AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.

PAGE OF PAGES

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

Items 8 and 15, and returning is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required.)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.

E. IMPORTANT: Contractor is not, is required to sign this document and return

ORDER NO. IN ITEM 10A.

1 5

0002 06/27/2023

FEDERAL AVIATION ADMINISTRATION

AAQ-500 - REGIONAL ACQUISITIONS

1701 COLUMBIA AVENUE

COLLEGE PARK GA 30337

AAQ510ATL-AFN

x

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ 1 x x

697DCK-23-R-00331

1 copies to the issuing office.

05/19/2023

(x)

BIL-funded: Replace HVAC, ATL TDWR, Ellenwood, GA

The purpose of this amendment is to Change the Offers due date, Add a new clause, and

Answer vendor questions.

CHANGES:

Offers due date: 28-JUN-23 changed to 07-JUL-23

ADDITIONS:

Section I: Clause titled "Prohibition on Using ByteDance Covered Applications Including

TikTok (INTERIM-June 2023) " is incorporated as follows:

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Section I - Contract Clause was added as follows:

Clause List was revised as follows.

Clause 3.6.4-26 is incorporated as follows:

3.6.4-26 PROHIBITION ON USING BYTEDANCE COVERED APPLICATIONS INCLUDING

TIKTOK (INTERIM-JUNE 2023)

(a) Definitions. As used in this clause—

“Covered Application” means the social networking service TikTok or any successor application or service developed or provided by ByteDance Limited or an entity owned by ByteDance Limited.

“Information technology,” as defined in 40 U.S.C. 11101(6)—

(1) Means any equipment, or interconnected system or subsystem of equipment, used in the automatic acquisition, storage, analysis, evaluation, manipulation, management, movement, control, display, switching, interchange, transmission, or reception of data or information by the executive agency, if the equipment is used by the executive agency directly or is used by a Contractor under a contract with the executive agency that requires the use—

(i) Of that equipment; or

(ii) Of that equipment to a significant extent in the performance of a service or the furnishing of a product;

(2) Includes computers, ancillary equipment (including imaging peripherals, input, output, and storage devices necessary for security and surveillance), peripheral equipment designed to be controlled by the central processing unit of a computer, software, firmware and similar procedures, services (including support services), and related resources; but

(3) Does not include any equipment acquired by a Federal Contractor incidental to a Federal contract.

(b) Prohibition. Section 102 of Division R of the Consolidated Appropriations Act, 2023 (Pub. L. 117-328), the No TikTok on Government Devices Act, and its implementing guidance under Office of Management and Budget (OMB) Memorandum M-23-13, dated February 27, 2023, “No TikTok on Government Devices” Implementation Guidance, collectively prohibit the presence or use of a covered application on executive agency information technology, including certain equipment used by Federal contractors. The Contractor is prohibited from having or using a covered application on any information technology owned or managed by the Government, or on any information technology used or provided by the Contractor under this contract, including equipment provided by the Contractor’s employees; however, this prohibition does not apply if the Contracting Officer provides written notification to the Contractor that a waiver has been granted in accordance with AMS Guidance T3.6.4.A.19.c.(2).

(c) Subcontracts. The Contractor must insert the substance of this clause, including this paragraph (c), in all subcontracts including subcontracts for the acquisition of commercial products or commercial services.

(End of Clause)

697DCK-23-R-00331 Amendment 0002

QUESTION/ANSWERS

1. What are the work hours at this facility? Is there anticipation of 2nd. or 3rd. work shifts under this contract…? ANSWER: Work hours Mon -Fri 0700 to 1600 (Local) No weekends or holidays.

2. Is any clearance required for each technician and subcontractors for gaining access to the facility?

ANSWER: None required.

3. Is there a controls contractor at this facility who manages the existing controls systems? ANSWER:

No

4. Does the scope of work include the installation of a duct smoke detector and its integration into the existing fire alarm system? ANSWER: No, these are single zone dedicated units.

