A0004 Page 2.pdf
PDF 209 KB Posted
- Attached to
- DOCKSIDE (DS): USCGC ALERT DS Federal contract opportunity
- Solicitation number
- 70Z080-22-Q-MEC-ALERTDS
About this file
This document contains questions and answers regarding a dockside availability for the USCGC ALERT from February 4th to March 31st, 2023. The availability requires potable water access, which can be obtained from the pier's source with the proper adapters and sanitized hoses. While an extra power outlet is available, the contractor will not be able to utilize the pier's shore power and will need to rely on pier-side generators, which are extremely costly to operate due to fuel and environmental requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A0005 Page 1.pdf | ||
| A0005 Page 2.pdf | ||
| Amendment 0004 Page 1.pdf | ||
| A0003.pdf | ||
| Specification_REV1.pdf | ||
| UPDATED Schedule of Services.xls | XLS spreadsheet | |
| Amendment 002_CGC ALERT_.pdf | ||
| QUESTIONS_RESPONSES_2.pdf | ||
| A0001 Questions_Answers.pdf | ||
| Amendment 0001_CGC ALERT_.pdf | ||
| ALERT_Schedule_of_Services.xls | XLS spreadsheet | |
| ALERT_Statement_of_work.pdf | ||
| Solicitation USCGC_ALERT_ 9.29.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
“This DS requires a fair amount of water to clean tanks, flush pipes, flush chill water, Potable Water to support Shower and Toilet Trailers, if the contractor can not access the Potable Water on the Pier
Q: Where do we access Potable Water?
A: Counter to what was provided in a previous answer the KTR can access the pier’s P/W source given they have the right adapters and sanitize their hoses prior to connection.
Q: There is 1 open or extra Viking/NATO outlet on the Shore Tie Power Vault, if the contractor has the correct equipment to hook up to that shore tie, would that be allowed?
A: The previous answer stands regarding the use of the pier’s shore power. The KTR will not be able to use the pier’s shore tie. Pier-side generators have been used during previous availabilities.
Warning running Diesel Generators for an entire dockside is extremely costly to maintain Fueling. In addition to the secondary containments and daily diesel fuel deliveries adds significant environmental risk, noise and air pollution. This location has heavy public domain being exposed to an Industrial Environment.”