About this file

This solicitation is for the modernization of air traffic control tower consoles at Long Beach Airport in California. The scope of work includes design, demolition, fabrication and installation of new slat wall consoles; replacement of carpeting, millwork and sinks; relocation of outlets and equipment; and provision of temporary power. Drawings must be provided in DWG format. The contractor will work with FAA personnel to develop an installation plan to minimize impacts to operations. The solicitation number is 697DCK-22-R-00432 and was issued by the Department of Transportation Federal Aviation Administration Southwestern Region. The complete scope of work is detailed in Attachment 01 of Section J.

View the file

Other files for this federal contract opportunity

Other files attached to Console modernization at Long Beach Airport, CA, newest first.
File Type Posted
Update_LGB Console Modernization SOW and Specifications.pdf PDF
697DCK-22-R-00432 Amendment 01.pdf PDF
Hazmat Plan.pdf PDF
RFI Questions 7-18-22.xlsx XLSX spreadsheet
IM Pei Standard Tower.pdf PDF
697DCK-22-R-00432.pdf PDF
LGB Sketch Up Model.pdf PDF
Past Performance Questionnaire.pdf PDF
Davis Bacon Wage Determination.pdf PDF
ATCT Equipment List.pdf PDF
Existing Electrical Drawings.pdf PDF
LGB Transition Plan and Drawings.pdf PDF
LGB Console Modernization SOW and Specifications.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DESIGN FILE:

DATE: TIME: USER:

A

B

C

D

E

$$DATE $$TIME $$USER

$$DGN

DEPARTMENT OF TRANSPORTATION

FEDERAL AVIATION ADMINISTRATION

SUBMITTED BY

DRAWN BY

DESIGNED BY

CHECKED BY

APPROVED BY

DATE

DRAWING NO.

DESCRIPTIONREV.

REVIEWED BY

2 3 4 5 6

A

B

D

E

1 2 3 4 5 6

REV.

JCN:

JCN

DATE

REDLINE

APVD

DATE

APPROVED

FOR OFFICIAL USE ONLY

PUBLIC AVAILABILITY TO BE DETERMINED UNDER 5 USC 552

R

LGB ATCT AND BASE BUILDING MODERNIZATION

07/08/21

LYNDON LAWYER VANCE WHITESEL

PROJECT ENGINEER, AJW-2W11C MANAGER, AJW-2W11C

LONG BEACH CA

ISSUED BY

ATO - TECHNICAL OPERATIONS WESTERN SERVICE AREA

ISSUE FOR 100% DESIGN SUBMISSION

LGB-1508914- CALIFORNIA

LONG BEACH

LONG BEACH ATCT

1508914

LONG BEACH AIRPORT (LGB)

TERMINAL, LA A

ENGINEERING SERVICES

JULY 8, 2021

A4 ATCT - CAB LEVEL

SCALE:‚" = 1'-0"

N

CAB

DEMOLITION PLAN

02'4' 4' 8'

1/4" = 1'-0"

DEMOLITION - ATCT FLOOR PLANS

A2

SCALE:‚" = 1'-0"

A3

SCALE:‚" = 1'-0"

C1

SCALE:‚" = 1'-0"

C2

SCALE:‚" = 1'-0"

D1

SCALE:‚" = 1'-0"

D2

SCALE:‚" = 1'-0"

D3

SCALE:‚" = 1'-0"

ATCT - JUNCTION LEVEL C4

SCALE:‚" = 1'-0"

A1

SCALE:‚" = 1'-0"

ATCT - BASEMENT LEVEL ATCT - 3RD & 4TH LEVELS

ATCT - 1ST LEVEL ATCT - 5TH LEVEL

ATCT - 6TH & 7TH LEVELSATCT - 2ND LEVEL

CAB

ELEVATOR

VESTIBULE

ELEVATOR

SHAFT

ELEVATOR SHAFT

CABLE

SHAFT

CABLE

PIT

ELEVATOR

MACHINE ROOM

SHAFT

CABLE

SHAFT

ELEVATOR

SHAFT

ELEVATOR SHAFT

CABLE

R.A.

S.A.

SHAFT

CABLE

SHAFT

ELEVATOR

R.A.

S.A.

SHAFT

ELEVATOR SHAFT

CABLE

R.A.

S.A.

R.A.

S.A.

R.A.

S.A.

R.A.

S.A.

DN

UP

DN

DN

DN

UP

UP

UP

DN

UP

DN

DN

DN

UP

DN

UP

DN

DN

DN

UP

HATCH

FLOOR

REMOVE FLOOR CARPET

8 11

DEMOLITION PLAN DEMOLITION PLAN DEMOLITION PLAN

DEMOLITION PLAN

DEMOLITION PLANDEMOLITION PLAN

DEMOLITION PLAN DEMOLITION PLAN

DEMOLITION PLAN

ATCT - CAB ROOF

STAIR

STAIR

401 STAIR

B01

STAIR

STAIR

VEST

STAIR

STAIR

1002 1001

VEST

802A

B01

A

B1004

A

B

A

B

B

A

C

JUNCTION ROOM

ACCESS

CATWALK

STAIR

CATWALK

REMOVE ROOF HATCH, HATCH CURB TO REMAIN

14 14

14 14

VEST

REST ROOM

ATCT - 8TH LEVEL (SUB-JUNCTION LEVEL)

802C

802B

A.

B.

REMOVE DOOR FRAME FROM CONCRETE WALL

REMOVE FLOOR TILES AND WALL BASE, COORDINATE WITH HAZMAT.

CAB STAIR TREADS AND NOSINGS, TYP.

