About this file
This is a Request for Proposal (RFP) issued by Timpanogos School District for Construction Manager/General Contractor (CM/GC) services for a new District Office facility in Lindon, Utah. The project involves construction of approximately 22,000 square feet on an undeveloped 1-acre portion of an existing district site. Proposals are due electronically through the Utah Public Procurement Place (UPPP) by 2:00 p.m. Mountain Time on Thursday, July 30, 2026. Construction is projected to commence in October 2026 with completion targeted for June 2027. The CM/GC work consists of two phases: pre-construction (including design meetings, cost estimation, schedule development, and constructability reviews) and construction (furnishing and installing all required work). The contract will remain in effect for the duration of the project, with work potentially bid in multiple packages such as excavation, footings, foundations, and structural steel.
The Fixed Limit of Construction Cost (FLCC) for the project is $8,000,000. The fee proposal must include: a lump-sum pre-construction fee, a lump-sum construction management fee, monthly construction supervision costs, costs for payment and performance bonds, contractor change order markups (capped at 5% for work up to $50,000 and 3% for work exceeding $50,000), and self-performed work markups (capped at 15% for work up to $50,000 and 10% for work exceeding $50,000). Evaluation criteria are weighted at 200 points for technical components, including contractor team strength (60 points), past performance (100 points), and management and safety plan approach (100 points), with the final 100 points allocated to the fee proposal. The contract may be canceled with 60 days' notice due to lack of funding or poor performance. All CM/GC firms and their subcontractors must comply with Utah licensure laws and provide proof of valid Utah contractor's licenses at submission.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-TIMP TERMS AND CONDITIONS ASD 5.9.25.pdf | ||
| 2-Confidentiality Claim Form.pdf | ||
| 3-CMGC+Required+Schedules+A-E+(2026) TSD.docx | DOCX document | |
| 4-Vendor Prerequisites for RFP TIMP.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
490 N State Street, Lindon, UT, 84042 | Phone (385)579-5000
Request for Proposal Construction Manager/General Contractor (CM/GC) for New TSD District Office
July 2026
Solicitation #TSD07302026
Timpanogos School District RFP for CM/GC (New TSD District Office) #TSD07302026 P 1 of 7
INTRODUCTION
Pursuant to Utah Procurement Code 63g-6a and Administrative Rule 33, Timpanogos School District finds that using a Construction Manager/General Contractor (CM/GC) for this project is in the best interest of the district because a CM/GC will be accessible early in the cost-effective design of the building. This request for proposals (RFP) seeks qualified firms, licensed and certified as applicable in the State of Utah, to construct a new district office in Lindon, Utah.
SUBMITTAL DEADLINE
Submissions will be accepted electronically through the Utah Public Procurement Place (UPPP).
RFP DUE DATE: 2:00 p.m. MT, Thursday, July 30th, 2026 RFP's received after the deadline will be late and ineligible for consideration.
Submittals should be concise and address the specific items listed on UPPP and in this packet.
DESCRIPTION OF WORK
The CM/GC must be capable of and willing to work closely with Timpanogos School District representatives and the selected architect, through the design phase, providing cost estimates, schedules, and feedback on design details, phasing, and availability of materials selected.
The new building will be approximately 22,000 square feet on an undeveloped portion (approximately 1 acre) of an existing district site located in Lindon, Utah. Construction is projected to start in October 2026, and the project is to be completed in June 2027. The Fixed Limit of Construction Cost (FLCC) for the CM/GC is 8,000,000.
CM/GC WORK PHASES
The CM/CG work for the project consists of two (2) phases: pre-construction and construction.
Pre-construction Phase: This phase of the work includes, but is not limited to, attending design meetings, estimating and cost control, schedule development, and drawing/constructability reviews. The construction manager shall provide a full construction estimate prior to bidding the project to subcontractors. The construction manager shall monitor the bid climate, make recommendations to the design team for the most advantageous bidding time, and then solicit bids from subcontractors.
Construction Phase: This phase of the work consists of the contractor furnishing and installing all work as required in the contract documents. Please note that Work of the Construction Phase may be bid in several packages, such as excavation, footings, foundations, structural steel, etc.
FLCC AND GMP
A. FLCC: The Fixed Limit of Construction Cost, or FLCC, is the project’s construction budget as listed in the Notice to Contractors and this RFP’s Description of Work section. The Owner, the design team, and the CM/GC Contractor agree to work together to keep the cost of construction, as represented in the design, within the FLCC.
