OR JOSEPH 2401(2), Galice Road Improvements
Solicitation number
69056718B000022
Issued by

View the file

Other files

File Type Posted
BidSum_OR_Galice.pdf PDF
Q&A_10-24-18.pdf PDF
Q&A_10-24-18.pdf PDF
A002_.pdf PDF
A001.pdf PDF
Q&A_10-18-18.pdf PDF
Plan_Request_Form_Galice_Rd.pdf PDF
Galice_Rd_Plan_Set_Sign_Off.pdf PDF
IFB_Galice.pdf PDF
PROJECT_DESCRIPTION_Galice.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OR JOSEPH 2401(2)

Galice Road Improvements

# General Technical Question Answer Date

1 x The guardrail run at MP 5.29 appears to be incorrect. It shows removing 636 LF and installing 1225 LF with a buried terminal, Tangent Terminal, and a transition. How is this possible? And in order to get 1225 LF you would be installing guardrail in front of an existing rock wall.

Run 005 removes the existing 636’ of guardrail and replaces that. The run is then extended in front of the short rock wall until meeting the BLM lookout area where a tangent terminal is placed near the southeast end of the lookout so that pedestrian access can be maintained from the lookout in between the new guardrail and existing short rock wall. The lateral offset to the guardrail face in the short rock wall section should be 2’. The east end of the run is a buried in backslope terminal near the small pullout. This buried in backslope terminal would then use standard drawing 617‐39 where appropriate at the west end of the terminal to transition the G4 height to MGS for the remainder of the run.An Amendment will be issued addressing plan quantities.

10/17/18

Check General or Technical

2 Why at MP 5.29 to MP 6.23 are you switching the guardrail to Natina Stained instead of corten? Natina is a very expensive process.

FHWA does not recommend Corten weathering steel unless the maintaining agency has an inspection process in place to monitor deterioration over time. In order to satisfy the desired aesthetic look in this area in conjunction with the BLM lookout, a weathering agent such as Natina was chosen as the best long‐term option.

10/17/18

3 The actual mileposts on this road are different then your plans. It appears your intent is to install guardrail in front of rock cuts and various areas.

Is that your intent?

The contract mileposts are based on the line shown on sheet A.3.

10/17/18

4 No utilities are shown or indicated in the plans.

What is their involvement in the project? Are they a conflict? Will they be moved?

Utilities were not identified. Please refer to requirements is Section 107.

10/17/18

5 x The guardrail transition at MP 5.57 is at a rock wall, and it is on a radius. These transitions are intended to be installed on a tangent. Will there be any radius numbers available for this area?

The guardrail transition at MP 5.57 is at a rock wall, and it is on a radius. These transitions are intended to be installed on a tangent. Will there be any radius numbers available for this area?

10/17/18

6 x Regarding Pay Items A0070, A0210, A0220, A0230 & A0240: The contract provisions (622.01 Rental Equipment) state that “ This work consists of furnishing and operating equipment for the construction work as ordered by the CO and listed below. Work under this section does not include equipment time used to perform work provided for under any other pay item shown in the bid schedule. The work anticipated under this section includes: shoulder reconditioning.” Shoulder reconditioning is pay item A0070. The contract provisions (617.06 Terminal Sections) state “perform and necessary grading required to install terminals as required on the standard drawings under sections 622 and 623” Was it intended for the terminal grading to be paid for under section

622.01 and not the shoulder reconditioning since there is an existing pay item (A0070) for the shoulder reconditioning already? If in fact section 622 & 623 are intended for the terminal grading how would and additional aggregate that could be required to build the terminal pads be paid for?

An amendment will be issued to address your questions. Required aggregate base is not measured for payment.

10/17/2018

7 X Stationing where the shoulder reconditioning is to happen

Shoulder reconditioning has not been defined by stationing, but will be required as described in Special Contract Requirements. The contractor is encouraged to visit the site prior to bidding.

10/19/2018

8 X Spec states that if the shoulder is soft, we are to subexcavate and repair. It is unknown how deep, how many square feet, and what we are to use to repair. A typical detail, and a quantity is needed.

303.04 requires surface course aggregate as backfill compacted according to 301.05 .

There is no specific detail.

10/19/2018

9 X A government furnished disposal site, for disposal of the excavated spoils, debris, etc. that is supposed to result from this work. According to the specials, any disposal site we come up with, must go through what amounts to months of permitting, therefore precluding us providing a disposal site

There is no government furnished disposal site. Dispose according to 203.05(a). Please see the requirements of 203.05(a) and 105.02(c) Contractor‐located sources, for requirements including the use of commercial sources.

10/19/2018

10 X A typical detail showing how wide and how deep that rock is desired on the shoulder reconditioning. This will also allow us to calculate spoils offhaul to the above waste site.

The Typical sections in the Plans indicate shoulder reconditioning as required (C.3).

The contractor is encouraged to visit the site.

10/19/2018

11 X A bid item for the aforementioned rock, by the ton.

There is no bid item for rock and payment for such work is indirectly included under other pay items

10/19/2018

12 X If shoulder reconditioning and earthwork is desired at the guardrail terminal ends, we need a detail of what that should look like, and a quantity per each, so that we can estimate the export and import, as above.

Terminal grading is required per the applicable standard drawings in the Plans.

Sections 622 and 623 are to be used for equipment and labor needed to meet terminal grading requirements.

10/19/2018

13 X There is a quantity of 50 feet listed in the bid schedule but I only see a quantity of 25 feet in the plans. (12.5 LF at location 5 and 12.5 LF at location 6

Please see Amendment A002. 10/15/2018

14 X In the bid schedule that item is listed only as structure transition railing, in the plans it is called structure transition railing (Natina)

This structure transition railing will be Natina stained as well as indicated on C.1.

10/15/2018

15 X What is the transition railing connecting to? I see only the existing rock wall / railing at those locations which would not be suitable for the connections as shown on page C‐10 of the plans.

The structure transition railing connects to the existing rock wall at the BLM turnout.

Preliminary measurements in the field indicate the approximately 20’ transition will fit on a tangent connected to a curved G4 panel (or multiple as needed). The run would then immediately transition to MGS from the G4 height once in line with the roadway headed northwest. No major

10/15/2018

16 X Will concrete walls need to be built and if so how will they be paid for? And if so we would need construction details to bid correctly.

No, see above response. 10/15/2018

17 X No survey work is shown on the bid schedule.

How is this work to be paid for?

Please see SCR 109.05(b) Indirect payment.

Work for which direct payment is not provided is a subsidiary obligation of the Contractor.

10/18/2018

18 X No radius information for the guardrail is shown. Does the FHWA have a list of potential radiuses to be used on this project?

No. The bidders are responsible for estimating curved guardrail panels throughout the project, whether shop bent or field bent.

10/18/2018

19 X Bid item A0120 terminal section anchor doesn’t identify what kind is being used here. Is it a type 1 or type 1 modified? Is there a separate pay item for the end pcs?

This bid item is associated with the detail on C.14 and is based on ODOT Standard Drawing RD450.

10/18/2018

20 X Our previous question regarding the transition at MP 5.57 was not answered. Is the FHWA intent to radius the transitions? If so what is the radius?

Preliminary measurements in the field indicate the approximately 20’ transition will fit on a tangent connected to a curved G4 panel (or multiple as needed). The run would then immediately transition to MGS from the G4 height once in line with the roadway headed northwest. If needed, using a curved panel for the “Single W beam rail element” as shown on standard drawing 617‐26 may be acceptable as well to help make the turn. The bidders are responsible for estimating curved guardrail panels throughout the project, whether shop bent or field bent.