This amendment to a solicitation of offers modifies the requirements for a contract to provide carpet replacement and kitchen remodeling services at the Buffalo Air Traffic Control Tower in New York. Key changes include extending the response deadline to March 31, 2022, replacing statements of work, and requiring performance and payment bonds. Offerors must submit a proposal guarantee, wage determination applies, and the contractor will be selected using firm fixed price evaluation. The Federal Aviation Administration seeks to award a contract for removal and disposal of approximately 4,290 square feet of carpet tiles, and full renovation of the existing kitchen including cabinets, countertops, appliances, plumbing, and electrical work. A mandatory site visit will be held on February 22. All questions must be submitted by February 22 to allow response before final offers are due.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| double ovens.pdf | ||
| Questions and Answer as of 3.24.2022.pdf | ||
| dishwasher.pdf | ||
| microwave.pdf | ||
| fridge with ice maker.pdf | ||
| toaster oven.PNG | PNG image | |
| ice maker.pdf | ||
| stove top.pdf | ||
| BUF ATCT Kitchen Remodel SOW Rev 1 as of 3.8.22.doc | DOC document | |
| J.8 Performance Bond.pdf | ||
| J.6 Bid Bond.pdf | ||
| J.7 Payment Bond.doc | DOC document | |
| Questions and Answer as of 3.15.2022.pdf | ||
| SIR Amend 6973GH-22-R-00055-0002_FE.pdf | ||
| 6973GH-22-R-00055-0001_FE.pdf | ||
| Questions and Answer as of 2.22.2022.pdf | ||
| J.5 Wage Determination.pdf | ||
| J.1 BUF Carpet Base Building SOW.pdf | ||
| 6973GH-22-R-00055.pdf | ||
| J.3 Experience Information Form.pdf | ||
| J.2 BUF ATCT Kitchen Remodel SOW.pdf | ||
| J.4 Contractor's Release.pdf |
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The purpose of this Amendment is to:
FIRST: Extend the solicitation due date from 1700 on 21 March 2022 to 1700 on 31 March 2022.
SECOND: Incorporate and replace all other SOW versions of BUF ATCT Kitchen Remodel SOW
THIRD: Update SIR cover page block 12A to reflect Performance and Payment Bonds are REQUIRED
FOURTH: Update SIR cover page block 13C to reflect an Offer Guarantee IS REQUIRED
FIFTH: Incorporated Clauses 3.4.1-1 Proposal Guarantee and 3.6.2-47 Minimum Wage
SIXTH: Revoked Clause AC2916 Payment Procedures as it conflicts with clause 3.3.1-40 Electronic Invoicing Procedures
SEVENTH: All other terms and conditions remain unchanged and in full force and effect.
LIST OF CHANGES:
Section G - Contract Administration Data was revised as follows.
Clause List was revised as follows.
The following clauses are no longer incorporated.
AC2916 PAYMENT PROCEDURES (JUL 1997)
Section I - Contract Clauses was revised as follows.
Clause List was revised as follows.
The following clauses are incorporated by reference.
3.6.2-47 MINIMUM WAGES FOR CONTRACTOR WORKERS UNDER EXECUTIVE ORDER 14026
(JAN 2022)
Clause 3. is incorporated as follows:
(a) Offerors must furnish a proposal guarantee in the form of a proposal bond, a postal money order, a certified or cashier's check, an irrevocable letter of credit, or United States bonds or notes with a maturity of less than five years.
(b) The required amount of the proposal guarantee is 20% of proposed firm fixed price.
(c) The Contracting Officer will return proposal guarantees, other than proposal bonds:
(1) To unsuccessful offerors as soon as possible after an award decision is made; and
(2) To the successful offeror after it signs the contract and submits acceptable bonds required under the contract.
(d) If the successful offeror fails to sign the contract or submit the required bonds within the time specified by the Contracting Officer, the contract may be terminated for default.
(e) If the contract is terminated for default, the offeror is liable for any cost of acquiring the work in excess of its proposed price, and the guarantee is available to offset the difference. However, the guarantee is not an exclusive remedy.
Page
Section J - List of Documents, Exhibits and Other Attachments was revised as follows.
Attachment List was revised as follows.
Table has been revised and now reads as follows:
ATTACHMENT TITLE DATE
NO. OF
PAGES
1 BUF Carpet Base Building SOW 12/14/2021 9 2 BUF ATCT Kitchen Remodel SOW 12/14/2021 17 3 Experience Information Form 01/18/2022 1 4 Contractor's Release 01/07/2022 1 5 Wage Determination 12/24/2021 11 6 BUF ATCT Kitchen Remodel SOW Rev 1 as of 3.8.22 03/08/2022 9 7 Bid Bond 03/15/2022 2 8 Payment Bond 03/15/2022 2 9 Performance Bond 03/15/2022 2