This federal solicitation seeks offers for a roof and HVAC replacement project at a Long Range Radar site in London, Ohio. The work includes removing an existing roof and HVAC units, installing a new roof and HVAC systems along with associated components, and abating asbestos. Offers are due by July 26, 2022 and shall be submitted via email. The project is set aside for small businesses and has an estimated value between $450,000 to $550,000. The period of performance is approximately 120 calendar days. The soliciting agency is the Federal Aviation Administration Southwestern Region.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
A. NAME B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder"
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED BID (RFP)
WS-22-01566
FEDERAL AVIATION ADMINISTRATION
AAQ-500 - REGIONAL ACQUISITIONS
1701 COLUMBIA AVENUE
COLLEGE PARK GA 30337
AAQ510ATL-AFN
suzanne.t-ctr.huggins@faa.gov
Suzanne Huggins
104/29/2022 59
PURCHASE REQUEST NO.
697DCK-22-R-00350
10. THE CONTRACT AUTHORITY REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
The total estimated contract value for this project is between $450,000 and $550,000.
THIS IS A TOTAL SET-ASIDE FOR SMALL BUSINESS CONCERNS ONLY.
11. The Contractor shall begin performance within
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award notice to proceed. The performance period is mandatory, negotiable. (See ________________________________________________ .)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and is not required.is, B. An offer guarantee
C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers must be publicly opened at that time . Sealed envelopes containing offers shall be marked to show the offeror's name and address. The solicitation number, and the date and time offers are due.
D. Offers providing less than
12B. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in item 12B.)
5 120 calendar days and complete it within ________________ ________________ calendar days after receiving
1 1500
07/26/2022 x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Contract Authority acceptance after the date offers are due will not be considered and will _________________ be rejected.
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Contract Authority in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13D. Failure to insert any number means the offeror accepts the minimum in item 13D.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (MUST BE FULLY COMPLETED BY OFFEROR)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20B. SIGNATURE 20C. OFFER DATE
AWARD (To be completed by Contract Authority)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Contract Authority solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31A. NAME OF CONTRACTING OFFICER (Type or print)
30B. SIGNATURE 30C. DATE 31B. CONTRACT AUTHORITY 31C. AWARD DATE
BY
2PAGE OF
FEDERAL AVIATION ADMINISTRATION
AAQ-500 - REGIONAL ACQUISITIONS
1701 COLUMBIA AVENUE
COLLEGE PARK GA 30337
AAQ510ATL-AFN
Marc R. LeMay
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.)
Continued...
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
3 59
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
697DCK-22-R-00350
(A) (B) (C) (D) (E) (F)
Delivery: 120 Days After Notice to Proceed
Delivery Location Code: C695536F
C695536F
695536 DOT FAA
KCMH SSC LONDON LRR OFFICE
1365 OLD XENIA RD SW F
LONDON OH 431409250 US
00001 The selected Contractor shall furnish all labor, product, equipment, materials, and supervision for the demolition and installation associated with HVAC and Roof Replacement at the QWO Long
Range Radar (ARSR) site located near London, OH in accordance with the statement of work, specifications and project drawings described in
Section J of this Screening Information Request
(SIR).
Electronic & IT: 03
00002 The selected Contractor shall furnish all labor, product, equipment, materials, and supervision for third-party air monitoring associated with the HVAC Replacement project at the London (QWO)
Long Range Radar (ARSR) site located near London, OH in accordance with the statement of work and specifications described in Section J of this
Screening Information Request (SIR).
Electronic & IT: 03
Section B - Supplies or Services/Prices Section B - Schedule
The Contractor price must include all costs related to (a) direct and indirect labor, fringe benefits, overhead, G&A expenses, profit, material, equipment, other direct costs, insurance, freight, handling, transportation, inspection, testing, operation and maintenance manuals, bonds, etc, (b) federal, state, and local taxes, (c) all applicable fees permits, licenses, and (d) any miscellaneous charges.
TOTAL PRICE: _________________________
Clause List
The remainder of this page has been intentionally left blank.
Section C - Description/Specifications Scope of Work
The selected Contractor shall furnish all labor, product, equipment, materials, and supervision for the demolition and installation associated with the Roof and HVAC Replacement Project, including asbestos abatement and air monitoring, at the London (QWO) Long Range Radar (ARSR) site located near London, OH in accordance to the attached Statements of Work and drawings.
Clause List
Section D - Packaging and Marking Clause List
D - SECTION D - N/A
There are no applicable Section D clauses.
Section E - Inspection and Acceptance Clause List
3.10.4-10 INSPECTION OF CONSTRUCTION (SEP 2009)
(a) 'Work' includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not--
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) below.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.
(e) The Contractor shall promptly furnish, without additional charge, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer.
