This document is an Addendum to Invitation to Bid (ITB) Number 6829 OF issued by the State of Nebraska, Department of Administrative Services (DAS), Materiel Division, State Purchasing Bureau (SPB) for a Traffic Classification Camera System. The addendum provides answers to questions submitted by potential bidders. The key details include: Bidders should provide an itemized breakdown of pricing for hardware, service, and warranty; the goal is to implement the project in Q1 2024; and the camera distance range can be set from 25 to 35 feet from the edge of the first lane to accommodate both AC-powered and solar-powered systems.

The solicitation is for a commodity contract, and the resulting contract may not be exclusive as the State reserves the right to contract for the same or similar goods from other sources. Pricing terms, set-asides, incumbents, funding requirements, and other salient information were not provided in the document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM ONE

QUESTIONS and ANSWERS

6829 OF

Date: 11/14/23

To: All Bidders

From: Brenda Sensibaugh, Procurement Contracts Officer AS Materiel State Purchasing Bureau (SPB)

RE: Addendum for Invitation to Bid (ITB) Number 6829 OF for Traffic Classification Camera System to be opened on November 29, 2023 at 2:00 p.m. Central Time

Following are the questions submitted and answers provided for the above-mentioned ITB. The questions and answers are to be considered as part of the ITB.

It is the Bidder’s responsibility to check the SPB website for all Addenda or Amendments.

Question Number

ITB

Section

Reference

ITB

Page

Number

Question State Response

1 S,1 6 How should vendors submit pricing for this bid? Should we provide an itemized breakdown and should it include items such as hardware, service, and warranty?

Please provide an itemized breakdown, and include items such as hardware, service, warranty, etc.

2 What is the expected timeline for implementation of this project? Can we expect it Q1 of 2024, Q2 of 2024, or some other date?

The goal is to implement Q1 of 2024.

3 D Camera distance set at 35 ft from the edge of first lane, Camera height set at 30 ft from ground level. IR light set at 18 ft high. Traffic Classification Cameras for use on bi-direct.

While the our AC based system is optimize at 30 to 35 ft from the edge of first lane, for solar based system, 25 ft from the edge of first lane would provide better performance.

Could we set the range from 25 to 35 to cover different systems?

Yes, but list both systems (AC and solar) as separate options, then note the distance range for each power option.

This Addendum will become part of the ITB and should be acknowledged with the ITB.