A0005 Attachment 1 - Q and A Spreadsheet.xlsx

XLSX spreadsheet 121 KB Posted

Attached to
USCGC KIMBALL DRYDOCK FY23 Federal contract opportunity
Solicitation number
70Z08023QLREKIMB
Issued by
Department of Homeland Security US Coast Guard

About this file

This document includes a spreadsheet attachment with questions and answers related to a solicitation for drydocking and repairs to USCGC KIMBALL. The solicitation requires various hull preservation and inspection work items, equipment overhauls and repairs, and vessel modifications and tests. Responses are needed by early November for an anticipated award in early 2023. The Coast Guard requests consideration of alternative surface preparation methods and clarification on areas requiring treatment. Quantities for waste disposal and temporary power requirements are also addressed.

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Work Items

CountWIWORK ITEM DESCRIPTIONESTSUB NOTESACTION ITEMSISSUESSCHEDULE NOTESGOV'T QUESTIONSGOV'T ANSWERS
11Hull 3D, Laser ScanGJSea Engineering

Kilohana Construction

See Tech Rep ListKC - Derek - General overviewPlease provide a copy of the 3D model referenced in paragraph 3.2.1: …"Non-Uniform Rational Basis Spline (NURBS) surface developed and provided by U.S. Coast Guard SFLC…"
22Hull Plates (Freeboard), InspectGJNDTKC - Derek - General overview
33Hull Plates (U/W Body), InspectGJNACE III

NDT

44Freeboard, Preserve (Full)GJNACE III
PRESSurface prep: SP-10/Abrasive water blasting1. Paragragh 3.1.7 notes that "The Contractor may have the option of using either “Wet Abrasive Blasting” or “Dry Abrasive Blasting” to achieve the required surface preparation…" The note in this paragraph states that "Water jetting without abrasive addition does not provide any additional anchor profile to the surface, beyond what was present after the previous surface preparation.". Contractor requests that the USCG consider revising the work specification to allow for Water jetting without abrasive addition. With new construction, abrasive blast media is needed to achieve the required anchor profile, but with repair the anchor profile already exists, and Water jetting without abrasive addition is generally an acceptible surface prepartion method; the Navy and other government agencies allow for this surface prepartion method. Water jetting without abrasive addition will provide the government with a better value.

2. For estimating purposes, please provide surface areas for the regions shown in Table 1 as well as the "adjacent structural members" referenced in paragraph 3.4 & 4.1.

55Superstructure, Preserve (Partial)GJNACE III
PRESSurface prep: SP-10/Abrasive water blasting1. Paragragh 3.1.7 notes that "The Contractor may have the option of using either “Wet Abrasive Blasting” or “Dry Abrasive Blasting” to achieve the required surface preparation…" The note in this paragraph states that "Water jetting without abrasive addition does not provide any additional anchor profile to the surface, beyond what was present after the previous surface preparation.". Contractor requests that the USCG consider revising the work specification to allow for Water jetting without abrasive addition. With new construction, abrasive blast media is needed to achieve the required anchor profile, but with repair the anchor profile already exists, and Water jetting without abrasive addition is generally an acceptible surface prepartion method; the Navy and other government agencies allow for this surface prepartion method. Water jetting without abrasive addition will provide the government with a better value.

2. For estimating purposes, please provide surface areas for each location listed in Table 1, Table 2, and Table 3 as well as all the structures noted in paragraph 4.1 and 4.2.

66U/W Body Hull, Preserve (Full)GJNACE III
PRESSurface prep: SP-10/Abrasive water blasting1. Paragragh 3.1.7 notes that "The Contractor may have the option of using either “Wet Abrasive Blasting” or “Dry Abrasive Blasting” to achieve the required surface preparation…" The note in this paragraph states that "Water jetting without abrasive addition does not provide any additional anchor profile to the surface, beyond what was present after the previous surface preparation.". Contractor requests that the USCG consider revising the work specification to allow for Water jetting without abrasive addition. With new construction, abrasive blast media is needed to achieve the required anchor profile, but with repair the anchor profile already exists, and Water jetting without abrasive addition is generally an acceptible surface prepartion method; the Navy and other government agencies allow for this surface prepartion method. Water jetting without abrasive addition will provide the government with a better value.

