Bid Tabulation NV FLAP US50 Round Hill Pines Access.pdf

PDF 658 KB Posted

Attached to
NV FLAP US50(1) Round Hill Pines Access
Solicitation number
6982AF22B000005
Issued by

About this file

This tabulation of bids report summarizes bids received for the NV FLAP US50(1) Round Hill Pines Access federal contract opportunity. The project involves widening 0.34 miles of US 50 and constructing 0.13 miles of new access road to the Round Hill Pines Beach Resort near Lake Tahoe, Nevada to improve safety and accessibility. Two bids were received by the March 24th deadline, with Herback General Engineering, LLC providing the lowest bid of $5,228,520 and Hooker Creek, Inc. bidding $7,761,117. The engineer's estimate for the project was $4,425,000. Key work items include road widening, drainage improvements, signing, stripping, and construction of new roadway segments involving large fills. Award of the contract is pending.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 03/28/22

1 out of 13

Project No: NV FLAP US50(1)

Project Name: Round Hill Pines Access

Schedule: A

Schedule Type: Base

Solcitation No: 6982AF22B000005

Division: Central Federal Lands

State: NV County: Douglas

Federal Land: Lake Tahoe Basin National Forest Opened at: Lakewood, CO

Opened by: Leslie Karsten

Date: 03/24/22

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Herback General Engineering, LLC $5,228,520.00 2531 Nowlin Road Minden, NV 89423

Hooker Creek, Inc. $7,761,117.00 1015 Anderson St.

Red Bluff, CA 96080

Engineer's Estimate $4,425,000.00

Contract Specialist

03/28/2022

2 out of 13

Project No: NV FLAP US50(1)

Project Name: Round Hill Pines Access

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0020 15101-0000 MOBILIZATION

Herback General Engineering, LLC Lump Sum $328,220.00 Hooker Creek, Inc. Lump Sum $840,000.00 Engineer's Estimate ALL LPSM Lump Sum $522,195.00

A0040 15215-3000 SURVEY AND STAKING, DRAINAGE STRUCTURE

Herback General Engineering, LLC $1,220.00 $3,660.00 Hooker Creek, Inc. $1,000.00 $3,000.00 Engineer's Estimate 3 EACH $1,300.00 $3,900.00

A0060 15225-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING CONTROL

Herback General Engineering, LLC $16,000.00 $7,776.00 Hooker Creek, Inc. $80,000.00 $38,880.00 Engineer's Estimate 0.486 MILE $15,000.00 $7,290.00

A0080 15236-2000 SURVEY CONTROL, GRADE FINISHING

Herback General Engineering, LLC $4,000.00 $3,884.00 Hooker Creek, Inc. $26,000.00 $25,246.00 Engineer's Estimate 0.971 MILE $20,000.00 $19,420.00

A0100 15301-0000 CONTRACTOR QUALITY CONTROL

Herback General Engineering, LLC Lump Sum $122,000.00 Hooker Creek, Inc. Lump Sum $180,000.00 Engineer's Estimate ALL LPSM Lump Sum $116,800.00

A0120 15401-0000 CONTRACTOR TESTING

Herback General Engineering, LLC Lump Sum $65,400.00 Hooker Creek, Inc. Lump Sum $175,000.00 Engineer's Estimate ALL LPSM Lump Sum $116,800.00

A0140 15501-0000 CONSTRUCTION SCHEDULE

Herback General Engineering, LLC Lump Sum $14,000.00 Hooker Creek, Inc. Lump Sum $15,000.00 Engineer's Estimate ALL LPSM Lump Sum $19,460.00

3 out of 13

Project No: NV FLAP US50(1)

Project Name: Round Hill Pines Access

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0160 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

Herback General Engineering, LLC $10.00 $68,000.00 Hooker Creek, Inc. $5.00 $34,000.00 Engineer's Estimate 6,800 LNFT $9.00 $61,200.00

A0180 15706-1000 SOIL EROSION CONTROL, INLET PROTECTION

Herback General Engineering, LLC $375.00 $1,500.00 Hooker Creek, Inc. $200.00 $800.00 Engineer's Estimate 4 EACH $320.00 $1,280.00

A0200 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT

Herback General Engineering, LLC $1,890.00 $3,780.00 Hooker Creek, Inc. $4,200.00 $8,400.00 Engineer's Estimate 2 EACH $7,000.00 $14,000.00

A0220 15802-0000 WATERING FOR DUST CONTROL

Herback General Engineering, LLC Lump Sum $75,000.00 Hooker Creek, Inc. Lump Sum $62,000.00 Engineer's Estimate ALL LPSM Lump Sum $50,000.00

