This is a Logging Systems Layout Worksheet template used to document the planning and design of logging operations for a harvest unit. The worksheet captures comprehensive information about a proposed timber harvest project, including project identification, resource constraints, infrastructure requirements, and operational specifications.
The form requires documentation of improvements (survey monuments, fences, and other structures), resources (streams with buffer zones, wet areas, wildlife habitat, and special management areas), and road systems (haul routes, new or reconstruction needs, and temporary access roads). Section C details the preferred logging method—skyline, cut-to-length (CTL), or tractor systems—along with specific parameters including uphill and downhill skidding percentages, maximum yarding distances, average slope, and the number and location of landings. The worksheet also requires documentation of special conditions that may affect logging difficulty, such as rocky ground or areas that must be dropped from the harvest unit. An attached map must illustrate unit boundaries, excluded areas, skidding directions, go-back trails, directional falling requirements, hand-falling areas, and excavated skid trail locations. The completed worksheet must be signed by both the person preparing the layout and the layout personnel conducting the field work, with references to township, range, and section information for geographic identification.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date_____________ Name____Names or Names of layout personnel
LOGGING SYSTEMS LAYOUT WORKSHEET
Project or Sale Name________Example: Buck Mountain___________________
Harvest Unit # _____ ____
GPS Acres __________
Rx _____NOT REQUIRED_____
A. IMPROVEMENTS:
Survey Monuments, Posts, or Signs Note any located in or on boundary of unit, also show location on map __
Fences Note any located in or on boundary of unit, also show location on map
Other __Any other improvements located in or on boundary of unit
B. RESOURCES:
Streams ____Note the category of stream buffered with feet and show location on map (Example: Buffered Category 3 _intermittent_150’ on east boundary of unit)
No Cut Wet Areas Note any located in or on boundary of unit, also show location on map (Example: Two wet areas; 1 wet area buffered inside unit, one just outside boundary by SW corner.
No Cut – Other (SMA, etc.) Note any located in or on boundary of unit, also note the type and show location on map.
Example: 1 No Cut buffered inside unit due to steep slopes)
Wildlife Note any buffered during layout (Example: Elk Wallow buffered on west edge of unit)
Roads:
Haul Route Existing System Road#__List roads from unit to main highway of sale________________________________________________________________________
New or Reconstruction Specified Length ___Note if reconstruction is needed on any existing system roads
New Temporary Length (feet)________Note length of new temporary road and show location on map
Existing Temporary Length (feet) _Note any found and show location on map
Culvert (size, length, amount) NOT APPLICABLE Station___ NOT APPLICABLE
C. LOGGING METHOD (Preferred): (Skyline, CTL, Tractor) ______________________________________________________ Logging System Specifics
Average Percentage Uphill Skidding _Example: 20%_ Maximum Skidding/Yarding Distance _in feet
Average Percentage Downhill Skidding Example: 80%_ Average Skidding/Yarding Distance _in feet
Average Slope Average slope of unit Number of Landings (Show location on map) _See layout guide for landing requirements
Profiles NOT REQUIRED
Unit_________
Special or additional information _Document why areas were dropped, any locations that may make logging difficult, (ie rocky ground) ________________________________________________________________________ _________________
D. OTHER COMMENTS
E. MAP:
Township Date Range Prepared by:
Section(s) Layout by:
Unit_________
Attach Map with required information.
Draw/Map the following:
Note reasons why areas are dropped on map, skidding direction, required go back trails, directional falling, areas that may require hand falling, areas of needed excavated skid trail and any other pertinent information. (See example below)