Q_&_R.pdf

PDF 39 KB Posted

Attached to
Replacement of Laundry Room Flooring
Solicitation number
693JF718Q000024
Issued by

About this file

Q & R

View the file

Other files

File Type Posted
Q_&_R_v.1.pdf PDF
SOW__Rev.1.pdf PDF
SOW_.pdf PDF
Sol___693JF718Q000024.pdf PDF
Qtrs_B_Laundry_Diagrams.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sol # 693JF718Q000024 Replacement of Laundry Room Flooring Questions & Responses

Question 1) Is the crawl space easily accessible?

Response: The crawl space is somewhat accessible. The best access will be achieved when the existing floor and sub floor is removed.

Question 2) How many layers of sub-flooring is currently present?

Response: Since the exact number of sub-flooring layers cannot be determined, the flooring is the same height as adjoining rooms. (Note: The POC does not believe there are any additional layers of flooring below what can be seen).

Question 3) Must we remove the sub-floor down to the joist?

Response: Yes, the contractor would be responsible for removing the sub-floor down to the joist.

Question 4) What is the distance between the floor drain and the stack (main drain)?

Response: Since this is the laundry room, the drain runs directly below the floor. There may be a main line (4” cast iron) within approx. 20’.

Question 5) What is the length of the floor drain?

Response: Although the length of the floor drain cannot be determined, the idea is to install a traditional floor drain (round) in the center of the room not linear.

Question 6) Please clarify plumbing hardware?

Response: The plumbing hardware will consist of piping, fittings and hangars.

Question 7) What is the current size of the ceramic tile?

Response: Unable to provide the current size of the ceramic tile. The current the floor is vinyl.

Question 8) Is there storage space to relocate the washer and dryer, while work is underway?

Response: Yes, there is storage space to relocate the washer and dryer while work is underway.

The Academy POC intends to store the machines in the adjoining garage.

Question 9) What type of bond is required?

Response: A performance bond is required for this project.