5__02826_Fence_Drainage_Crossings_mvo.doc

DOC document 41 KB Posted

Attached to
SEVEN LAKES FENCE Federal contract opportunity
Solicitation number
140L6221R0048
Issued by
Department of the Interior Bureau of Land Management Wyoming Region

View the file

Other files for this federal contract opportunity

Other files attached to SEVEN LAKES FENCE, newest first.
File Type Posted
140L6221R0048_AMD_0001_QUESTION_AND_ANSWERS_0001.docx DOCX document
Sol_140L6221R0048_Amd_0001.pdf PDF
8_Work_Data_Sheet_wire_mvo.docx DOCX document
6__02827_fence_removal_mvo.docx DOCX document
Bid_Schedule.xlsx XLSX spreadsheet
1_SOW_mvo_KJP.docx DOCX document
Seven_Lakes_Fence_2021_Drawings.pdf PDF
4__02824_Wire_Fence_and_Gates_mvo.docx DOCX document
2__01009_general_mvo.docx DOCX document
3_01505__Mobilization_mvo.doc DOC document
Sol_140L6221R0048.pdf PDF
Seven_Lakes_Fence_Map__pipeline_and_rain_gauge.pdf PDF
7__Material_Specifications_mvo.doc DOC document
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAGE

SECTION 02826

FENCE-DRAINAGE CROSSINGS

PART 1: GENERAL

1.1

SUMMARY

A. Section Includes: Furnishing and installing drainage crossings at the locations shown on the drawings, or as staked in the field.

1.1

PROJECT/SITE CONDITIONS

A. Requirements: Access roads shall not be constructed along fence lines and to the construction site unless written approval is granted by the Contracting Officer. Cross country travel with wheeled or tracked vehicles shall be only to and along fence lines.

PART 2: PRODUCTS

2.1

MATERIALS

A. Wire Fence Materials: Shall be according to Section 02824 - Wire Fences and Gates and as shown on the drawings.

PART 3: EXECUTION

3.1

PREPARATION

A. Clearing: Clearing shall be limited to hand clearing. Only vegetation that interferes with the fence shall be removed. All debris shall be disposed of in the immediate vicinity.

3.2

INSTALLATION

A. Type A: Construct Type A drainage crossings as shown on the drawings, with an auxiliary fence of wire, rock weights, and posts constructed under and independent of the main fence, so that when the crossing washes out, the main fence will not be damaged.

PART 4: MEASUREMENT AND PAYMENT

4.1

METHOD OF MEASUREMENT

A. Units: The work described in this section will be measured and paid for as part of the fence and not a separate unit.

4.2

BASIS OF PAYMENT

A. Payment: Prices and payment will be full compensation for the work described in this section. Payment will be made under:

Pay Item

Pay Unit

Fence Construction

Linear Foot

END OF SECTION