A001.pdf

PDF 484 KB Posted

Attached to
CO FLAP DEN 56(1) Access Connections to ROAR Federal contract opportunity
Solicitation number
6982AF19B000013
Issued by
Department of Transportation Federal Highway Administration

About this file

Amendment A001

View the file

Other files for this federal contract opportunity

Other files attached to CO FLAP DEN 56(1) Access Connections to ROAR, newest first.
File Type Posted
Bid Tabulation CO FLAP DEN56(1) Access Connections to ROAR.pdf PDF
Bid_Opening_Summary_-__CO_FLAP_DEN_56(1)_Access_Connections_to_ROAR.pdf PDF
QnA_10.28.19.pdf PDF
Amendment_A002.pdf PDF
QnA_10.16.19.pdf PDF
Access_Connections_to_ROAR_Final_Hydraulics_Report.pdf PDF
CO_FLAP_DEN56(1)_100__2019-9-10.pdf PDF
RMA_Geotech_Report_20190627.pdf PDF
6982AF19B000013.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

1 4

A001 10/21/2019 HFLCEO190267PR CO FLAP DEN56(1)

FEDERAL HIGHWAY ADMINISTRATION

CENTRAL FEDERAL LANDS HIGHWAY DIVISION

12300 WEST DAKOTA AVENUE, SUITE 360

LAKEWOOD, COLORADO 80228

ATTENTION: CONTRACT SPECIALIST NAME

6905001

6982AF19B000013

09/23/2019

0*

*See Item 14

INVITATION FOR BID

Remove and replace pages A-iii, A-1, and E-15 with the attached corresponding pages.

*FAILURE TO ACKNOWLEDGE THIS AMENDMENT IN BLOCK 19 OF THE SF 1442 BY THE DESIGNATED DATE AND HOUR SPECIFIED IN THE

SOLICITATION MAY RESULT IN REJECTION OF YOUR BID (REFER TO ITEM 11.)

NOTICE TO BIDDERS

A-iii offers lines of credit to finance accounts receivable. Maximum line of credit is $500,000 with interest at the prime rate. For further information, call (800) 532-1169. Internet address:

http://osdbuweb.dot.gov.

Accuracy and Completeness of Bid- The Contractor is fully responsible to verify that all data is correct when an offer is submitted. Failure to properly update your data may cause the offer to be rejected.

Request for Technical Information – Questions relative to the plans and SCRs for this solicitation will only be accepted in writing (see Item 9 on Page A-3).

TECHNICAL QUESTIONS REGARDING THIS SOLICITATION WILL NOT BE

ACCEPTED AFTER 4 P.M. ON OCTOBER 16, 2019 OCTOBER 30, 2019.

Questions can be submitted to CFLContracts@dot.gov. Questions and answers will be posted at http://www.fbo.gov

Modifications to Bids - Bids may be modified or withdrawn by regular mail, electronic commerce (email) or facsimile, if such notice is received prior to the time specified for receipt of bids. The Government will not be responsible for ANY failure attributable to the transmission or receipt of electronic commerce (email) or facsimile data.

For all modifications, we STRONGLY ENCOURAGE you to resubmit the entire bid schedule with a unit price and amount for every bid item, and a Schedule Total. See FAR Provision 52.214-5, Submission of Bids. Modifications which make the bid ambiguous, indefinite, or uncertain as to any essential requirement of the contract will cause the bid to be rejected as nonresponsive.

FAX Number to submit modifications to bids for this project is (720) 963-3360

Email Address to submit modifications to bids for this project is cflcontracts@dot.gov

II. POST AWARD INFORMATION

CFLHD will no longer be providing paper copies of the conformed contract to the Awarded Prime Contractor.

Subcontracting - FAR Clause 52.219-8, Utilization of Small Business Concerns states that Prime Contractors afford small business concerns, veteran-owned small business concerns, service-disabled veteran-owned small business concerns, HUBZone small business concerns, small disadvantaged business concerns, and women-owned small business concerns the maximum practicable opportunity to participate in performing contracts let by any Federal agency.