B. Guaranteed Maximum Price (GMP): The guaranteed Maximum Price is the final price that the contractor agrees to accept in full performance of the attached Construction Manager/General Contractor Agreement (CM/CG Agreement) and is based on the final contract drawings and specifications. The GMP shall include all fees and percentages required by the RFP, as well as the costs for General Conditions and all work as required in the Contract Documents.
Please note that should the work be completed in project phases and bid packages, the successful contractor will be required to submit a GMP for each of these phases and packages of the work. The sum or total of all the GMP’s for these phases of the work, shall be the final GMP. In addition to the Pre-construction Fee, all other GMP’s for the phases of the work shall become part of the CM/GC Agreement by contract modification. The final GMP will be determined at the completion of the contract documents and upon receipt of the subcontractor’s bid. The contract may be canceled upon giving a sixty (60) day notice due to lack of funding or poor performance.
SUBMITTAL INFORMATION REQUIREMENTS
(Please respond to each of the items below and provide a tab for each schedule requiring submittal information in the order listed) (Responses shall be brief and limited to (50) fifty pages, the cover and tabs will not be counted towards the page limit).
A. SCHEDULE ‘A’ – Certification of Proposal. The District’s Certification of Proposal form completed and signed. (See attached schedule ‘A’)
B. SCHEDULE ‘B’ – CM/GC Firm’s Statement of Experience/Qualifications
1. Experience and qualifications of the CM/GC and the project team key individuals as identified in the management plan. Include a description of each member of the team; including qualifications and experience. Project team members shall be agreed upon between the CM/GC and Timpanogos School District prior to entering into a contract. This team shall not be changed throughout the project unless agreed upon by both the CM/GC and Timpanogos School District. Failure to adhere to this may be grounds for termination of the contract. Enter on the Fee Breakdown form the name of the project manager and superintendent you intend to assign to the job.
2. Similar projects that have been completed by the CM/GC and the project team. When listing similar projects, include information to indicate the dates, size, firm worked for at the time and what the responsibility of each individual was on the project. Include projects that involved the use of tilt-up concrete panels, and any relevant information regarding the construction of these projects. Include projects with a minimum of three (3) references from the past three (3) years, including Company name, Contact name, phone number and email address, etc.
3. Experience and special qualifications of the team that are applicable to this project(s) and/or are part of the project-specific selection criteria.
4. All firms or individuals your company anticipates utilizing to provide surveying, engineering, and any other necessary professional services.
5. Ability to perform services as reflected by workload and the availability of adequate personnel, equipment, and facilities to perform the services expeditiously.
6. Present level of professional liability insurance coverage for the firm, including errors and omissions insurance.
7. Any litigation, arbitration, or other alternative dispute resolution proceedings your firm has been involved in with an owner within the past ten years.
8. Other pertinent information regarding qualifications and performance data that may be requested by Timpanogos School District.
C. SCHEDULE ‘C’ – Management Plan/Safety Plan
1. How the construction of the project, will be managed, including items such as security and safety controls, and coordination with Timpanogos School District.
2. Include a description of the company’s safety plan and a safety plan for this particular project per Utah Procurement Code 63g-6a-703.2.e
3. A proposed construction schedule.
4. Project-specific criteria; risks that have been identified from the RFP, additional risks that the team has identified for each project, and how those risks will be mitigated.
D. SCHEDULE ‘D’ – Licensure
1. CM/GC firms and their employees shall comply with, and require all of their subcontractor’s employees to comply with, the licensure laws of the State of Utah. All RFPs must include proof of a valid Utah contractor’s license at the time of submission.
E. SCHEDULE ‘E’ – Fee Proposal, GMP
All contractors shall furnish the following fees and markups as part of the cost proposal:
a. Pre-Construction Fee: This lump sum fee consists of all costs for the CM/CG to provide the required services of the Pre-construction phase, except pre-authorized, out-of-state travel. No other reimbursable costs will be allowed or considered in addition to this fee.
b. Construction Management Fee: This lump sum fee shall consist of and include overhead (e.g., home office), profit, and home office personnel who will be managing the project during bidding, construction, and closeout, including the warranty period. The fee does not include General Conditions.
c. Construction Supervision Cost: This is a per month cost to the project from notice to proceed to final completion for the CM/CG’s on-site management/supervision team (e.g., project manager, superintendent, etc.). All services and personnel not specifically identified as a Construction Supervision Cost will be part of the lump sum Construction Management Fee. This includes receptionists, Timpanogos School District RFP for CM/GC (New TSD District Office) #TSD07302026
P 4 of 7 accountants, safety officers, expediters, commissioning agents, etc. This cost does not include general conditions or people performing the actual construction activities.
d. Costs of Bonds: This is the cost of payment and performance bonds based on an amount equal to 100% of the FLCC amount.
e. Contractor Change Order Markup: This is the fixed percentage markup that the Contractor may apply to a change order for scope increase to the CM/CG Agreement. The markup shall replace the percentages indicated elsewhere in the construction documents and shall apply to sub-contractors.
f. Self-Performed Work Markup: This is the fixed percentage markup that will be applied to the cost for the CM/CG’s actual labor plus burden cost, material costs, and equipment costs for self-performed work.
