AMENDMENT 0001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ABSTRACT.pdf | ||
| Revised_APPENDIX_B.pdf | ||
| A005.pdf | ||
| A004.pdf | ||
| J&A_Sole_Source_Brand_Name.pdf | ||
| M2254-E03_SHEET_9.pdf | ||
| A003.pdf | ||
| A002.pdf | ||
| IFB_Construction.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGES
1 2
2. AMENDMENT/MODIFICATION NO.
04/17/2019 4. REQUISITION/PURCHASE REQ. NO.
21-19-829PACP0400
5. PROJECT NO. (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
CONTRACTING OFFICER
USCG, CIVIL ENGINEERING UNIT MIAMI
15608 SW 117TH AVENUE
MIAMI, FL 33177-1630
CONTRACTING OFFICER
USCG, CIVIL ENGINEERING UNIT MIAMI
15608 SW 117TH AVENUE
MIAMI, FL 33177-1630
8. NAME AND ADDRESS OF CONTRACTOR (NO., STREET, COUNTY, STATE AND ZIP CODE)
PROSPECTIVE CONTRACTORS
9A. AMENDMENT OF SOLICITATION NO.
70Z08219BPACP0400
9B. DATED (SEE ITEM 11)
04/05/2019
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE REFERENCED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET
FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (SPECIFY TYPE OF MODIFICATION AND AUTHORITY)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (ORGANIZED BY UCF SECTION HEADINGS, INCLUDING SOLICITATION/CONTRACT SUBJECT MATTER WHERE FEASIBLE.)
SOLICITATION NUMBER: 70Z08219BPACP0400 – WATERFRONT REPAIRS AT U.S. COAST GUARD SECTOR KEY WEST, FL
IS AMENDED AS FOLLOWS:
A. THIS AMENDMENT PROVIDES ANSWERS FROM CONTRACTOR’S REQUEST FOR INFORMATION ON ATTACHED
PAGES.
B. BID OPENING DATE OF MAY 7, 2019 AT 2:00 P.M. LOCAL TIME MIAMI, FL REMAINS UNCHANGED.
C. PLEASE RETURN A SIGNED COPY OF THIS AMENDMENT WITH YOUR BID.
15A. NAME AND TITLE OF SIGNER (Type or Print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
ADA HOGGARD, CONTRACT SPECIALIST, USCG
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED
16B UNITED STATES OF AMERICA
BY
(Signature of Contracting Officer)
16C. DATE SIGNED
NSN 7540-01-152-8070 STANDARD FORM 30 (Rev. 10-83) PREVIOUS EDITION UNUSABLE Prescribed by GSA
FAR (48 CFR) 53.243
70Z08219BPACP0400
AMENDMENT 0001
QUESTION: Sheet S-02 Construction note 4 states "All hardware shall be stainless steel, except nails which shall be galvanized steel. Sheet S-03 Section D-D Calls out 5/8" Dia. x 7" LG Galv. Bolt, Nut & Washers. Can we install Galv. bolts?
ANSWER: No. All hardware shall be stainless steel as per note 4, sheet S-02 and specification 05 50 00 “Miscellaneous Metals”.
QUESTION: S-04 Concrete Spall Repair Type SP1 note #4 "For spalls with exposed prestressing tendons, remove any loose concrete around tendons." Are there post tension concrete decks on this project?
ANSWER: No. There are no presstressing tendons on this project. That is a generic note that includes steel reinforcement and presstressing tendons.
QUESTION: Are the areas of work to be done simultaneously or consecutively (phased)?
ANSWER: Areas of work may be simultaneously but in close coordination with unit small boat operations.
END OF QUESTIONS/ANSWERS