2. For estimating purposes, please provide surface areas for each location listed in Table 1 and paragraph 4.1.1.

77Tenting, ProvideGJSCAFPotential question about where to include the cost of tenting all work items
1010Tenting (Mast), Provide (Option)GJSCAF
1111Propulsion Shaft Fairwaters And Rope Guards, InspectTASCAFSurface prep: SP-10/Abrasive water blastingQuestion: Surface Prep

12 12 Chain Lockers and Sump, Preserve GJ NACE III

PRES

13 13 Chain Lockers and Sump, Clean and Inspect GJ NACE III

NDT

D&D

1414Voids (Non-Accessible), PreserveGJD&D
1515Voids (Non-Accessible), Leak TestGJD&D
1616Sideport Shell Door, Level 2, InspectKCTK

ELEC

BERNELL

1717Mast, PreserveGJNACE III
NDTKC - Bob - General overview recommend sub support
1818Propulsion Shaft Alignment & Bearings (External) Clearances, CheckTADIEHL
SPSIs it the requirement of the contractor or the Coast Guard to …. Liquid loading… align. Note on PG 163
1919Propulsion Shaft Coverings (MIL-STD-2199B), Inspect and RepairTANDT
SPSKC - Derek - General overviewPara 3.1.6 references a work item to remove shafts "Propulsion Shafts, Remove, Inspect, and Install." Does the Coast Guard intend to invoke a work spec that will require the shafts to be removed
2020Propulsion Shaft Seals (Mechanical), OverhaulTASHAFT
2121Controllable Pitch Propeller Hub Assembly, General MaintenanceTACPP

D&D 22 22 Controllable Pitch Propeller System, Perform General Maintenance TA CPP D&D

2323Doppler Speed Log Valve, OverhaulKCSPERRYKC - Ask Noe about sub sperry options
2424Doppler Speed Log, General MaintenanceKCSPERRY
2525Fathometer Transducer (Deep Water), General MaintenanceTASHAFT
2626Shallow Water Transducer, RenewTASHAFT
2727Sea Valves and Waster Pieces, Overhaul Or RenewKCTK
2828Seawater Strainers (All Sizes), Overhaul and InspectKCTK
2929Rudder Stock Bearings, Check ClearancesTASHAFT
3030Rudder Stock Seals, OverhaulTASHAFT
3131Bow Thruster Unit (General), OverhaulTACPP

D&D

LUBE OIL SAMPLE

BLADE POLISHING

NDT

32 32 Anchors Chains and Ground Tackles, Inspect and Preserve GJ PRES

NDT

33 33 Stern Ramp, Preserve 100% KC NACE III

NDT

34 34 Transom Doors, Inspect And Repair KC TRANSOM DOOR

HPU

SCAF

PRES

MACHINE SHOP

D&D

3535Impressed Current Cathodic Protection System Dielectric Shield (Capastic Fairing), RenewTAICCP
3636Impressed Current Cathodic Protection System, Inspect and MaintainTAICCP
3737Cathodic Protection (Zincs), RenewTATK
3838Impressed Current Cathodic Protection System Anodes, RenewTATK

ICCP

39 39 Impressed Current Cathodic Protection System Reference Cells, Renew TA TK

ICCP

4040Ship Service Diesel Generator (No. 3) Exhaust Piping, ModifyKCTK
4141Transom Double Doors and Tow Outfits, ModifyKCTK