Amendment A001 10/21/2019 http://osdbuweb.dot.gov/ mailto:CFLContracts@dot.gov http://www.fbo.gov/ Leslie.Karsten Cross-Out

SOLICITATION, OFFER

AND AWARD

(Construction, Alteration or Repair)

1. SOLICITATION NO.

6982AF19B000013

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

09/23/2019

PAGE OF

PAGES

IMPORTANT - THE "OFFER SECTION ON THE REVERSE MUST BE FULLY COMPLETED BY OFFEROR.

4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

HFLCEO190267PR

6. PROJECT NO.

CO FLAP DEN56(1)

7. ISSUED BY:

FEDERAL HIGHWAY ADMINISTRATION

CENTRAL FEDERAL LANDS DIVISION

12300 WEST DAKOTA AVENUE, SUITE 167

LAKEWOOD, COLORADO 80228

CODE: 69050001 8. ADDRESS OFFER TO:

Leslie Karsten, Contract Specialist Federal Highway Administration Central Federal Lands Division Office 12300 W. Dakota Avenue Lakewood, CO 80228

9. FOR INFORMATION CALL

SEE PAGE A-3

A. NAME:

SEE PAGE A-3

B. TELEPHONE NO. (Include area code)

SEE PAGE A-3

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS:

ROADWAY CONSTRUCTION PROJECT IN STRICT ACCORDANCE WITH:

1. FEDERAL ACQUISITION AND TRANSPORATION ACQUISITION REGULATIONS (FAR & TAR)

2. DEPARTMENT OF LABOR, CONSTRUCTION WAGE RATE REQUIREMENT RATES

3. SPECIAL CONTRACT REQUIREMENTS

4. PLANS

5. BID SCHEDULE

6. STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY

PROJECTS, FP-14, U.S. CUSTOMARY UNITS

See Subsection 104.04 of the FP-14 for governing order of precedence

11. The Contractor shall begin performance within 10 calendar days and complete it within * calendar days after receiving award notice to proceed. The performance period is mandatory negotiable. *Refer to Subsection 108.01 as amended in the Special Contract Requirements.

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.) YES NO

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and 0 copies to perform the work required are due at the place specified in Item 8. by 2:00 p.m. (hour) local time on 10/23/2019 (date) 11/06/2019. If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is is not required.

C. All offers are subject to the (1) work requirements and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-102 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53-236-1(e)

X

X

X

X

X

A-1 Amendment A001 10/21/2019

E-15

CO FLAP DEN56(1)

Access Connections to ROAR

Section 108. — PROSECUTION AND PROGRESS

108.01 Commencement, Prosecution, and Completion of Work. Add the following:

Limit operations as follows: The Contractor shall coordinate construction of entry arches and dual vestibules with the CO prior to construction.

Perform no work except to maintain traffic control devices, erosion control devices, the roadway driving surface, and to control dust during the listed Federal holidays and surrounding days as shown in Table 108-2.

Table 108-2 Federal Holidays and Surrounding Days

Federal Holiday

Time Remarks

Memorial Day 12:00 Noon Friday to 6:00 am Tuesday

Independence Day

12:00 Noon July 3 to 6:00 am July 5

If July 4 falls on a weekend, Friday, or Monday, do not work the weekend.

Labor Day 12:00 Noon Friday to 6:00 am Tuesday

Thanksgiving 12:00 Noon

Wednesday to 6:00 am Monday

Christmas / New Year’s

12:00 Noon December 23 to

6:00 am January 2

If December 23 or January 1 falls on a Monday, do not work the adjacent weekend and do not work on December 23. If January 1 falls on a Friday, do not work the weekend.

Amendment A001 10/21/2019

Schedule at least 2 non-work days out of every 14 calendar days. The selected non-work days do not need to be consecutive, but they must be scheduled. Provide at least 2 weeks notice before changing the scheduled days off.

Exemptions to scheduled days off may be granted by written approval from the CO for specific project operations and/or for periods of limited duration.

Add the following:

A Notice to Proceed must be issued before commencement of any work. The contract completion date is October 6, 2020. August 31, 2020.