The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless the Government determines that it is in the public interest to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may:
(1) by contract or otherwise, replace or correct the work and charge the cost to the Contractor or
(2) terminate for default the Contractor's right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.
(j) In the absence of any formal disputes, a project will be deemed physically and financially complete within one year after final acceptance and excess funds will be deobligated at that time.
(End of clause)
Section F - Deliveries or Performance Clause List
3.10.1-24 NOTICE OF DELAY (MAR 2009)
If the Contractor becomes unable to complete the contract work at the time(s) specified because of technical difficulties, notwithstanding the exercise of good faith and diligent efforts in the performance of the work called for hereunder, the contractor shall give the Contracting officer written notice of the anticipated delay and the reasons therefor. Such notice and reasons shall be delivered promptly after the condition creating the anticipated delay becomes known to the contractor, but in no event less than forty-five (45) days before the completion date specified in this contract, unless otherwise directed by the Contracting Officer. When notice is so required, the Contracting officer may extend the time specified in the Schedule for such period as deemed advisable.
Section G - Contract Administration Data Clause List
3.10.1-23 CONTRACTING OFFICER'S REPRESENTATIVE-CONSTRUCTION CONTRACTS (APR
2012)
(a) The Contracting Officer may appoint other Government personnel to accomplish certain contract administration matters. While there shall be various titles and divisions of duties for these individuals, generically they are known as Contracting Officer's Representatives (CORs). The Contracting Officer will provide written notice of COR appointment(s), setting forth the authorities and limitations, to the Contractor within 5 calendar days prior to the notice to proceed. COR duties may include, but are not limited to:
(1) Perform as the authorized representative of the Contracting Officer for technical matters, including interpretation of specifications and drawings, and inspection and review of work performed.
(2) Perform as the authorized representative of the Contracting Officer for administrative matters, including reviewing payments, and updated delivery schedules.
(b) These representatives are authorized to act for the Contracting Officer in all specifically delegated matters pertaining to the contract, except:
(1) contract modifications that change the contract price or cost, technical requirements or time for performance, unless delegated field change order authority;
(2) suspension or termination of the Contractor's right to proceed, either for default or for convenience;
(3) final decisions on any matters subject to appeal, e.g., disputes under the "Contract Disputes" clause; and
(4) final acceptance under the contract.
Section H - Special Contract Requirements Clause List
3.1.9-1 ELECTRONIC COMMERCE AND SIGNATURE (JUL 2020)
(a) The Electronic Signatures in Global and National Commerce Act (E-SIGN) establishes a legal equivalence between:
(1) Contracts written on paper and contracts in electronic form;
(2) Pen-and-ink signatures and electronic signatures; and
(3) Other legally-required written records and the same information in electronic form.
(b) With the submission of an offer, the offeror acknowledges and accepts the utilization of electronic commerce as part of the requirements of this solicitation and the resultant contract.
(c) Certain documents may need to be provided or maintained in original form, such as large-scale drawings impractical to convert to electronic format or a document with a raised seal signifying authenticity. This clause does not change or affect any other requirements that a document must be in paper format to satisfy legal requirements such as for certain real estate transactions.
(d) The use of electronic signature technology is authorized under this solicitation and the resulting contract.
(e) Contractors must not digitally sign any documents with software that uses the Secure Hash Algorithm 1 (SHA- 1). All digitally signed documents and contracts sent to the FAA must use a SHA-256 or higher hash algorithm. This is based on the National Institute of Standards and Technology (NIST) Policy Statement on Hash Functions dated August 5, 2015. Further guidance on the use of SHA-256 is in NIST Special Publication (SP) 800-57 Part 1, section
5.6.2 as amended and SP 800-131A, Revision 1 dated November 6, 2015. Additional guidance on the use of SHA-3 is in NIST SP 800-185 as amended.
(f) Contractors do not have to update documents previously digitally signed using SHA-1 hash algorithms unless the document requires updating. The FAA and contractors may continue to use SHA-1 for the following applications:
Verifying old digital signatures and time stamps, generating and verifying hash-based message authentication codes (HMACs), key derivation functions (KDFs), and random bit/number generation.
(End of Clause)
Section I - Contract Clauses Clause List
3.1-1 CLAUSES AND PROVISIONS INCORPORATED BY REFERENCE (JUL 2019)
This screening information request (SIR) or contract, as applicable, incorporates by reference the provisions or clauses listed below with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make the full text available, or offerors and contractors may obtain the full text via Internet at:
https://fast.faa.gov/contractclauses.cfm.
