8-KL27-101 Bids - Unofficial.xlsx

XLSX spreadsheet 9 KB Posted

Attached to
Oak Creek Mastication
Solicitation number
KL27-101
Issued by
Utah

About this file

This is an unofficial bid tabulation spreadsheet for an Invitation for Bid (IFB) issued by the State of Utah Division of Purchasing, with the Department of Natural Resources as the conducting procurement unit, for mastication services related to the Oak Creek project. The solicitation is limited to prequalified contractors only and requests mastication services across 292 acres as detailed in the Scope of Work (Attachment B). The project must be completed no later than April 15, 2027, with no mandatory site visit required. The IFB anticipates a single contract award to the lowest cost responsive and responsible vendor.

Seven contractors submitted bids for the mastication services, with total costs ranging from $129,799.84 to $189,800.00. Hall's HammerTime Construction LLC submitted the lowest bid at $129,799.84 ($444.52 per acre), followed by Summitt Forests, Inc. at $134,904.00 ($462.00 per acre) and GE Forestry, Inc. at $139,868.00 ($479.00 per acre). The remaining bids were submitted by Maynes Equipment Repair ($140,744.00), England Construction ($189,800.00), Kolob Mountain Construction LLC ($160,016.00), and Mountain Peak Land Management ($164,688.00). The vendor must guarantee its pricing through project completion.

View the file

Other files

File Type Posted
PJ Bullhog.cpg —
Oak Bullhog.sbx —
7-Attachment B - Scope of Work.docx DOCX document
PJ Bullhog.dbf DBF file
PJ Bullhog.shx —
Oak Bullhog.sbn —
Oak Bullhog.shp —
Oak Bullhog.shx —
PJ Bullhog.shp —
10-Award Memo (1).pdf PDF
2-Vendor Prerequisites - IFB Agency.pdf PDF
PJ Bullhog.sbx —
Oak Bullhog.shp.xml XML file
PJ Bullhog.shp.xml XML file
Oak Bullhog.prj —
Oak Bullhog.cpg —
4-Oak Creek Location.pdf PDF
3-Att.-A-PO-Terms-and-Conditions (5).docx DOCX document
1-Contract Performance Evaluation FOR REFERENCE USE ONLY.pdf PDF
Oak Bullhog.dbf DBF file
PJ Bullhog.prj —
PJ Bullhog.sbn —
6-Oak Creek Treatments.pdf PDF
9-KL27-101 Bids - Official.xlsx XLSX spreadsheet
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet 1

England ConstructionGE Forestry, INc.Hall's HammerTime Construction LLCKolob Mountain Construction LLCMOUNTAIN PEAK LAND MANAGEMENTMaynes equipment repairRazr Bak RestorationSummitt Forests, Inc
Total Cost$189,800.00$139,868.00$129,799.84$160,016.00$140,744.00$164,688.00$134,904.00$875,416.00
#ItemsQuantity
RequiredUnit

of

MeasurementUnit
PriceTotal
CostUnit
PriceTotal
CostUnit
PriceTotal
CostUnit
PriceTotal
CostUnit
PriceTotal
CostUnit
PriceTotal
CostUnit
PriceTotal
CostUnit
PriceTotal

Cost

Basket 1: Totals$189,800.00$139,868.00$129,799.84$160,016.00$140,744.00$164,688.00$134,904.00$875,416.00
#1-1Mastication Services292Acre$650.00$189,800.00$479.00$139,868.00$444.52$129,799.84$548.00$160,016.00$482.00$140,744.00$564.00$164,688.00$462.00$134,904.00$2,998.00$875,416.00