senior Advisor to the Secretary, Exercising the Delegated Authority of the Director, U.S. Fish and Wildlife Service
Implementing and Enforcing Mask-Wearing Requirements for Visitors
Purpose This memorandum provides guidance for implementation and enforcement of mask-wearing requirements for visitors to federal facilities and federal lands administered by the Service, as directed by Executive Order 13991, Protecting the Federal Workforce and Requiring Mask- Wearing.
General Guidance for Non-Law-Enforcement Staff and Volunteers Non-law-enforcement staff and volunteers who interact with visitors to federal facilities and federal lands administered by the Service can promote compliance with the mask mandate as follows:
1. If a visitor forgets to wear a mask, gently remind them of the requirement to wear one. If the station has the means to offer disposable masks, offer one.
2. If the conversation escalates or turns hostile, stay calm, walk away to a safe place, and contact your supervisor. The supervisor should seek to deescalate the situation through calm discourse to the best of their ability.
3. If attempts at peaceful resolution are ineffective, the supervisor has the discretion to implement safety measures to protect our employees, volunteers, partners, contractors, and visitors. These measures may include, but are not limited to:
• request the non-compliant visitor to leave the facility or area,
• contact the geographically assigned Federal Wildlife Officer, building security, Federal Protective Service, or local law enforcement for assistance,
• and/or temporarily close the affected facility or area.
Maintaining the safety of others present should be everyone’s paramount concern.
https://www.whitehouse.gov/briefing-room/presidential-actions/2021/01/20/executive-order-protecting-the-federal-workforce-and-requiring-mask-wearing/ https://www.whitehouse.gov/briefing-room/presidential-actions/2021/01/20/executive-order-protecting-the-federal-workforce-and-requiring-mask-wearing/
Guidance on National Wildlife Refuge System Managed Lands The following guidance provides Project Leaders, Refuge Managers, and Federal Wildlife Officers with information on how to implement and enforce mask-wearing requirements for refuge visitors.
Authorities The authority for Project Leaders and Refuge Managers to implement this mandated condition of entry and use of National Wildlife Refuge System managed lands is from the statutory authority found in the National Wildlife Refuge System Administration Act of 1966 (16 U.S.C. 668dd- 668ee), the Refuge Recreation Act of 1962 (16 U.S.C. 460k-460k-4), and the regulatory authorities granted in 50 Code of Federal Regulations, Subchapter C, including 50 CFR 25.21(e) and 50 CFR 25.31.
Refuge-Specific Required Actions To protect the health and safety of our employees, volunteers, partners, contractors, and visitors to National Wildlife Refuges, Project Leaders and Refuge Managers are directed to implement mask-wearing requirements for all public users and visitors to National Wildlife Refuge System managed lands by using the authority in 50 CFR 25.21(e) and giving public notice in accordance with the provisions in 50 CFR 25.31.
Language Project Leaders and Refuge Managers must use the following language in their refuge’s notification:
While entering or remaining upon a National Wildlife Refuge, all visitors over the age of 2 years* must wear masks, except when actively eating or drinking, in the following locations:
1. All common areas and shared workspaces in buildings owned, rented, or leased by the U.S. Fish and Wildlife Service, including, but not limited to, visitor centers, administrative offices, and gift shops.
2. The following outdoor areas, when others are present where the Project Leader and/or Refuge Manager has determined that physical distancing (staying at least 6 feet apart) cannot reasonably be maintained:
• Outdoor areas adjacent to visitor centers or administrative office entry areas.
• Parking lots or pull-off viewing areas when outside of an enclosed motor vehicle.
• Trailheads, trails, rest areas, fishing piers, boat ramps, and close proximity hunting areas.
Masks must cover the nose and mouth and fit snugly around the nose and chin with no large gaps around the sides of the face. Masks with ventilation valves and face shields do not meet the mask requirement.
https://www.ecfr.gov/cgi-bin/retrieveECFR?gp=&SID=aed6f90feea89103efc2fef76be28ea2&mc=true&n=pt50.9.25&r=PART&ty=HTML#se50.9.25_121 https://www.ecfr.gov/cgi-bin/text-idx?SID=aed6f90feea89103efc2fef76be28ea2&mc=true&node=se50.9.25_131&rgn=div8
*Masks should not be worn by:
• Children younger than 2 years old
• Anyone who has trouble breathing
• Anyone who is unconscious, incapacitated, or otherwise unable to remove the mask without assistance
Public Notification 50 CFR 25.31 provides that the public may be notified by:
• Official signs posted conspicuously at appropriate intervals and locations. Approved signage can be found on the Service’s Intranet.
• Other appropriate methods that will give the public actual or constructive notice of the permitted or curtailed public access, use, or recreational activities. Refuge websites will automatically post the notification.
Permitted Events and Activities The Project Leader and/or Refuge Manager must include mask-wearing requirements in the terms and conditions of permits for events or activities that will take place inside or in outdoor areas where physical distancing (staying at least 6 feet apart) cannot be reasonably maintained.
These terms and conditions must include the same requirements about the proper fitting and type of masks that are included above in the approved language.
Federal Wildlife Officer Enforcement on System Lands Violations of Refuge management actions through 50 CFR 25.21(e) with notification made through 50 CFR 25.31 are prohibited under 50 CFR 26.22 “General exception for entry,” which requires: “(a) Any person entering or using any national wildlife refuge will comply with the regulations in this subchapter C, the provisions of any special regulations and any other official notification as is appropriate under § 25.31” and are enforceable by Service Federal Wildlife Officers.
We recognize the sensitivity of this mandate and that our Federal Wildlife Officers are well trained, highly professional, and exercise their authority with a great degree of trusted discretion.
The following guidance recognizes that the dynamics of an encounter are highly variable and that no two situations are the same. Federal Wildlife Officer’s safety, the safety of our employees, and the safety of visitors are the Service’s highest priorities.
Our intent is to promote voluntary compliance with mask mandate requirements to the fullest extent possible. Enforcement is intended to be a last resort option. The Service is authorizing Federal Wildlife Officers to implement enforcement under the following directions:
1. Initiate compliance contacts in a non-confrontational manner and start with words similar to: “You may not be aware, but the wearing of masks is required at the National Wildlife Refuge.”
https://doimspp.sharepoint.com/sites/fws-FF09X00000/SitePages/COVID-19-Signs.aspx https://www.ecfr.gov/cgi-bin/text-idx?SID=c725b0e547f854330d37dd3ea06b6d21&mc=true&node=se50.9.26_122&rgn=div8
2. Ensure the recording of contacts and incidents are in compliance with Director’s Order 220, Body-Worn Cameras.