(End of clause)
3.1.7-1 EXCLUSION FROM FUTURE AGENCY CONTRACTS (JUL 2018)
3.1.7-2 ORGANIZATIONAL CONFLICTS OF INTEREST (JUL 2018)
3.2.2.3-42 DIFFERING SITE CONDITIONS (JUL 2004)
3.2.2.3-43 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (JUL 2004)
3.2.2.3-45 MATERIAL AND WORKMANSHIP (JUL 2004)
3.2.2.3-46 SUPERVISING THE CONTRACT WORK (JUL 2004)
3.2.2.3-47 PERMITS AND RESPONSIBILITIES (JUL 2004)
3.2.2.3-48 OTHER CONTRACTS (MAR 2009)
3.2.2.3-49 PROTECTING EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,
AND IMPROVEMENTS (JUL 2004)
3.2.2.3-50 PROPERTY PROTECTION (OCT 2014)
3.2.2.3-51 OPERATIONS AND STORAGE AREAS (APR 2012)
3.2.2.3-53 CLEANING UP AND ROADWAY MAINTENANCE (JUL 2004)
3.2.2.3-54 PREVENTING ACCIDENTS (JUL 2004)
3.2.2.3-56 SCHEDULES FOR CONSTRUCTION CONTRACTS (JUL 2004)
3.2.2.3-60 SPECIFICATIONS, DRAWINGS, AND MATERIAL OFFERS (MAR 2009)
3.2.2.3-68 SAFETY AND HEALTH (OCT 2014)
3.2.2.3-83 PROHIBITION AGAINST CONTRACTING WITH INVERTED DOMESTIC
CORPORATIONS (OCT 2015)
3.2.2.7-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH
CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (APR 2011)
3.2.2.7-8 DISCLOSURE OF TEAM ARRANGEMENTS (APR 2008)
3.2.4-4 FIXED-PRICE CONTRACTS WITH ECONOMIC PRICE ADJUSTMENT-LABOR AND
MATERIAL (OCT 2019)
3.2.5-1 OFFICIALS NOT TO BENEFIT (APR 2021)
3.2.5-3 GRATUITIES OR GIFTS (OCT 2019)
3.2.5-4 CONTINGENT FEES (OCT 1996)
3.2.5-5 ANTI-KICKBACK PROCEDURES (OCT 2019)
3.2.5-8 WHISTLEBLOWER PROTECTION FOR CONTRACTOR EMPLOYEES (APR 1996)
3.3.1-2 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (JUL 2018)
3.3.1-4 PAYMENT UNDER COMMUNICATION SERVICE CONTRACTS WITH COMMON
CARRIERS (JUL 2018)
3.3.1-15 ASSIGNMENT OF CLAIMS (JUL 2018)
3.3.1-19 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2021)
3.3.1-20 PROVIDING ACCELERATED PAYMENT TO SMALL BUSINESS SUBCONTRACTORS
(OCT 2012)
3.3.1-31 PROGRESS PAYMENTS (JUL 2018)
3.3.1-34 PAYMENT BY ELECTRONIC FUNDS TRANSFER- SYSTEM FOR AWARD
MANAGEMENT (JUL 2018)
3.4.1-7 NOTICE TO PROCEED (OCT 2019)
3.4.1-10 INSURANCE - WORK ON A GOVERNMENT INSTALLATION (OCT 2020)
3.4.2-6 TAXES - CONTRACTS PERFORMED IN U.S. POSSESSIONS OR PUERTO RICO (OCT
1996)
3.4.2-8 FEDERAL, STATE, AND LOCAL TAXES - FIXED PRICE CONTRACT (JUL 2019)
3.5-1 AUTHORIZATION AND CONSENT (JAN 2019)
3.5-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT
(JAN 2009)
3.5-4 PATENT INDEMNITY - CONSTRUCTION CONTRACTS (JAN 2009)
3.6.1-1 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (OCT 2019)
3.6.2-1 CONTRACT WORK HOURS AND SAFETY STANDARDS ACT-OVERTIME
COMPENSATION (OCT 2018)
3.6.2-2 CONVICT LABOR (APR 1996)
3.6.2-9 EQUAL OPPORTUNITY (JUL 2020)
3.6.2-12 EQUAL OPPORTUNITY FOR VETERANS (APR 2022)
3.6.2-13 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (APR 2022)
3.6.2-18 DAVIS BACON ACT (OCT 2018)
3.6.2-19 WITHHOLDING-LABOR VIOLATIONS (JUL 2017)
3.6.2-20 PAYROLLS AND BASIC RECORDS (APR 2017)
3.6.2-21 APPRENTICES, TRAINEES, AND HELPERS (JAN 2019)
3.6.2-22 SUBCONTRACTS (LABOR STANDARDS) (JAN 2019)
3.6.2-23 CERTIFICATION OF ELIGIBILITY (JAN 2019)
3.6.2-35 PREVENTION OF SEXUAL HARASSMENT (OCT 2018)
3.6.2-39 TRAFFICKING IN PERSONS (APR 2019)
3.6.2-44 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS
ACT (JAN 2019)
3.6.3-7 WASTE MANAGEMENT AND POLLUTION PREVENTION (JAN 2020)
3.6.3-13 AFFIRMATIVE PROCUREMENT OF RECYCLED CONTENT AND PRODUCTS UNDER
SERVICE AND CONSTRUCTION CONTRACTS (JAN 2020)
3.6.3-14 USE OF ENVIRONMENTALLY PREFERABLE PRODUCTS (JAN 2020)
3.6.3-16 DRUG FREE WORKPLACE (MAR 2009)
3.6.3-23 DELIVERY OF ELECTRONIC AND PAPER DOCUMENTS (JAN 2020)
3.6.4-2 BUY AMERICAN ACT - SUPPLIES (APR 2022)
3.6.4-10 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JAN 2010)