A0240 20101-0000 CLEARING AND GRUBBING (Includes stump removal)

Herback General Engineering, LLC $16,592.00 $99,552.00 Hooker Creek, Inc. $13,500.00 $81,000.00 Engineer's Estimate 6.0 ACRE $12,500.00 $75,000.00

A0260 20120-1000 REMOVAL, INDIVIDUAL TREE

Herback General Engineering, LLC $1,685.00 $5,055.00 Hooker Creek, Inc. $1,000.00 $3,000.00 Engineer's Estimate 3 EACH $800.00 $2,400.00

A0280 20301-0700 REMOVAL OF DELINEATOR

Herback General Engineering, LLC $46.00 $2,990.00 Hooker Creek, Inc. $27.00 $1,755.00 Engineer's Estimate 65 EACH $30.00 $1,950.00

4 out of 13

Project No: NV FLAP US50(1)

Project Name: Round Hill Pines Access

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0300 20301-1400 REMOVAL OF INLET

Herback General Engineering, LLC $1,000.00 $2,000.00 Hooker Creek, Inc. $1,400.00 $2,800.00 Engineer's Estimate 2 EACH $1,600.00 $3,200.00

A0320 20301-2000 REMOVAL OF PIPE END SECTION

Herback General Engineering, LLC $135.00 $405.00 Hooker Creek, Inc. $190.00 $570.00 Engineer's Estimate 3 EACH $300.00 $900.00

A0340 20301-2400 REMOVAL OF SIGN

Herback General Engineering, LLC $46.00 $230.00 Hooker Creek, Inc. $145.00 $725.00 Engineer's Estimate 5 EACH $150.00 $750.00

A0360 20302-1200 REMOVAL OF GUARDRAIL

Herback General Engineering, LLC $20.00 $30,000.00 Hooker Creek, Inc. $7.00 $10,500.00 Engineer's Estimate 1,500 LNFT $6.00 $9,000.00

A0380 20302-2100 REMOVAL OF PIPE CULVERT

Herback General Engineering, LLC $26.00 $1,170.00 Hooker Creek, Inc. $125.00 $5,625.00 Engineer's Estimate 45 LNFT $250.00 $11,250.00

A0400 20304-1000 REMOVAL OF STRUCTURES AND OBSTRUCTIONS

Herback General Engineering, LLC Lump Sum $18,800.00 Hooker Creek, Inc. Lump Sum $35,000.00 Engineer's Estimate ALL LPSM Lump Sum $75,000.00

A0420 20310-1000 PLUG, EXISTING PIPE

Herback General Engineering, LLC $1,450.00 $1,450.00 Hooker Creek, Inc. $850.00 $850.00 Engineer's Estimate 1 EACH $5,000.00 $5,000.00

5 out of 13

Project No: NV FLAP US50(1)

Project Name: Round Hill Pines Access

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0440 20402-0000 SUBEXCAVATION

Herback General Engineering, LLC $156.00 $78,000.00 Hooker Creek, Inc. $177.00 $88,500.00 Engineer's Estimate 500 CUYD $150.00 $75,000.00

A0460 20420-0000 EMBANKMENT CONSTRUCTION

Herback General Engineering, LLC $46.40 $2,338,560.00 Hooker Creek, Inc. $72.00 $3,628,800.00 Engineer's Estimate 50,400 CUYD $30.00 $1,512,000.00

A0480 20703-2000 GEOGRID, STABILIZATION

Herback General Engineering, LLC $3.85 $13,475.00 Hooker Creek, Inc. $5.50 $19,250.00 Engineer's Estimate 3,500 SQYD $12.00 $42,000.00

A0500 21101-1000 ROADWAY OBLITERATION, METHOD 1

Herback General Engineering, LLC $2.20 $3,608.00 Hooker Creek, Inc. $5.00 $8,200.00 Engineer's Estimate 1,640 SQYD $6.00 $9,840.00

A0520 25101-0100 PLACED RIPRAP, METHOD A, CLASS 1 (2 ft. thick. Use behind curb returns at US50/Access Rd. per USFS detail.)