5. Can the Government provide a submittal or technical cut-sheet of furnished GFM-OAS 2,5 HVAC

Controller? ANSWER: Yes, see attached literature for Ggovernment-furnished HVAC controller.

6. On drawing number ATL-20015144-M002, Note-1 reads: “During the replacement of the HVAC units, the contractor shall furnish and install a temporary HVAC system. The temporary HVAC unit shall have a cooling capacity of 10 Tons (nominal) and shall be powered from the facility as directed by the FAA” Can the Government clarify how the temporary unit will be powered? Is there an existing spare circuit breaker available in the electrical sub-panel? ANSWER: Upon demolition, after feeder cables have been removed from panelboard LP to existing CU-1 disconnect switch, the contractor can use existing branch circuit breaker no. 25,27,29 (208 v/ 3phase/ 90amp) from the panelboard LP to power the temp HVAC. Please note that the temp power cables shall run from panelboard LP to a temp free standing fused disconnect switch that will supply power to the temp

HVAC. A facility shut-down permit will be required.

7. On drawing number ATL=20015144+M002, Note-7 reads: “Contractor to replace one system at a time”. Does this mean the temporary cooling system needs to be turned ‘ON’ only if the Air

Conditioning is completely lost? ANSWER: Correct, the temporary HVAC is a back-up system only.

8. If the lead time on the equipment extends the project into the winter season, do we need to provide temporary heating? ANSWER: Temporary heating is not required.

9. Is a Test and Balance (TAB) required for each Air Conditioning system? ANSWER: Yes, a system start-up condition checklist must be performed.

10. Does the temporary flex supply duct get suspended from the ceiling or can we place it on the floor?

ANSWER: The temporary flex supply duct can be placed on the floor but in a location that does not limit access to FAA equipment, create a tip hazard or block the remaining means of egress. For the contractor’s convenience the flex duct can be suspended from the ceiling

11. Related to Q10. If suspended from the ceiling, can the contractor drill hole in the ceiling to facilitate the suspension of flex ductwork for the temporary cooling system? ANSWER: Drilling holes in the ceiling to support temporary ductwork will be allowed, dust mitigation with HEPA vacuum will be required. Drilling above electronic equipment will not be allowed except if absolutely necessary. If needed, safeguards must be approved by FAA COR and established to ensure that no debris or shavings will fall into the equipment racks. All ceiling holes must be fully restored (spackled and painted) after no longer needed.

12. Is there a requirement to always keep a specific indoor temperature, please confirm? ANSWER:

Yes.

13. For the anticipated electrical work, the facility cannot experience any power interruption(s), correct?

ANSWER: If needed, a planned power outage can be requested.

14. Is this contract sales-tax exempt...? ANSWER: Reference Section B - Supplies or Services/Prices, Clause B01 PRICE/COST.

15. To corroborate, the contract does not have any applicable liquidated damages, correct? ANSWER:

Correct.

16. Regarding the listed and mandatory Period of Performance, 30 c. days; we anticipate the equipment lead time(s) will drive the entire project schedule, can the government advise on how they plan to approach this timeframe? ANSWER: Reference page 3 of the SIR, paragraph titled, “The Notice to

Proceed (NTP)”.

17. Please confirm the Bid Proposal response for this solicitation will be submitted electronically only.

ANSWER: Reference block 13, page 1 of the SIR, B. “An offer guarantee is not required.”

18. Can the Government furnish specifications for the concrete to be used for the service disconnect switch rack concrete pad? ANSWER: (4000 PSI average compressive strength blend of Portland cement, sand and gravel or stone.)

19. Are there any tests required to be performed post-curing for the concrete? ANSWER: No.

20. Section 01, Part 1, A, Point-10 reads “Replace existing AHUs outside air intake damper actuator and controls.” Can the government provide specifications of the damper control system which controls the outside air damper? ANSWER: The outside air damper must be interlocked with the enable command from the thermostat controller. An end switch must be provided with the damper actuator to energize the system after the outside air damper is fully opened.

21. Section 01, Part 1, A, Point-6 reads “AHUs must be interlocked with new supply-side motor driven isolation damper(s)”. Can the Government clarify if there is an additional supply side damper in addition to the outside air damper? If yes, can you provide specifications of the existing damper?