3.6.4-23 PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND
VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (APR 2022)
3.9.1-1 CONTRACT DISPUTES (JAN 2020)
3.9.1-2 PROTEST AFTER AWARD (AUG 1997)
3.10.1-7 BANKRUPTCY (APR 1996)
3.10.1-8 SUSPENSION OF WORK (SEP 1998)
3.10.1-15 CHANGES-CONSTRUCTION, DISMANTLING, DEMOLITION, OR REMOVAL OF
IMPROVEMENTS (APR 2022)
3.10.1-16 CHANGES AND CHANGED CONDITIONS (APR 2022)
3.10.1-20 WARRANTY-CONSTRUCTION (JUL 1996)
3.10.1-25 NOVATION AND CHANGE-OF-NAME AGREEMENTS (OCT 2007)
3.10.3-2 GOVERNMENT PROPERTY - BASIC CLAUSE (APR 2022)
3.10.6-6 DEFAULT (FIXED PRICE CONSTRUCTION) (OCT 1996)
3.13-5 SEAT BELT USE BY CONTRACTOR EMPLOYEES (OCT 2001)
3.13-13 CONTRACTOR POLICY TO BAN TEXT MESSAGING WHILE DRIVING (JAN 2011)
3.14-4 ACCESS TO FAA FACILITIES, SYSTEMS, GOVERNMENT PROPERTY, AND SENSITIVE
UNCLASSIFIED INFORMATION (OCT 2021)
3.2.2.3-41 PERFORMING WORK (JUL 2004)
The Contractor (you) must perform, using your own organization, work equivalent to at least 25 percent of the total amount of work under the contract on the site. The CO may modify this contract to reduce this percentage if you request a reduction and the CO determines that it would be to the Government's advantage to do so.
(End of clause)
3.2.2.3-71 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (OCT 2021)
The Contractor must (a) begin work under this contract within 5 calendar days after the date you receive the notice to proceed, (b) perform the work diligently, and (c) complete the entire work ready for use not later than 120 calendar days. The time allowed for completion must include final cleanup of the premises.
(End of clause)
3.3.1-31 PROGRESS PAYMENTS (JUL 2018) - ALTERNATE I (JUL 2018)
Substitute the following paragraphs(a)(1) and (a)(2) in the basic clause
Progress payments will be made to the Contractor when requested as work progresses, but not more frequently than monthly in amounts approved by the Contracting Officer, under the following conditions:
(a)Computation of amounts.
(1) Unless the Contractor requests a smaller amount, each progress payment will be computed as
(i) 85 percent of the Contractor's total costs incurred under this contract whether or not actually paid, plus
(ii) Progress payments to subcontractors (see paragraph (j) below), all less the sum of all previous progress payments made by the Government under this contract.
(iii) Cost of money is allowable subject to the requirements of clause 3.3.2-1, "FAA Cost Principles".
(2) Accrued costs of Contractor contributions under employee pension plans will be excluded until actually paid unless"
(i) The Contractor's practice is to make contributions to the retirement fund quarterly or more frequently; and
(ii) The contribution does not remain unpaid 30 days after the end of the applicable quarter or shorter payment period (any contribution remaining unpaid will be excluded from the Contractor's total costs for progress payments until paid).
(A) Materials issued from the Contractor's stores inventory and placed in the production process for use on this contract.
(B) Direct labor, direct travel, and other direct in-house costs.
(C) Properly allocable and allowable indirect costs.
(iii) Accrued costs of Contractor contributions under employee pension or other postretirement benefit, profit sharing, and stock ownership plans will be excluded until actually paid unless---
(A) The Contractor's practice is to contribute to the plans quarterly or more frequently; and
(B) The contribution does not remain unpaid 30 days after the end of the applicable quarter or shorter payment period (any contributions remaining unpaid will be excluded from the Contractor's total costs for progress payments until paid).