TRANSOM DOOR

HPU

NACE III

NDT

D&D 42 42 Stern Door Hydraulic and Control System, Modify KC TRANSOM DOOR

SPECIALTY FLUSH

SCAF

D&D

LAG

43 43 Stern Ramp Rails, Modify KC TK

NACE III

NDT

D&D

LAG

PRES

44 44 Cascade Orificial Resistive Device, Clean And Inspect KC TK D&D 45 45 Deck Covering (Slip-Resistant) Mast, Preserve GJ DECK

PRES

SCAF

NDT

ELEC

4646Drydocking, AccomplishMYDIVEENG - Prep drydocking calculations
4747Vessel in Drydock Temporary Services, ProvideGJD&D

WASA

48 48 Sea Trial Performance, Support, Provide KC

Questions

WIWORK ITEM DESCRIPTIONQUESTIONSRESPONSE
6U/W Body Hull, Preserve (Full)Contractor solicited multiple paint manufacturers for all of the paint required for all work items in this work package. The best lead time received was 8-10 weeks. Would the government consider making all paint GFM so that it can be ordered immediately?No, the government will not consider making paint GFE.
17Propulsion Shaft Coverings (MIL-STD-2199B), Inspect and RepairNote that since the shafts are not being removed from the vessel, it may not be possible to inspect the entire length of the FRP Shaft Coverings due to a portion of the length being contained in the stern tube. Please confirm that it is acceptable to inspect only the portion of the shaft covering that is accesible without removing the shafts.If the shafts are *not* removed from the ship then inspection and repair is only on the accesible area of the shafts. *If* shafts are removed then inspection and repair is on all areas of the tail shaft. If removed the difference in area can be documented via CFR/CR.
18Propulsion Shaft Seals (Mechanical), OverhaulPlease provide the contents of the GFM Major Overul Kit NSN: 2840-01-576-0008 PN: WLP001354-001.
25Sea Valves and Waster Pieces, Overhaul Or Renew3.11 Can the hydrostatic test be accomplished in shop?The contractor only needs to conduct hydrostatic testing on welds. Disconnecting or connecting a flanged fitting or a union fitting does not require a hydrostatic test. If the contractor is authorized by the COR to repair a valve with clad welding, then that would require hydrostatic testing - either on the ship or in the shop. If the valve is welded into the piping system, then that weld would need to be tested on board the ship. If the contractor is welding a flange or union onto a valve, then that weld could be hydrostatically tested on the ship or in the shop.
44Vessel in Drydock Temporary Services, Provide1. Para 3.19 refers to SFLC 8635 for Bilge Water/Waste Oil. No Bilge Water/Waste Oil quantities are provided. Please confirm that all disposal will be covered as a change order based on removed and disposed quantities per para 3.3.8.2 in SFLC 8635.

2. The lead time for the required "400 A MIL-C-24368 receptacle(s) with standard Navy plug(s)" and associated cable may not support the timeline for this project. The lead time is currently ~8-10 weeks, and if an award is made in early November, Contractor will not have time to procure and receive these components. Is is possible for the government to provide these as GFM?

3. Table 1 lists 16,000 kWh per day while SFLC 8635 lists 12,000 kWh per day for this class of vessel in Table 3. Please clarify the correct kWh per day. 1. For bidding purpose,Bilge Water/Waste oil, use 500 Gallons. Additional requirements will be covered by a CFR/CR through the COR.

2. Cutter currently outfitted with 03 "pitail" adapters. Email form cutter "They are just capped with electrical tape; essentially they do not have the connection ends of the three (03) leads. Which makes sense; as the shore-side connection varies." Also: For shore tie cable supplier : sales@eslpwr.com 800-922-4188

3. Expected energy use shall be in accoradnce with Table 1 as 16000 KWH/DAY GENERAL QUESTION ABOUT SOLICITATION SCHEDULE REQUIREMENTS 1. Under Technical: Sub Para : Submit Planning Doc (PD) is Bullet Weld Cert Bullet Fire Safety Plan Bullet Temp Duty Section is the expectation that this info is provided as part of the schedule? These are ususally part of the Tech Narrative. Please submit information under technical narrative.