Herback General Engineering, LLC $161.00 $9,177.00 Hooker Creek, Inc. $120.00 $6,840.00 Engineer's Estimate 57 CUYD $405.00 $23,085.00

A0540 25101-2200 PLACED RIPRAP, METHOD B, CLASS 2

Herback General Engineering, LLC $294.00 $5,586.00 Hooker Creek, Inc. $210.00 $3,990.00 Engineer's Estimate 19 CUYD $360.00 $6,840.00

A0560 30202-2000 ROADWAY AGGREGATE, METHOD 2

Herback General Engineering, LLC $48.80 $87,840.00 Hooker Creek, Inc. $112.00 $201,600.00 Engineer's Estimate 1,800 TON $55.00 $99,000.00

6 out of 13

Project No: NV FLAP US50(1)

Project Name: Round Hill Pines Access

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0580 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1

Herback General Engineering, LLC $165.00 $453,750.00 Hooker Creek, Inc. $280.00 $770,000.00 Engineer's Estimate 2,750 TON $140.00 $385,000.00

A0600 40601-0000 FOG SEAL

Herback General Engineering, LLC $1,385.00 $11,080.00 Hooker Creek, Inc. $1,700.00 $13,600.00 Engineer's Estimate 8 TON $650.00 $5,200.00

A0620 41102-0000 PRIME COAT

Herback General Engineering, LLC $18.70 $86,020.00 Hooker Creek, Inc. $3.25 $14,950.00 Engineer's Estimate 4,600 SQYD $1.25 $5,750.00

A0640 41105-0000 BLOTTER

Herback General Engineering, LLC $183.00 $4,575.00 Hooker Creek, Inc. $100.00 $2,500.00 Engineer's Estimate 25 TON $110.00 $2,750.00

A0660 41201-0000 TACK COAT

Herback General Engineering, LLC $1,935.00 $17,415.00 Hooker Creek, Inc. $1,800.00 $16,200.00 Engineer's Estimate 9 TON $1,500.00 $13,500.00

A0680 41301-0600 ASPHALT PAVEMENT MILLING, 2-INCH DEPTH

Herback General Engineering, LLC $4.56 $54,720.00 Hooker Creek, Inc. $9.50 $114,000.00 Engineer's Estimate 12,000 SQYD $4.00 $48,000.00

A0700 60201-0500 15-INCH PIPE CULVERT

Herback General Engineering, LLC $334.00 $6,012.00 Hooker Creek, Inc. $235.00 $4,230.00 Engineer's Estimate 18 LNFT $400.00 $7,200.00

7 out of 13

Project No: NV FLAP US50(1)

Project Name: Round Hill Pines Access

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0720 60201-0600 18-INCH PIPE CULVERT

Herback General Engineering, LLC $244.00 $64,904.00 Hooker Creek, Inc. $260.00 $69,160.00 Engineer's Estimate 266 LNFT $150.00 $39,900.00

A0740 60210-0500 END SECTION FOR 15-INCH PIPE CULVERT

Herback General Engineering, LLC $1,011.00 $1,011.00 Hooker Creek, Inc. $400.00 $400.00 Engineer's Estimate 1 EACH $500.00 $500.00

A0760 60210-0600 END SECTION FOR 18-INCH PIPE CULVERT

Herback General Engineering, LLC $1,062.00 $2,124.00 Hooker Creek, Inc. $1,000.00 $2,000.00 Engineer's Estimate 2 EACH $800.00 $1,600.00

A0780 60212-0600 ELBOW, 18-INCH

Herback General Engineering, LLC $425.00 $850.00 Hooker Creek, Inc. $1,650.00 $3,300.00 Engineer's Estimate 2 EACH $500.00 $1,000.00

A0800 60213-0600 BRANCH CONNECTION, 18-INCH

Herback General Engineering, LLC $930.00 $1,860.00 Hooker Creek, Inc. $1,200.00 $2,400.00 Engineer's Estimate 2 EACH $1,500.00 $3,000.00

A0820 60401-0000 MANHOLE

Herback General Engineering, LLC $11,225.00 $11,225.00 Hooker Creek, Inc. $1,200.00 $1,200.00 Engineer's Estimate 1 EACH $6,200.00 $6,200.00

A0840 60403-0000 INLET

Herback General Engineering, LLC $10,665.00 $21,330.00 Hooker Creek, Inc. $17,000.00 $34,000.00 Engineer's Estimate 2 EACH $6,000.00 $12,000.00

8 out of 13

Project No: NV FLAP US50(1)

Project Name: Round Hill Pines Access

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0860 60704-0000 CLEANING CULVERT IN PLACE

Herback General Engineering, LLC $1,500.00 $1,500.00 Hooker Creek, Inc. $800.00 $800.00 Engineer's Estimate 1 EACH $2,400.00 $2,400.00

A0880 60902-1000 CURB AND GUTTER, CONCRETE, 12-INCH DEPTH (NDOT Type 1)