(iv) If the contract is subject to the special transition method authorized in Cost Accounting Standard (CAS) 410, Allocation of Business Unit General and Administrative Expense to Final Cost Objective, General and Administrative expenses (G&A) will not be included in progress payment requests until the suspense account prescribed in CAS 410 is less than--
(A) Five million dollars; or
(B) The value of the work-in-process inventories under contracts entered into after the suspense account was established (only a pro rata share of the G&A allocable to the excess of the inventory over the suspense account value is includable in progress payment requests under this contract).
(3) The Contractor must not include the following in total costs for progress payment purposes in subparagraph (a)(1)(i) above:
(i) Costs that are not reasonable, allocable to this contract, and consistent with sound and generally accepted accounting principles and practices.
(ii) Costs incurred by subcontractors or suppliers.
(iii) Costs ordinarily capitalized and subject to depreciation or amortization except for the properly depreciated or amortized portion of such costs.
(iv) Payments made or amounts payable to subcontractors or suppliers, except for--
(A) Completed work, including partial deliveries, to which the Contractor has acquired title; and
(B) Work under cost-reimbursement or time-and-material subcontracts to which the Contractor has acquired title.
(4) The amount of unliquidated progress payments may exceed neither (i) the progress payments made against incomplete work (including allowable unliquidated progress payments to subcontractors) nor (ii) the value, for progress payment purposes, of the incomplete work. Incomplete work will be considered to be the supplies and services required by this contract, for which delivery and invoicing by the Contractor and acceptance by the Government are incomplete.
(5) The total amount of progress payments will not exceed 80 percent of the total contract price.
(6) If a progress payment or the unliquidated progress payments exceed the amounts permitted by subparagraphs (a)(4) or (a)(5) above, the Contractor must repay the amount of such excess to the Government on demand subject to
1.6 percent interest calculated from the time the excess payment was received by the contractor until such time as the reimbursement is received by the Government
(b) Liquidation. Except as provided in termination clauses of the contract, all progress payments will be liquidated by deducting from any payment under this contract, other than advance or progress payments, the unliquidated progress payments, or 80 percent of the amount invoiced, whichever is less. The Contractor must repay to the Government any amounts required by a retroactive price reduction, after computing liquidations and payments on past invoices at the reduced prices and adjusting the unliquidated progress payments accordingly. The Government reserves the right to unilaterally change from the ordinary liquidation rate to an alternate rate when deemed appropriate for proper contract financing.
(c) Reduction or suspension. The Contracting Officer may reduce or suspend progress payments, increase the rate of liquidation, or take a combination of these actions, after finding on substantial evidence any of the following conditions:
(1) The Contractor failed to comply with any material requirement of this contract (which includes paragraphs (f) and (g) below).
(2) Performance of this contract is endangered by the Contractor's (i) failure to make progress or (ii) unsatisfactory financial condition.
(3) Inventory allocated to this contract substantially exceeds reasonable requirements.
(4) The Contractor is delinquent in payment of the costs of performing this contract in the ordinary course of business.
(5) The unliquidated progress payments exceed the fair value of the work accomplished on the undelivered portion of this contract.
(6) The Contractor is realizing less profit than that reflected in the establishment of any alternate liquidation rate in paragraph (b) above, and that rate is less than the progress payment rate stated in subparagraph (a)(1) above.
(d) Title.
(1) Title to the property described in this paragraph (d) will vest in the Government. Vestiture will be immediately upon the date of this contract, for property acquired or produced before that date. Otherwise, vestiture will occur when the property is or should have been allocable or properly chargeable to this contract.
(2) Property, as used in this clause, includes all of the below-described items acquired or produced by the Contractor that are or should be allocable or properly chargeable to this contract under sound and generally accepted accounting principles and practices.
(i) Parts, materials, inventories, and work in process;
(ii) Special tooling and special test equipment to which the Government is to acquire title under any other clause of this contract;
(iii) Nondurable (i.e., noncapital) tools, jigs, dies, fixtures, molds, patterns, taps, gauges, test equipment, and other similar manufacturing aids, title to which would not be obtained as special tooling under subparagraph (ii) above;
and
(iv) Drawings and technical data, to the extent the Contractor or subcontractors are required to deliver them to the Government by other clauses of this contract.
(3) Although title to property is in the Government under this clause, other applicable clauses of this contract; e.g., the termination or special tooling clauses, will determine the handling and disposition of the property.
(4) The Contractor may sell any scrap resulting from production under this contract without requesting the Contracting Officer's approval, but the proceeds will be credited against the costs of performance.
(5) To acquire for its own use or dispose of property to which title is vested in the Government under this clause, the Contractor must obtain the Contracting Officer's advance approval of the action and the terms. The Contractor must
(i) exclude the allocable costs of the property from the costs of contract performance, and (ii) repay to the Government any amount of unliquidated progress payments allocable to the property. Repayment may be by cash or credit memorandum.
