7-Change Order Form.pdf.pdf

PDF 201 KB Posted

Attached to
Southshore Sportsplex - Phase 2
Solicitation number
IFB-26-00279
Issued by
Hillsborough County, Florida

About this file

This is a Change Order Form template utilized by Hillsborough County, Florida for managing modifications to construction contracts. The form provides a standardized structure for authorizing changes and modifications to existing contracts, including adjustments to contract sums, project timelines, and scope of work. The document accommodates various types of changes, including time extensions, extra work, credits, and other modifications. The form requires detailed documentation of cost impacts, reasons for changes, and final completion date adjustments, with fields for identifying the original contract sum, cumulative effects of previous change orders, and the resulting new contract sum. All changes must be approved through multiple organizational layers, including the County Attorney for legal sufficiency, the Department Fiscal Director, and the Board of County Commissioners, with appropriate documentation of BOCC approval dates and staff signatures required for validity.

The form mandates contractor acknowledgment and waiver of claims for additional time or compensation beyond those specified in the change order itself. Surety consent is required when change orders affect contract amounts or completion dates, necessitating updates to performance and payment bonds. The document requires notarization for contractor acknowledgments, with separate acknowledgment procedures for corporations, partnerships, and individuals. All signatures must be executed by duly authorized representatives, and the contractor waives rights to additional claims or compensation resulting from the authorized changes. This standardized form applies to the Southshore Sportsplex Phase 2 project, a construction initiative valued at $12,650,011.00 for base bid items plus $2,769,574.00 for alternate bid items, with an established 8% Small Business Enterprise subcontractor participation goal.

View the file

Other files

File Type Posted
1-Drug Free Workplace Form.doc.doc DOC document
11-SBE Subcontractors Material Suppliers List SBE-1 Form.pdf PDF
22-IFB-26-00279 Special Conditions.pdf PDF
14-Subcontractor Letter of Intent .pdf PDF
9-Substitute W9 Form.pdf.pdf PDF
6-Consent of Surety to Final Payment.pdf.pdf PDF
18-Agreement - Construction - Stand Alone.pdf PDF
24-IFB-26-00279 Insurance Requirements.pdf PDF
13-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
8-Insurance Certificate.doc.doc DOC document
20-Payment Bond.pdf PDF
5-Subcontractors Statement of Satisfaction.pdf.pdf PDF
10-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
16-IFB-26-00279 Location Map.pdf PDF
25-IFB-26-00279 Contract Terms and Conditions.pdf PDF
4-Application for Payment.pdf.pdf PDF
17-IFB-26-00279 Technical Specifications.pdf PDF
19-Bid Bond.doc DOC document
12-Contractors Affidavit for Payment of Debts and Claims 02.18.2026.pdf PDF
2-Florida Trench Safety Act, Certification and Disclosure Statement.pdf.pdf PDF
15-IFB-26-00279 Drawings.pdf PDF
21-Performance Bond.pdf PDF
3-Allowance Authorization Release Form.pdf.pdf PDF
23-SBE Goal Participation SBE-1 Form Tutorial (SBE Division v3).mp4 MP4 file
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revised 01.29.2025

HILLSBOROUGH COUNTY

CHANGE ORDER FORM

CONTRACT: CHANGE ORDER NO.:

BID NO:

CONTRACTOR: PROJECT NO:

CPA NO:

TIME CHANGE EXTRA WORK CREDIT OTHER

The Contractor is hereby authorized and directed to make the following changes and modifications to the aforesaid Contract in accordance with all requirements applicable thereto.

DESCRIPTION OF CHANGE:

COST

IMPACT

FINAL

COMPLETION

DAYS

REASON FOR CHANGE:

The original Contract Sum (TOTAL GMP) was . . . . . . . . . . . . $____________ Net change by previous Change Orders . . . . . . . . . . . . . . . . $____________ The Contract Sum prior to this Change Order was . . . . . . . . . . . . . $____________ The Contract Sum will be by this Change Order. . . . . . $ ____________ (increased, decreased or unchanged) The new Contract Sum including this Change Order will be . . . . . . . . . . $ ____________

The Final Completion Milestone prior to this Change Order was .

The time for Final Completion Milestone will be ______________ by __________( )days.

(extended, reduced or unchanged) The Final Milestone for this change order therefore is therefore

The Contractor waives any and all claims to additional time extension and/or additional monetary compensation resulting from these changes and all cost associated with the change order as herein addressed.

Excepting those terms and provisions conflicting with this Change Order which are hereby changed to conform hereto, the aforesaid Contract as amended by all previous change orders hereto is otherwise reaffirmed in its entirety.

IN WITNESS WHEREOF, this Change Order No. _______ to __________________________________ has been executed by the parties hereto or their duly authorized representatives.

ATTEST: VICTOR D. CRIST COUNTY: HILLSBOROUGH COUNTY FLORIDA

Clerk of Circuit Court

BY: BY:

Deputy Clerk Chair, Board of County Commissioners

BOCC Document Number Date of BOCC approval

ATTEST: CONTRACTOR:

BY:

Witness Authorized Signature (SEAL)

TITLE:

DATE:

BOCC Staff Approval Date

Department Fiscal Department Director Procurement County Attorney:

Approved as to Form and Legal Sufficiency

(ACKNOWLEDGMENT OF CONTRACTOR, IF A CORPORATION)

STATE OF )

COUNTY OF )

The foregoing instrument was acknowledged before me by means of physical presence or online notarization this day of , 20 , by ______________________ (Name of person) as____________________________ for ___________________________________________________.

(ie. Officer, attorney in fact) (Name of party on behalf of whom instrument was executed.)

(Signature of Notary Public)

(Print, Type, or Stamp Name of Notary Public)

Personally Known OR Produced Identification

Type of Identification Produced ______________________

(ACKNOWLEDGMENT OF CONTRACTOR, IF A PARTNERSHIP OR INDIVIDUAL)

STATE OF )

COUNTY OF )

The foregoing instrument was acknowledged before me by means of physical presence or online notarization this day of , 20 , by .

(Name of person acknowledging)

(Signature of Notary Public)

(Print, Type, or Stamp Name of Notary Public)

Personally Known OR Produced Identification

Type of Identification Produced ______________________

CONSENT OF SURETY TO CHANGE ORDER

CONTRACT TITLE:

CONTRACTOR (PRINCIPAL):

SURETY:

AGENT:

The SURETY does hereby acknowledge and agree to Change Order No. to the above referenced contract with Hillsborough County, the contract amount (increasing/decreasing) by $ , and/or extending the completion date by ( ) calendar days. The SURETY further acknowledges that the performance bond and/or payment bond furnished under the aforementioned contract is accordingly changed to reflect the change in contract amount, and/or time included in Change Order No. .

This Consent is dated this day of , 20 .

SURETY:

BY: (SEAL)

Authorized Signature

-OR-

BY: (SEAL)

As Attorney in Fact (Attach Power of Attorney)

Printed Name

STATE OF FLORIDA

COUNTY OF HILLSBOROUGH

The foregoing instrument was acknowledged before me by means of physical presence or online notarization this ___ day of ____________, 20___, __________________________ by (Name of person) ________________________ for _________________________________________________.

(ie. Officer, attorney in fact) (Name of party on behalf of whom instrument was executed.)

(Signature of Notary Public) (Print, Type, or Stamp Name of Notary Public)

Personally Know OR Produced Identification

Type of Identification Produced __________________

File details come from the government source that posted it. Updated .