Herback General Engineering, LLC $36.00 $54,720.00 Hooker Creek, Inc. $61.00 $92,720.00 Engineer's Estimate 1,520 LNFT $65.00 $98,800.00

A0900 61401-0000 LEAN CONCRETE BACKFILL

Herback General Engineering, LLC $565.00 $186,450.00 Hooker Creek, Inc. $450.00 $148,500.00 Engineer's Estimate 330 CUYD $500.00 $165,000.00

A0920 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS (Stained)

Herback General Engineering, LLC $58.50 $59,260.50 Hooker Creek, Inc. $98.00 $99,274.00 Engineer's Estimate 1,013 LNFT $100.00 $101,300.00

A0940 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT (Stained)

Herback General Engineering, LLC $8,165.00 $32,660.00 Hooker Creek, Inc. $7,700.00 $30,800.00 Engineer's Estimate 4 EACH $4,700.00 $18,800.00

A0960 61902-0900 GATE, METAL (USFS Gate, 32 FEET WIDTH)

Herback General Engineering, LLC $15,050.00 $15,050.00 Hooker Creek, Inc. $26,000.00 $26,000.00 Engineer's Estimate 1 EACH $15,000.00 $15,000.00

A0980 62102-0000 MARKER (Settlement Plates)

Herback General Engineering, LLC $5,575.00 $11,150.00 Hooker Creek, Inc. $8,900.00 $17,800.00 Engineer's Estimate 2 EACH $2,000.00 $4,000.00

9 out of 13

Project No: NV FLAP US50(1)

Project Name: Round Hill Pines Access

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1000 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY

Herback General Engineering, LLC $150.00 $6,000.00 Hooker Creek, Inc. $185.00 $7,400.00 Engineer's Estimate 40 HOUR $110.00 $4,400.00

A1020 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH

Herback General Engineering, LLC $150.00 $3,000.00 Hooker Creek, Inc. $150.00 $3,000.00 Engineer's Estimate 20 HOUR $120.00 $2,400.00

A1040 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE

Herback General Engineering, LLC $250.00 $5,000.00 Hooker Creek, Inc. $205.00 $4,100.00 Engineer's Estimate 20 HOUR $170.00 $3,400.00

A1060 62201-3000 HYDRAULIC EXCAVATOR

Herback General Engineering, LLC $250.00 $5,000.00 Hooker Creek, Inc. $195.00 $3,900.00 Engineer's Estimate 20 HOUR $160.00 $3,200.00

A1080 62301-0000 GENERAL LABOR

Herback General Engineering, LLC $60.00 $2,400.00 Hooker Creek, Inc. $80.00 $3,200.00 Engineer's Estimate 40 HOUR $50.00 $2,000.00

A1100 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES

Herback General Engineering, LLC $250.00 $5,000.00 Hooker Creek, Inc. $225.00 $4,500.00 Engineer's Estimate 20 HOUR $125.00 $2,500.00

A1120 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES

Herback General Engineering, LLC $250.00 $10,000.00 Hooker Creek, Inc. $250.00 $10,000.00 Engineer's Estimate 40 HOUR $150.00 $6,000.00

10 out of 13

Project No: NV FLAP US50(1)

Project Name: Round Hill Pines Access

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1140 62406-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH

Herback General Engineering, LLC $8,300.00 $24,900.00 Hooker Creek, Inc. $4,300.00 $12,900.00 Engineer's Estimate 3.0 ACRE $5,500.00 $16,500.00

A1160 62510-2000 SEEDING, HYDRAULIC METHOD

Herback General Engineering, LLC $3,048.00 $9,144.00 Hooker Creek, Inc. $3,150.00 $9,450.00 Engineer's Estimate 3.0 ACRE $1,400.00 $4,200.00

A1180 62515-2000 MULCHING, HYDRAULIC METHOD

Herback General Engineering, LLC $5,080.00 $15,240.00 Hooker Creek, Inc. $5,050.00 $15,150.00 Engineer's Estimate 3.0 ACRE $2,000.00 $6,000.00

A1200 62901-0000 ROLLED EROSION CONTROL PRODUCT

Herback General Engineering, LLC $8.35 $46,760.00 Hooker Creek, Inc. $8.50 $47,600.00 Engineer's Estimate 5,600 SQYD $11.00 $61,600.00

A1220 63301-0000 SIGN SYSTEM

Herback General Engineering, LLC $992.00 $12,896.00 Hooker Creek, Inc. $2,250.00 $29,250.00 Engineer's Estimate 13 EACH $600.00 $7,800.00

