- Contract number
- 26-557THA-ENGCO-P-96701
- Issued by
- Illinois
About this file
This document is Addendum No. 2 to Contract RR-25-4999 issued by the Illinois State Toll Highway Authority. The addendum was issued on March 23, 2026, and includes minutes and sign-in sheets from an Optional Pre-Bid Meeting held on March 5, 2026, as well as responses to requests for information from plan holders. The meeting was chaired by Linda Myers, Senior Contract Negotiator, and included representatives from Illinois Tollway Procurement, Engineering, Design Section Engineers (Orion Engineers), and related departments. The bid opening is scheduled for April 3, 2026, at 10:30 a.m. local time via electronic bidding through BidBuy, with the final deadline for plan holder questions set for March 13, 2026, at 2:00 p.m.
The contract covers bridge rehabilitation work on the Tri-State Tollway (I-294/I-94) Bridge over Waukegan Road in Cook County, Illinois. Work includes expansion joint gland replacement, structural precast prestressed concrete (PPC) beam repairs, cleaning and painting structural steel, bearing replacement, substructure repairs, slopewall repairs, concrete sealing, bridge drainage system cleaning, and maintenance of traffic operations. The project schedule includes an anticipated Notice-to-Proceed on June 15, 2026, with a Substantial Completion Date of November 30, 2026, and a Contract Completion Date of December 31, 2026. Compliance requirements include a 13% Disadvantaged Business Enterprise (DBE) program goal, 3.0% Veteran-Owned Small Business (VOSB) goal, and Equal Employment Opportunity (EEO) workforce targets of 19.6% minority and 6.9% female participation. Bidders seeking a 4% Illinois Business Bid Preference must submit the Illinois Business Bid Preference Affidavit at the time of bid. Cooperation with the Illinois Department of Transportation, Cook County Department of Transportation and Highways, Union Pacific Railroad, and the Metropolitan Water Reclamation District is required.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Illinois State Toll Highway Authority Contract No. RR-25-4999 Addendum 2 Page 1 of 1 3/23/2026
ADDENDUM NO. 2
TO
CONTRACT REQUIREMENTS
FOR CONTRACT RR-25-4999
ILLINOIS STATE TOLL HIGHWAY AUTHORITY
Date: 3/23/2026
For which bids will be received by the Illinois State Toll Highway Authority through electronic bidding via BidBuy until 10:30:00 A.M. local time, April 3, 2026
NOTICE OF REVISION TO CONTRACT
NOTES:
1. The minutes and sign-in sheet from the Optional Pre-Bid Meeting held on March 5, 2026 are included in this
Addendum.
2. Responses to Request for Information received from the Plan Holders are included in this Addendum.
END OF ADDENDUM CHANGES
Addendum 2 1 of 4 3/23/2026
Capital Program
PRE-BID MEETING AGENDA
MEETING PURPOSE: Optional Pre-Bid Meeting - Contract RR-25-4984
MEETING DATE: March 5, 2026
MEETING TIME: 2:00 p.m.
CHAIRPERSON: Linda Myers – Senior Contract Negotiator
LOCATION: Illinois Tollway Microsoft TEAMS
TO:
Names Initials Organization / Title
Eric Occomy EO Procurement / Chief of Contract Services Maria Campuzano MC Procurement/Deputy Chief of Procurement Lindia Myers LM Procurement/Senior Contract Negotiator Morgan Coppola MC Procurement / Contract Analyst Susan Garcia SG Procurement / Contract Compliance Timothy Coleman TC Procurement / Diversity AJ Pebler AP Engineering / Project Manager Lukas Janulis LJ DSE / Orion Engineers
TOPICS DISCUSSED:
1.0 Open: Welcome; Self-introduction by Procurement Representative
2.0 Introduction of Presenters
2.1 Tollway Procurement – Contract Services – Kathi Hacking
2.2 Tollway Procurement – Contract Compliance – Yolanda Ramirez
2.3 Tollway Diversity – Timothy Coleman
2.4 Tollway Engineering Project Manager – AJ Pebler
2.5 Design Section Engineers – Lukas Janulis
3.0 Brief Project Description
3.1 The location of the services to be performed for this contract is Cook County in Illinois.
The work under this contract includes, but is not limited to, expansion joint gland replacement, structural PPC beam repairs, cleaning and painting structural steel, and bearing replacement. substructure repairs, slopewall repairs, concrete sealing, and cleaning of the existing bridge drainage system. maintenance of traffic operations,
4.0 Advertisement Schedules
4.1 Plan Holder questions should be provided 9241D.4999_Questions@docs.e-builder.net as identified on Page A-1
Addendum 2 2 of 4 3/23/2026
Capital Program
PRE-BID MEETING AGENDA
4.2 Final Date for Plan Holder Questions – March 13, at 2:00 pm
4.3 Bid Opening Date – April 3, 10:30 a.m. local time.
4.4 System will not accept late bid submittals.
4.5 Please note that in accordance with the R pages of the Illinois Tollway Bid Requirements and section 45-105 of the Illinois Procurement Code (30 ILCS 500/45-105), the bidder or contractor must submit at the time of bid the Illinois Business Bid Preference Affidavit and any other supporting documents demonstrating that the bidder or contractor is an Illinois business at the time of bid in order to be eligible for a 4% bid preference.
5.0 Compliance Goals
5.1 Disadvantaged Business Enterprise Program (DBE) – 13%
5.2 Veteran-Owned Small Business Program (VOSB) – 3.0%
5.3 Workforce
5.3.1 Equal Employment Opportunity (EEO)
Minority (19.6%) Female (6.9%)
6.0 Diversity Programs – Overview of Available Programs
6.1 Earned Credit Program (ECP) Bid Credit Cap
6.2 Technical Assistance Program
6.3 Partnering for Growth (P4G)
6.4 Construction Works
7.0 Risk Management (by Risk Insurance Representative)
Addendum 2 3 of 4 3/23/2026
Capital Program
PRE-BID MEETING AGENDA
8.0 Project Schedule
8.1 S.P. 104 Anticipated Notice-to-Proceed – June 15,2026
8.2 S.P. 103.2 Substantial Completion Date – November 30, 2026
8.3 S.P. 103.1 Contract Completion Date – December 31, 2026
9.0 Special Items to Note
9.1 Cooperation with other agencies is required. Please review the S. P. 106.
9.1.1 Illinois Department of Transportation
9.1.2 The Cook County Department of Transportation and Highways
9.1.3 Union Pacific Railroad
9.1.4 Metropolitan Water Reclamation District
10.0 Responses to Plan Holder Questions
10.1 Questions received to date
10.2 Anticipated Addendum 2 targeted for week of March 27, 2026
11.0 Questions
Addendum 2 Page 4 of 4 3/23/2026
Addendum 2 Page 1 of 1 3/23/2026
CONTRACT RR-25-4999
ILLINOIS STATE TOLL HIGHWAY AUTHORITY
RESPONSES TO REQUEST FOR INFORMATION
QUESTION 1
Can the traffic control equipment stay up overnight up top on Waukegan Road?
RESPONSE 1
The traffic control equipment along the topside of Waukegan Rd Bridge is to perform the work associated with bridge joint gland replacement as well as to minimize the live load during the bearing replacement work below the bridge deck. The joint work is short term (less than 1 day) after which the barrels/cones will be pulled back behind the lane line and will remain in place for the bearing replacement. No equipment of personnel is expected to be present on the topside of Waukegan Rd during bearing replacement operations, and the bearing replacement is estimated to be completed in 4-5 days after which all MOT devices must be removed.