REMOVE RUBBER SLIP RESISTANT FINISH FROM THE

3 3

REFER TO MECH AND ELECT FOR MECH AND ELECT DEMOLITION ITEMS.

BUTT JOINTS.

REMOVE STRUCTURAL SEALANT AT GLAZING

TYP.

EXIST. HANDRAIL

REMOVE LADDER UP TO CAB ROOF ACCESS HATCH

DEMOLITION KEY NOTES:

GENERAL SHEET DEMOLITION NOTES:

AD103

AD103 AD103

AD103 AD103

AD103 AD103

AD103 AD103 AD103 AD103

K. KUSTRA

K. KUSTRA

W. STEVENS

REMOVE DOOR, COORDINATE WITH HAZMAT.

PROVIDE OPENING AT CAB PARAPET FOR OVERFLOW SCUPPER.

REMOVE STAIR HANDRAIL.

REMOVE DOOR AND FRAME, COORDINATE WITH HAZMAT.

TO MATCH ADJACENT EXISTING SURFACE AS REQUIRED.

REMOVE ROOM SIGNS. REPAIR AND FINISH WALL AND/OR DOOR

17 PREPARE GUARDRAIL FOR THE WORK. REMOVE LOOSE AND PEELING PAINT.

TYP. TYP.

TYP.

TYP.

TYP.

TYP. TYP.

TYP.

NOT USED

WITH COR TO MAINTAIN EGRESS IN THE ATCT DURING THE WORK.

REMOVE SLIP RESISTANT STRIPS FROM STAIR NOSING, TYP. COORDINATE

S E

A D

M A

T C

H

L

IN

NOT USED

EXIST. HOOD

EXIST. HOOD

COORDINATE WITH HAZMAT.

REMOVE DAMAGED SEALANT JOINTS FROM PARAPET COPING,

COORDINATE WITH HAZMAT.

REMOVE SEALANT AT PERIMETER OF CAB WINDOW FRAME,

Chanh Huynh Text Box This sheet and all sheets following it are part of a different modernization project for LGB ATCT. I've included them to show a clearer picture of tower. None of the work shown in these plans is part of solicitation for the slatwall consoles. They should only be used for reference and not indicate any additional scope or changes to the solicitation.

DESIGN FILE:

DATE: TIME: USER:

A

B

C

D

E

$$DATE $$TIME $$USER

$$DGN

DEPARTMENT OF TRANSPORTATION

FEDERAL AVIATION ADMINISTRATION

SUBMITTED BY

DRAWN BY

DESIGNED BY

CHECKED BY

APPROVED BY

DATE

DRAWING NO.

DESCRIPTIONREV.

REVIEWED BY

2 3 4 5 6

B

D

E

1 2 3 4 5 6

REV.

JCN:

JCN

DATE

REDLINE

APVD

DATE

APPROVED

FOR OFFICIAL USE ONLY

PUBLIC AVAILABILITY TO BE DETERMINED UNDER 5 USC 552

R

LGB ATCT AND BASE BUILDING MODERNIZATION

07/08/21

LYNDON LAWYER VANCE WHITESEL

PROJECT ENGINEER, AJW-2W11C MANAGER, AJW-2W11C

LONG BEACH CA

ISSUED BY

ATO - TECHNICAL OPERATIONS WESTERN SERVICE AREA

ISSUE FOR 100% DESIGN SUBMISSION

LGB-1508914- CALIFORNIA

LONG BEACH

LONG BEACH ATCT

1508914

LONG BEACH AIRPORT (LGB)

TERMINAL, LA A

ENGINEERING SERVICES

JULY 8, 2021

A3

N

HATCH

FLOOR

SCALE: 1/2" = 1'-0"

3/4" HW

3/4" CW

3" SAN

1 1/2" SAN 3" SAN DN

FD

3" V

3" SAN1" CW

WATER COOLER

BFP

1/2" CW

1/2" COND

1/2" COND UP

1/2" HW

1/2" CW

1/2" CW

1/2" HW

1 1/2" IW

1/2" HW DN

1/2" CW DN

1 1/2" INDIRECT DRAIN

SHEET NOTES:

ATCT - JUNCTION LEVEL PLAN - DEMOLITION

ATCT - CAB LEVEL PLAN -DEMOLITION

SCALE: 1/2 " = 1'-0"

02'4' 4' 8'

1/4" = 1'-0"

0 2' 4'1'12" 3' 5'

1/2" = 1'-0"

J. LEMENS

DEMOLISH WATER HEATER.

DEMOLISH SINK, BUBBLER AND FAUCET.

RESTROOM

ACCESS

CATWALK

VEST

JUNCTION ROOM

CAB

B01

STAIR

SHAFT

CABLE

ELEVATOR PIT

ELEVATOR MACHINE

DEMOLISH SUMP PUMP.

5 DEMOLISH LAVATORY AND FAUCET.

S. TRAN

S. TRAN

PD110

PD110

PD110

PD110

DEMOLISH WATER PRESSURE BOOSTER PUMP.

C1

B6

SCALE: 1/4" = 1'-0"

ATCT - BASEMENT LEVEL PLAN - DEMOLITION

GENERAL NOTES:

A.

GENERAL NOTES.

REFER TO SHEET P001 FOR ABBREVIATIONS, SYMBOLS AND

1/2" CW UP

1/2" CW

FLOOR PLANS DEMOLITION

PLUMBING CAB, JUNCTION, AND BASEMENT LEVEL

Chanh Huynh Sticky Note This is part of console solicitation needs to be removed from modernization scope.

Chanh Huynh Callout Supply duct/chase

Chanh Huynh Callout Supply chase/duct

File details come from the government source that posted it. Updated .