A1240 63309-0000 DELINEATOR

Herback General Engineering, LLC $175.00 $7,175.00 Hooker Creek, Inc. $110.00 $4,510.00 Engineer's Estimate 41 EACH $80.00 $3,280.00

A1260 63316-1000 REMOVE AND RESET SIGN

Herback General Engineering, LLC $585.00 $2,340.00 Hooker Creek, Inc. $1,750.00 $7,000.00 Engineer's Estimate 4 EACH $500.00 $2,000.00

11 out of 13

Project No: NV FLAP US50(1)

Project Name: Round Hill Pines Access

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1280 63402-0300 PAVEMENT MARKINGS, TYPE B, SOLID

Herback General Engineering, LLC $2,625.00 $11,812.50 Hooker Creek, Inc. $960.00 $4,320.00 Engineer's Estimate 4.50 MILE $1,100.00 $4,950.00

A1300 63402-0400 PAVEMENT MARKINGS, TYPE B, BROKEN

Herback General Engineering, LLC $2,040.00 $2,448.00 Hooker Creek, Inc. $395.00 $474.00 Engineer's Estimate 1.20 MILE $700.00 $840.00

A1320 63405-0500 PAVEMENT MARKINGS, TYPE B, TURN ARROW

Herback General Engineering, LLC $205.00 $1,640.00 Hooker Creek, Inc. $71.00 $568.00 Engineer's Estimate 8 EACH $200.00 $1,600.00

A1340 63405-0550 PAVEMENT MARKINGS, TYPE B, STRAIGHT ARROW

Herback General Engineering, LLC $2,045.00 $8,180.00 Hooker Creek, Inc. $175.00 $700.00 Engineer's Estimate 4 EACH $130.00 $520.00

A1360 63501-1000 TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR

Herback General Engineering, LLC Lump Sum $112,000.00 Hooker Creek, Inc. Lump Sum $180,000.00 Engineer's Estimate ALL LPSM Lump Sum $37,500.00

A1380 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

Herback General Engineering, LLC $350.00 $2,800.00 Hooker Creek, Inc. $360.00 $2,880.00 Engineer's Estimate 8 EACH $300.00 $2,400.00

A1400 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE

Herback General Engineering, LLC $36.00 $5,400.00 Hooker Creek, Inc. $18.00 $2,700.00 Engineer's Estimate 150 EACH $35.00 $5,250.00

12 out of 13

Project No: NV FLAP US50(1)

Project Name: Round Hill Pines Access

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1420 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM

Herback General Engineering, LLC $95.00 $11,400.00 Hooker Creek, Inc. $120.00 $14,400.00 Engineer's Estimate 120 EACH $75.00 $9,000.00

A1440 63502-2100 TEMPORARY TRAFFIC CONTROL, CRASH CUSHION

Herback General Engineering, LLC $11,800.00 $11,800.00 Hooker Creek, Inc. $10,000.00 $10,000.00 Engineer's Estimate 1 EACH $2,800.00 $2,800.00

A1460 63502-3900 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

Herback General Engineering, LLC $350.00 $14,000.00 Hooker Creek, Inc. $850.00 $34,000.00 Engineer's Estimate 40 EACH $275.00 $11,000.00

A1480 63503-0400 TEMPORARY TRAFFIC CONTROL, CONCRETE BARRIER

Herback General Engineering, LLC $68.00 $122,400.00 Hooker Creek, Inc. $45.00 $81,000.00 Engineer's Estimate 1,800 LNFT $50.00 $90,000.00

A1500 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE (For tree protection)

Herback General Engineering, LLC $10.00 $5,000.00 Hooker Creek, Inc. $6.70 $3,350.00 Engineer's Estimate 500 LNFT $10.00 $5,000.00

A1520 63505-1000 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS

Herback General Engineering, LLC $4,500.00 $13,500.00 Hooker Creek, Inc. $2,700.00 $8,100.00 Engineer's Estimate 3.0 MILE $3,300.00 $9,900.00

A1540 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER

Herback General Engineering, LLC $75.00 $262,500.00 Hooker Creek, Inc. $89.00 $311,500.00 Engineer's Estimate 3,500 HOUR $85.00 $297,500.00

13 out of 13

Project No: NV FLAP US50(1)

Project Name: Round Hill Pines Access

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Total Schedule - All Items

Herback General Engineering, LLC $5,228,520.00 Hooker Creek, Inc. $7,761,117.00 Engineer's Estimate $4,425,000.00