ANSWER: This is an error, there is no need for a supply-side motor driven isolation damper(s).

22. Special Notes No 2 reads “Permit required”. Can the government clarify what types of permits will be required for this contract? ANSWER: Supply-side motor driven isolation dampers are not part of this project.

23. Can the Government provide any special requirements/recommendations for the protection of all electronic equipment from construction debris and water infiltration? ANSWER: The contractor is to protect the electronic equipment from any risks from debris, water infiltration and the dropping of tools overhead. When working over equipment and where a drop hazard existing, all hand tools must have and use a safety wrist strap. The contract must submit a safety plan for the project for approval. The protection of equipment must not block air flow to the equipment.

24. Page E004 notes say 90Amp fuses. M006 states AHU-1,2 is fused at 15Amp and CU-1,2 are fused at

80Amps. Can you clarify if they knew fuses are 80A or 90A? ANSWER: CU-1, 2 are both fused at

80Amps (per manufacturer’s recommendations) (Dwg M006). AHU-1, 2 are both fused at 15Amps

(per manufacturer’s recommendations) (Dwg M006).

25. Where is the SPD currently located now? It says breaker 52. Does it need to be relocated or installed as brand new? It shows no feeder size. ANSWER: This SPD is not part of this project, and it is located inside the facility (equipment room) at the Essential Main Distribution Panel “LP”. This

SPD is different from the SPD that will be installed outside the facility to protect the condensing units CU-1,2 from lightning transient. Does it need to be relocated or installed as brand new? No, it does not need to be relocated. It shows no feeder size. This is an existing feeder, not part of this project.

26. Page E003 shows the TVSS and disconnect NOT clouded and not part of construction. Point #17

(Section 01, Part 1) reads furnish and install new TVSS as shown on drawings. Can the Government clarify? ANSWER: This TVSS is not part of construction. Point #17 (Section 01, Part 1) reads furnish and install new TVSS as shown on drawings. Can the Government clarify? This is a new

TVSS; Here, it is called “SPD” and is located outside of the facility. See DWG. M004.

27. Specifications say the disconnects need to be wall mounted but the diagram on E005 shows a rack system. Does the rack system take precedence? ANSWER: Yes, the rack system takes precedence.

28. Do the Air terminal Wire clamps need to be stainless? ANSWER: No. Clamps can be galvanized, same as the rack post.

29. ACU-1 and ACU-2 can have separate services, so you have redundancies. The drawing Is showing the TVSS on one circuit supplying the TVSS, ACU-1 and ACU-2? ANSWER: ACU-1 and ACU-2 do not operate simultaneously. Yes, they have separate services. The drawing Is showing the TVSS on one circuit supplying the TVSS, ACU-1 and ACU-2? The TVSS (Rayvoss SPD) is on a separate feeder, being fed from a 100Amp circuit breaker and a 100 Amp disconnect switch; ACU-1 and

ACU-2 are fed from separate feeders.

30. E003 says the wire size for the outdoor units is to be 4AWG. The code says it should be #3 AWG or bigger? Can the Government please clarify. ANSWER: Per NPFA 70, Table 310.16 , the correct wire size for 80Amp is #4AWG.

31. E003 says AHU-1-2 service wires to be #12 AWG. Code requires it to be #10 AWG or bigger. Can the Government please clarify? ANSWER: Per NPFA 70, Table 310.16, the correct wire size for

15Amp is #12AWG

32. E001 # 28 states conduit entrances are not to be top entered. The one-line diagram on E005 shows the top entrance to the disconnects. Can the Government please clarify? ANSWER: Top entrance to disconnect switches is permitted.

33. Can we replace rigid conduit for the outdoor units versus PVC coated rigid? ANSWER: Buried conduits shall be PVC coated rigid.

ATTACHMENT:

1. OAS 2.5 HVAC Controller User’s Manual, dated 2/19/2018, 26 pages.

END OF AMENDMENT 0002