Amendment 2 Page 2 of 2.pdf

PDF 45 KB Posted

Attached to
Drydock (DD): USCGC THETIS (WMEC-910)
Solicitation number
70Z080-21-Q-P4583900
Issued by

About this file

This document contains answers to questions regarding federal contract number 70Z080-21-Q-P4583900 for drydocking the CGC THETIS. The contract requires 100 hours of heavy lift equipment, 6000 gallons per day of potable water at 60 pounds per square inch gauge, and does not specify cooling water requirements. If lead paint is discovered during repairs, the contractor must submit a condition found report for review rather than automatically receiving additional compensation through a change request. The period of performance is July 28, 2021 through October 6, 2021. The contracting agency is the Department of Homeland Security's United States Coast Guard.

View the file

Other files

File Type Posted
Amendment 4.pdf PDF
Amendment 3 Page 2 of 2.pdf PDF
Amendment 3 Page 1 of 2.pdf PDF
Amendment 2 Page 1 of 2.pdf PDF
Amendment 1 Page 2 of 2.pdf PDF
Amendment 1 Page 1 of 2.pdf PDF
Attachment 2_Statement of Work_Specification.pdf PDF
Attachment 1_Schedule of Services_Blank Price Schedule.xls XLS spreadsheet
70Z080-21-Q-P4583900.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

70Z080-21-Q-P4583900

Question:

Work Items 044, 026, and 045 If lead paint is found to be present in the areas to be repaired will a Change Request be approved to compensate the contractor for removal of lead paint?

Answer :

All lead paint was removed during the midlife. If any lead is found, a Condition Found Report will be submitted by the contractor.

Question:

Work Item 024, Temporary services item requires Heavy lift equipment but does not identify the number of days/hours of service.

Temporary services item requires potable water but does not identify the gallons per day/psig, or gallons (bulk).

Temporary services item requires Cooling water but does not identify the gallons per day or psig requirement.

How many hours of heavy lift service are required?

How many gallons per day of potaable water are required and at what psig?

How many gallons per day of cooling water are required and at what psig?

Answer :

100 hours of heavy lift service is required

6000 gallons of potable water at 60 psig