(6) When the Contractor completes all of the obligations under this contract, including liquidation of all progress payments, title will vest in the Contractor for all property (or the proceeds thereof) not-
(i) Delivered to, and accepted by, the Government under this contract; or
(ii) Incorporated in supplies delivered to, and accepted by, the Government under this contract and to which title is vested in the Government under this clause.
(7) The terms of this contract concerning liability for Government-furnished property will not apply to property to which the Government acquired title solely under this clause.
(e) Risk of loss. Before delivery to and acceptance by the Government, the Contractor must bear the risk of loss for property, the title to which vests in the Government under this clause, except to the extent the Government expressly assumes the risk. The Contractor must repay the Government an amount equal to the unliquidated progress payments that are based on costs allocable to property that is damaged, lost, stolen, or destroyed.
(f) Control of costs and property. The Contractor must maintain an accounting system and controls adequate for the proper administration of this clause.
(g) Reports and access to records. The Contractor must promptly furnish reports, certificates, financial statements, and other pertinent information reasonably requested by the Contracting Officer for the administration of this clause.
Also, the Contractor must give the Government reasonable opportunity to examine and verify the Contractor's books, records, and accounts.
(h) Special terms regarding default. If this contract is terminated under the contract default clause,
(1) The Contractor must, on demand, repay to the Government the amount of unliquidated progress payments and
(2) Title will vest in the Contractor, on full liquidation of progress payments, for all property for which the Government elects not to require delivery under the contract default clause. The Government will be liable for no payment except as provided by the contract default clause.
(i) Reservations of rights.
(1) No payment or vesting of title under this clause will
(i) excuse the Contractor from performance of obligations under this contract or
(ii) constitute a waiver of any of the rights or remedies of the parties under the contract.
(2) The Government's rights and remedies under this clause
(i) Will not be exclusive but rather will be in addition to any other rights and remedies provided by law or this contract and
(ii) Will not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor will such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.
(j) Finance payments to subcontractors. The amounts mentioned in (a)(1)(ii) above will be all financing payments to subcontractors or divisions, if the following conditions are met:
(1) The amounts included are limited to (i) the unliquidated remainder of progress payments made plus (ii) for small business concerns any unpaid subcontractor requests for progress payments that the Contractor has approved for current payment in the ordinary course of business.
(2) The subcontract or interdivisional order is expected to involve a minimum of approximately 6 months between the beginning of work and the first delivery, or, if the subcontractor is a small business concern, 4 months.
(3) If the financing payments are in the form of progress payments, the terms of the subcontract or interdivisional order concerning progress payments--
(i) Are substantially similar to the terms of this clause at 3.3.1-31, Progress Payments, for any subcontractor that is a large business concern;
(ii) Are at least as favorable to the Government as the terms of this clause;
(iii) Are not more favorable to the subcontractor or division than the terms of this clause are to the Contractor;
(iv) Must indicate that the Contractor, and not the Government, awards the subcontract and administers the progress payments. (v) Subordinate all subcontractor rights concerning property to which the Government has title under the subcontract to the Government's right to require delivery of the property to the Government for valid reasons not limited to (A) default of the Contractor, or (B) bankruptcy or insolvency of the subcontractor.
(4) If the financing payments are in the form of performance-based payments, the terms of the subcontract or interdivisional order concerning payments--
(i) Are substantially similar to clause 3.3.1-32 -Performance-Based Payments;
(ii) Subordinate all subcontractor rights concerning property to which the Government has title under the subcontract to the Government's right to require delivery of the property to the Government for valid reasons, not limited to --
(A) the default of the Contractor; or
(B) The bankruptcy or insolvency of the subcontractor.
(5) If the financing payments are in the form of commercial item financing payments, the subcontract or interdivisional order concerning payments subordinates all subcontractor rights concerning property to which the Government has title under the subcontract to the Government's right to require delivery of the property to the Government if--
(i) The Contractor defaults; or
(ii) The subcontractor becomes bankrupt or insolvent.
(6) The progress payment rate in the subcontract is 80% unless the subcontractor specifies a lesser amount. If the subcontractor is a small business concern, the progress payment rate may be up to 85%.
(7) The parties agree concerning any proceeds received by the Government for property to which title has vested in the Government under the subcontract terms that the proceeds will be applied to reducing any unliquidated progress payments by the Government to the Contractor under this contract.
(8) If no unliquidated progress payments to the Contractor remain, but there are unliquidated progress payments that the Contractor has made to any subcontractor, the Contractor must be subrogated to all the rights the Government obtained through the terms required by this clause to be in any subcontract, as if all such rights had been assigned and transferred to the Contractor.
(9) The Contractor must pay the subcontractor's progress payment request under subdivision (j)(1)(ii) above, within a reasonable time after receiving the Government progress payment covering those amounts.