The contractor will be allowed to self-perform work. This work must be billed for at actual cost incurred, plus the self-performed work markup. Actual costs for self-performed work will be subject to audit. No billing rates will be allowed. The contractor must bid self-performed work against other sub-contractors. The contractor’s bid will then be evaluated by the owner and design consultant and must be determined to be the best value bid for the work to be awarded to the contractor. The cost of any work that is self- performed will be part of the established GMP. Sealed bids for self-performed work shall be submitted to the TSD Purchasing Department three (3) hours prior to the bid close time.
DISCUSSIONS WITH OFFERORS (ORAL PRESENTATION)
An oral presentation by the three (3) highest-ranking offerors to clarify and/or present their proposal may be required at the sole discretion of the district. However, the District may award a contract based on the initial proposals received without discussion with the offeror. If oral presentations are required, they will be scheduled after the submission of proposals. Oral presentations will be made at the Offerors expense.
EVALUATION CRITERIA
Weighted Criteria:
| 200pts |
| Strength of Contractor’s Team: |
60 Points – Project Team Experience: Show the overall experience of the project team in relation to projects of similar scope and cost.
40 Points – Project Manager Experience: Show the experience of past relevant projects. Consider availability, other current projects and percent of commitment, years of experience and years of experience with current company.
40 Points – Superintendent Experience: Show the experience of past relevant projects, availability, years of experience and years of experience with current company.
20 Points – Project Estimator Experience: Show the experience on relevant past projects, roles, availability, current assignments and percent of commitment.
40 Points – Experience of Additional Project Specific Team Members: Show experience with the unique requirements of the project.
| 100pts |
| Past performance: Each contractor will be given a past performance rating based on past projects with Timpanogos School District, or similar entities, and supplemented by references supplied by the contractor at the time the proposals are submitted. TSD reserves the right to contact other references and/or entities of the submitting firm that are not specifically included or listed in the RFP. |
| 100pts |
| Management and Safety Plan Approach: Each contractor will be rated on the items included in Schedule ‘C’ |
| 100pts |
| Fee Proposal: The contractor’s cost proposal will be considered with all other criteria to determine the ranking of the firm. |
The evaluation committee, for this RFP, will tally the final scores per criteria for each contractor. The contractor with the highest total technical and fee proposal points will represent the best value for the district and will be selected for the project.
490 N State Street, Lindon, UT, 84042 | Phone (385)579-5000
SCHEDULE ‘E’ - FEE PROPOSAL FORM
| Name of Bidder: |
| Date: |
| Phone: |
| Email: |
NEW DISTRICT OFFICE– CM/GC
A. Pre-construction Fee: For all work during the pre-construction period, I/we agree to perform for the lump sum of:
DOLLARS ($ )
(In case of discrepancy, written amount shall govern)
B. Construction Management Fee: For all work during the construction phase of the contract for the management of the project, I/we agree to perform for the lump sum of:
DOLLARS ($ )
(In case of discrepancy, written amount shall govern)
C. Construction Supervision Cost: For project supervision and support team costs not covered in the above management fee, I/we agree to perform for the sum of:
DOLLARS PER MONTH ($ /MONTH)
(In case of discrepancy, written amount shall govern)
D. Cost of Bonds: The cost of payment and performance bonds based on the amount of the FLCC.
DOLLARS ($ )
(In case of discrepancy, written amount shall govern)
E. Contractor Change Order Markup:
For all work added to the contract by change order up to $50,000, I/we agree to add not more than % to the subcontractor/supplier costs for the additional work, which is not to exceed 5%
For all work added to the contract by change order exceeding $50,000, I/we agree to add not more than % to the subcontractor/supplier costs for the additional work, which is not to exceed 3%
F. Self-Performed Work Markup:
For all self-performed work up to $50,000, I/we agree to add no more than % to our labor and material costs to perform the work, which is not to exceed 15%
For all self-performed work over $50,000, I/we agree to add no more than % to our labor and material costs to perform the work, which is not to exceed 10%
With the cooperation of TSD and the Design Consultant, the undersigned will continue to work with due diligence to provide a Guaranteed Maximum Price (GMP) within the FLCC
Authorized Signature: