A002_.pdf
PDF 1 MB Posted
- Attached to
- OR JOSEPH 2401(2), Galice Road Improvements
- Solicitation number
- 69056718B000022
About this file
Amendment A002
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BidSum_OR_Galice.pdf | ||
| Q&A_10-24-18.pdf | ||
| 10-24-18(2)Q&A.pdf | ||
| Q&A_10-24-18.pdf | ||
| A001.pdf | ||
| Q&A_10-18-18.pdf | ||
| Plan_Request_Form_Galice_Rd.pdf | ||
| Galice_Rd_Plan_Set_Sign_Off.pdf | ||
| IFB_Galice.pdf | ||
| PROJECT_DESCRIPTION_Galice.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A002 10/24/2018 N/A OR JOSEPH 2401(2), Galice Road Improvements
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X
69056718B000022
9B. DATED (SEE ITEM 11)
09/21/2018
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers (__ ) is extended, ( x ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
N/A
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
N/A
D OTHER (Specify type of modification and authority) N/A
E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
See page 2
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N/A
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Amendment No. A002, dated 10/24/2018 OR JOSEPH 2401(2), Solicitation No. 69056718B000022 Galice Road Improvements
REVISIONS ARE AS FOLLOWS:
BID SCHEDULE
Page A-8. Revises Item No. A0110 Description (post dimension) Page A-9 Revises Item No. A0190 Quantity
CONTRACT CLAUSES
SPECIAL CONTRACT REQUIREMENTS
Page F-4, Subsection 622.01(a) under Description, Revises the anticipated work under this section.
PLANS
Plan sheet B.1 Revises, Pay Item Description Item 61701-4500 and Quantity of Item 61707-1000
ENCLOSURES
Pages:
A-7 through A-9 F-4
Plan Sheets:
B.1 C.1 through C.2
Notice to Bidders: Please submit revised pages A-7 through A-9 with your bid.
Page A - 7
Bidder/Offeror please note: Before preparing the bid, carefully read the Solicitation Provisions.
Insert a unit bid price, in figures, for each pay item for which a quantity appears in the bid schedule. Multiply the unit price by the quantity for each pay item and show the amount bid. Should any mathematical check made by the Government show a mistake in the amount bid, the corrected unit price extension shall govern.
When the word "LPSM" (Lump Sum) appears as a unit bid price, insert an amount for each lump sum pay item.
When a sum based on a fixed rate appears for any pay item in the amount bid column, include the Government inserted amount bid for the item in the total bid amount.
Total all of the amounts bid for each pay item and show the total bid amount.
Bid Schedule
Project No:OR JOSEPH 2401(2)
Project Name:Galice Road Improvements
Revised by Amendment A002
Page A - 8
Item No. Pay Item No. Description Quantity Unit Unit Price Amount
A0010 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
A0020 15301-0000 CONTRACTOR QUALITY CONTROL
ALL LPSM $___LPSM_____ $____________
A0030 15501-0000 CONSTRUCTION SCHEDULE
ALL LPSM $___LPSM_____ $____________
A0040 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
10,700 LNFT $____________ $____________
A0050 20120-1000 REMOVAL, INDIVIDUAL TREE
2 EACH $____________ $____________
A0060 20302-1200 REMOVAL OF GUARDRAIL
13,470 LNFT $____________ $____________
A0070 30302-2000 SHOULDER RECONDITIONING
10,700 LNFT $____________ $____________
A0080 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS
16,000 LNFT $____________ $____________
A0090 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS (8' POSTS)
4,500 LNFT $____________ $____________
A0100 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS (NATINA)
3,625 LNFT $____________ $____________
A0110 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS (8' POSTS)
(NATINA)
875 LNFT $____________ $____________
A0120 61702-0000 TERMINAL SECTION (ANCHOR)
1 EACH $____________ $____________
A0130 61702-0300 TERMINAL SECTION, TYPE G4-BAT
3 EACH $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:OR JOSEPH 2401(2)
Project Name:Galice Road Improvements
A002
Page A - 9
A0140 61702-0300 TERMINAL SECTION, TYPE G4-BAT (NATINA)
1 EACH $____________ $____________
A0150 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT
21 EACH $____________ $____________
A0160 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT (NATINA)
1 EACH $____________ $____________
A0170 61702-1600 TERMINAL SECTION, TYPE MGS FLARED
11 EACH $____________ $____________
A0180 61702-1600 TERMINAL SECTION, TYPE MGS FLARED (NATINA)
3 EACH $____________ $____________
A0190 61707-1000 STRUCTURE TRANSITION RAILING, G4 SYSTEM
20 LNFT $____________ $____________
A0200 61709-4000 REMOVE AND RESET, TERMINAL SECTION
1 EACH $____________ $____________
A0210 62201-0850 WHEEL LOADER, 1 CUBIC YARD MINIMUM RATED CAPACITY
20 HOUR $____________ $____________
A0220 62201-2100 COMPACTOR (JUMPING JACK)
40 HOUR $____________ $____________
A0230 62201-2750 MOTOR GRADER
20 HOUR $____________ $____________
A0240 62301-0000 GENERAL LABOR
40 HOUR $____________ $____________
A0250 63501-0000 TEMPORARY TRAFFIC CONTROL
ALL LPSM $___LPSM_____ $____________
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:OR JOSEPH 2401(2)
Project Name:Galice Road Improvements
F-4 DIVISION 600
Special Contract Requirements Project: OR JOSEPH 2401(2), Galice Road Improvements
Section 622. — RENTAL EQUIPMENT
01/01/14–FP14
Description
622.01 Delete the text of this Subsection and substitute the following:
This work consists of furnishing and operating equipment for the construction work as ordered by the CO and listed below. Work under this Section does not include equipment time used to perform work provided for under any other pay item shown in the bid schedule. The work anticipated under this Section includes:
(a) Shoulder reconditioning.Terminal Section Grading.
Construction Requirements
622.02 Rental Equipment. Delete the text of the first paragraph and substitute the following:
Furnish and operate the following equipment:
Number of Units Type of Equipment 1 Wheel Loader, 1 Cubic Yard Minimum Rated Capacity
1 Motor Grader 1 Compactor (Jumping Jack)
Submit the model number and serial number for each piece of equipment before use. Make equipment available for inspection and approval before use.
Sheet and Description
Section C Section D
GUARDRAIL AND EROSION CONTROL TEMPORARY TRAFFIC CONTROL ALLOWANCE Bid Schedule
A0010 15101-0000 MOBILIZATION LPSM ALL
A0020 15301-0000 CONTRACTOR QUALITY CONTROL LPSM ALL
A0030 15501-0000 CONSTRUCTION SCHEDULE LPSM ALL
A0040 15705-1400 SOIL EROSION CONTROL, FIBER
ROLL LNFT 10,338 362 10,700
A0050 20120-1000 REMOVAL, INDIVIDUAL TREE EACH 2 2
A0060 20302-1200 REMOVAL OF GUARDRAIL LNFT 13,470 13,470
A0070 30302-2000 SHOULDER RECONDITIONING LNFT 10,338 362 10,700
A0080 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2,
CLASS A STEEL POSTS LNFT 15,378 622 16,000
A0090 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2,
CLASS A STEEL POSTS (8' POSTS) LNFT 4,328 172 4,500
A0100 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2,
CLASS A STEEL POSTS (NATINA) LNFT 3,515 110 3,625
A0110 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2,
CLASS A STEEL POSTS (8'
POSTS) (NATINA) LNFT 840 35 875
A0120 61702-0000 TERMINAL SECTION (ANCHOR) EACH 1 1
A0130 61702-0300 TERMINAL SECTION, TYPE G4-BAT EACH 3 3
A0140 61702-0300 TERMINAL SECTION, TYPE G4-BAT
(NATINA) EACH 1 1
A0150 61702-1500 TERMINAL SECTION, TYPE MGS
TANGENT EACH 21 21
A0160 61702-1500 TERMINAL SECTION, TYPE MGS
TANGENT (NATINA) EACH 1 1
A0170 61702-1600 TERMINAL SECTION, TYPE MGS
FLARED EACH 11 11
A0180 61702-1600 TERMINAL SECTION, TYPE MGS
FLARED (NATINA) EACH 3 3
A0190 61707-1000 STRUCTURE TRANSITION RAILING,
G4 SYSTEM LNFT 20 20
A0200 61709-4000 REMOVE AND RESET, TERMINAL
SECTION EACH 1 1
A0210 62201-0850 WHEEL LOADER, 1 CUBIC YARD
MINIMUM RATED CAPACITY HOUR 20 20
A0220 62201-2100 COMPACTOR (JUMPING JACK) HOUR 40 40
A0230 62201-2750 MOTOR GRADER HOUR 20 20
A0240 62301-0000 GENERAL LABOR HOUR 40 40
A0250 63501-0000 TEMPORARY TRAFFIC CONTROL LPSM All ALL
MileStone: Final Date Completed: In Progress Report Date: 10/23/18
A M E N D
Line Item No.
Pay Item Number
SUMMARY OF QUANTITIES - Schedule A
-O ct
-2
:3
A M
Remarks and/or Determination of Estimated QuantityPay Item Description Unit
Estimated Quantities
C
U se rs \l ot se
.t ow ns en d\ D es kt op
B 1_
JO
S
EP
H
.x ls m ]S he et
STATE PROJECT
B.1JOSEPH 2401(2)OR
SHEET
NUMBER
Revised By Amendment A002
QUANTITIES (1 of 2)
TABULATION OF C-SHEET
C.1
STATE PROJECT
NUMBER
SHEET
U
S S u r ft
D c m y fi le s p w p r o d u c ti o n d o r a c a .d g n
OR JOSEPH 2401(2)
P
M
O c to b e r
A
G u ti e r r e z
G
K r u m b in
C h e c k e d b y
D e s ig n e d b y
QUANTITIES (2 of 2)
TABULATION OF C-SHEET
Revised by Amendment A002
C.2
STATE PROJECT
NUMBER
SHEET
U
S S u r ft
D c m y fi le s p w p r o d u c ti o n d o r a c b .d g n
OR JOSEPH 2401(2)
P
M
O c to b e r
A
G u ti e r r z
G
K r u m b in
C h e c k e d b y
D e s ig n e d b y : 2
| AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT |
| A002 |
| Amd_Page_2_Master.pdf |
| BID SCHEDULE |
| CONTRACT CLAUSES |
File details come from the government source that posted it.