(10) To facilitate small business participation in subcontracting under this contract, the Contractor agrees to provide progress payments to small business concerns of up to 85%. The Contractor further agrees that the need for such progress payments must not be considered as a handicap or adverse factor in the award of subcontracts.
(k) Limitations on Undefinitized Contract Actions.
Notwithstanding any other progress payment provisions in this contract, progress payments may not exceed 80 percent of costs incurred on work accomplished under undefinitized contract actions. A contract action' is any action resulting in a contract, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes. This limitation will apply to the costs incurred, as computed in accordance with paragraph (a) of this clause, and will remain in effect until the contract action is definitized. Costs incurred which are subject to this limitation will be segregated on Contractor progress payment requests and invoices from those costs eligible for higher progress payment rates. For purposes of progress payment liquidation, as described in paragraph (b) of this clause, progress payments for undefinitized contract actions will be liquidated at 80 percent of the amount invoiced for work performed under the undefinitized contract action as long as the contract action remains undefinitized. The amount of unliquidated progress payments for undefinitized contract actions will not exceed 80 percent of the maximum liability of the Government under the undefinitized contract action or such lower limit specified elsewhere in the contract. Separate limits may be specified for separate actions.
(End of clause)
3.3.1-33 SYSTEM FOR AWARD MANAGEMENT (APR 2022)
(a) Definitions. As used in this clause
"Registered in the SAM database" means that the Contractor has entered all mandatory information, including the Unique Entity Identifier (UEI) or the Electronic Funds Transfer indicator, into the SAM database.
"System for Award Management (SAM) database" means the primary Government repository for Contractor information required for the conduct of business with the Government.
"Unique Entity Identifier (UEI)" (also known as the Unique Entity ID) means a number or other identifier used to identify a specific commercial, nonprofit, or Government entity. See www.sam.gov for the designated entity for establishing unique entity identifiers.
"Electronic Funds Transfer indicator" means a 4-character suffix to the Unique Entity Identifier. This 4-character suffix may be assigned at the discretion of the business concern to establish additional SAM records for identifying alternative Electronic Funds Transfer (EFT) accounts for the same parent concern.
(b)(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee must be registered in the SAM database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The offeror must enter, in Representations, Certifications and Other Statements of Offerors Section of the solicitation, the UEI or EFT indicator that identifies the offeror's name and address exactly as stated in the offer. The UEI will be used by the Contracting Officer to verify that the offeror is registered in the SAM database.
(c) If the offeror does not have a UEI, it should contact www.sam.gov directly to obtain one.
The offeror should be prepared to provide the following information:
(1) Company legal business name.
(2) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(3) Company Physical Street Address, City, State, and ZIP Code.
(4) Company Mailing Address, City, State and ZIP Code (if different from physical street address).
(5) Company Telephone Number.
(6) Date the company was started.
(7) Number of employees at your location.
(8) Chief executive officer/key manager.
(9) Line of business (industry).
(10) Company Headquarters name and address (reporting relationship within your entity).
(d) If the offeror does not become registered in the SAM database in the time prescribed by the Contracting Officer, the Contracting Officer may proceed to award to the next otherwise successful registered offeror.
(e) Processing time should be taken into consideration when registering. Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.
(f) The Contractor is responsible for the accuracy and completeness of the data within the SAM database, and for any liability resulting from the Government's reliance on inaccurate or incomplete data. To remain registered in the SAM database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the SAM database to ensure it is current, accurate and complete. Updating information in the SAM does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document. If registered in SAM as a Service-Disabled Veteran-Owned Small Business (SDVOSB), by submission of an offer, the offeror acknowledges that they are designated as a SDVOSB by the Department of Veterans Affairs, and this designation appears as such on the Veteran Affairs website, https://vetbiz.va.gov/vip//.
(g)(1)(i) If a Contractor has legally changed its business name, "doing business as" name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in AMS Procurement Guidance, the Contractor must provide the responsible Contracting Officer a minimum of one business day's written notification of its intention to:
(A) Change the name in the SAM database;
(B) Comply with the requirements of AMS regarding novation and change-of-name agreements; and
(C) Agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide the Contracting Officer with the notification, sufficient documentation to support the legally changed name.
(ii) If the Contractor fails to comply with the requirements of paragraph (g)(1)(i) of this clause, or fails to perform the agreement at paragraph (g)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the SAM information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the "Suspension of Payment" paragraph of the electronic funds transfer (EFT) clause of this contract.
(2) The Contractor must not change the name or address for EFT payments or manual payments, as appropriate, in the SAM record to reflect an assignee for the purpose of assignment of claims. Assignees must be separately registered in the SAM database. Information provided to the Contractor's SAM record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the "Suspension of payment" paragraph of the EFT clause of this contract.
(h) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the internet at http://www.sam.gov.
(End of Clause)
3.3.1-40 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (APR 2022)
(a) Definitions. As used in this clause-
(1) "Contract financing" is a contractual authorization for payments to a contractor prior to acceptance of products or services by FAA.
(2) "Payment request" means a bill, voucher, invoice, or request for contract financing payment or invoice payment with associated supporting documentation. The payment request must comply with the requirements identified in this clause, and the applicable Payment clause and invoicing requirements included in this contract
(3) "Electronic form" means an automated system transmitting information electronically according to the accepted electronic data transmission methods and formats identified in paragraph (c) of this clause. Facsimile, email, and scanned documents are not acceptable electronic forms for submission of payment requests.
(4) "Invoice payment" means a Government disbursement of monies to a Contractor under a contract or other authorization for supplies or services accepted by the Government. This includes payments for partial deliveries that have been accepted by the Government, final payments under T&M and labor-hour contracts, and final cost or fee payments where amounts owed have been settled between the Government and the Contractor.
(b) Electronic payment requests. Except as provided in paragraph (f) of this clause, the contractor must submit payment requests in electronic form. Purchases paid with a Government purchase card are considered to be an electronic transaction for purposes of this rule, and therefore no additional electronic invoice submission is required.
(c) The Federal Aviation Administration utilizes the Delphi eInvoicing web-portal for processing invoices.
Contractors submitting invoices are required to submit invoices via the Delphi eInvoicing web portal which is accessed and authenticated via www.login.gov
(d) In order to receive payment and in accordance with prompt payment standards, contractors must submit a proper invoice. All invoices submitted as attachments in the Delphi eInvoicing web-portal must contain the following:
(1) Invoice number and invoice date.
(2) Period of performance covered by invoice.
(3) Contract number and title.
(4) Task/Delivery Order number and title (if applicable).
(5) Amount billed (by CLIN), current and cumulative.
(6) Total ($) of billing.
(7) Cumulative total billed for all contract work to date.
(8) Name, title, phone number, mailing address, and email address (if available) of person to be contacted in the event of a defective invoice.
If the contract includes allowances for travel, all invoices which include charges pertaining to travel expenses will catalog a breakdown of reimbursable expenses with the appropriate receipts to substantiate the travel expenses.
(e) Payment system registration. All persons accessing the Delphi eInvoicing web-portal will be required to have their own unique user Delphi eInvoicing ID and password and be credentialed through login.gov.
(1) Electronic authentication. See www.login.gov for instructions. Click on the following link for instructions on establishing a login.gov account: https://login.gov/help/creating-an-account/how-do-i-create-an-account-with-logingov/.
(2) To create a login.gov account, the user will need a valid email address and a working phone number. The user will create a password and then login.gov will reply with an email confirming the email address.
(3) DELPHI registration instructions. New users should request access to Delphi eInvoicing by sending an email to 9-AMC-FAA-iSupplier@faa.gov. Once access is granted, users should navigate to http://einvoice.esc.gov to activate the account. Users are required to log in every 45 days to keep it active.
(4) Training on DELPHI. To facilitate use of DELPHI, comprehensive user information is available at http://einvoice.esc.gov
(5) Account Management. Contractors are responsible to contact the DELPHI Help Desk when their firm's points of contacts will no longer be submitting invoices so they can be removed from the system. Instructions for contacting the DELPHI Help D can be found at http://einvoice.esc.gov
(f) Waivers: If the contractor does not believe electronic invoicing can be used if they are awarded this contract, the contractor must respond accordingly to 3.3.1-41 "Electronic Invoicing-Representation". Waiver requests must be approved by the FAA and DOT and will be processed expeditiously upon contract award. If the waiver request is not approved, the contractor must use electronic invoicing consistent with this clause. If the waiver request is approved, conversion to electronic invoicing at a later date may be required. While the waiver is in effect, the current invoicing process must be used per AMS Guidance T3.3.1A.14 and the terms of the contract. The decision regarding a waiver request is not subject to the "Contract Disputes" clause AMS 3.9.1-1.
3.3.2-1 FAA COST PRINCIPLES (OCT 2019)
(a) Federal Aviation Administration (FAA) "Contract Cost Principles" must be used for:
(1) The pricing of contracts, subcontracts, and modifications to contracts and subcontracts whenever cost analysis is performed; and
(2) The determination, negotiation, or allowance of costs when required by a contract clause.
(b) The Contracting Officer will incorporate the FAA cost principles and procedures in contracts with commercial organizations as the basis for:
(1) Determining reimbursable costs under
(i) Cost-reimbursement contracts and cost-reimbursement subcontracts under these contracts performed by commercial organizations and
(ii) The cost-reimbursement portion of time-and-materials contracts except when material is priced on a basis other than at cost;
(2) Negotiating indirect cost rates, when:
(i) FAA has division or corporate contract administration responsibilities;
(ii) Quick Close-out procedures are used;…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .