RFP_47PL0218R0003_JFB&FOB_O&M_Pkg.pdf
PDF 4 MB Posted
- Attached to
- O&M Services for JFB & FOB Federal contract opportunity
- Solicitation number
- 47PL0218R0003
About this file
RFP 47PL0218R0003 Package
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30-Amendment_0005.pdf | ||
| SF30-Amendment_0004.pdf | ||
| RFP_47PL0218R0003_Amendment_0003.zip | ZIP file | |
| RFP_47PL0218R0003_Amendment_0002.zip | ZIP file | |
| SF30-Amendment_0001.pdf | ||
| Section_J_-_Exhibits.zip | ZIP file | |
| Section_J_-_Attachments.zip | ZIP file |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THIS PROCUREMENT IS A TOTAL SMALL BUSINESS SET ASIDE.
SOLICITATION NO: 47PL0218R0003
PROJECT: Operations &Maintenance Services
LOCATIONS:
Jackson Federal Building (JFB)
915 2 nd
Ave, Seattle, WA 98174
Federal Office Building (FOB)
901 1 st Ave, Seattle, WA 98174
PERIOD OF PERFORMANCE:
May 1, 2018 – November 30, 2018 ( Seven months) WITH
FOUR (4) ONE-YEAR OPTIONS
SOLICITATION ISSUE DATE: February 7, 2018
PROPOSAL DUE DATE/TIME: March 2, 2018 / 4:00 PM Pacific Time
NOTE: ANY QUESTIONS REGARDING THIS SOLICITATION MAY BE DIRECTED TO:
GENERAL SERVICES ADMINISTRATION
ACQUISITION MANAGEMENT DIVISION
SERVICES ACQUISITION BRANCH (10PQD)
400 15TH STREET SW
AUBURN, WASHINGTON 98001-6599
Mr. Min Kim Mr. Michael Metje
Contract Specialist Supervisory Contracting Officer
(253) 931-7081 (253) 931-7456 min.kim@gsa.gov michael.metje@gsa.gov
A pre-proposal conference WITH site visit is scheduled for February 14, 2018 @ 10:00 AM
PST. The conference will be conducted by meeting at the JFB in Seattle, WA on Fourth Floor
Room 414 with a site walk through to follow at both JFB and FOB. Please RSVP by email at:
min.kim@gsa.gov and/or michael.metje@gsa.gov by no later than February 13, 2018 @ 4:00
PM PT. All participants are responsible for their own transportation to the conference and between building sites. T
JFB & FOB O&M Services mailto:min.kim@gsa.gov mailto:michael.metje@gsa.gov mailto:min.kim@gsa.gov mailto:michael.metje@gsa.gov
SIGNIFICANT DATES
DATE ISSUE TIME
Wednesday - 2.7.2018 RFP posted to FedBizOps
Tuesday - 2.13.2018 RSVP due for Walk-Through 1000 hrs / 10AM PT
Wednesday - 2.14.2018 Site visit & pre-proposal
Conference 1000 hrs / 10AM PT
Monday - 2.19.2018 Final day for questions 1500 hrs / 3PM PT
Friday - 2.23.2018 Final answers posted 1500 hrs / 3PM PT
Friday - 3.2.2018 RFP Closes 1600 hrs / 4PM PT
CONTACT INFORMATION (SF1449 - block 7)
Point of Contact: Mr. Min Kim, Contract Specialist
Email: min.kim@gsa.gov
Office Phone: 253-931-7081
Cell Phone: 253-256-9666
Alternate Point of Contact: Michael Metje, Contracting Officer
Email: michael.metje@gsa.gov
Office Phone: 253-931-7456
Cell Phone: 253-326-1653
RFP TABLE OF CONTENTS
(Sections A through M)
A. SOLICITATION/CONTRACT FORM
A.1 FORMS
A.1.1 Standard Form 1449 Solicitation/Contract/Order for Commercial Items –
Attachment 1
A.1.2 Addendum to Standard Form 1449 – Attachment 1
A.1.3 Vendor Validation Information Form – Attachment 2
B. SERVICES, ORDERING AND PRICES
B.1 DESCRIPTION OF SERVICES
B.2 O&M RELATED SERVICES
B.3 REIMBURSABLE COSTS
B.4 OPTION YEARS
B.5 PRICING – ADDITIONAL SERVICES
C. DESCRIPTION/SPECIFICATION/PERFORMANCE WORK STATEMENT
INTRODUCTION
C.1 SCOPE OF WORK
C.1.1 Services
C.1.2 Responsibilities
C.1.3 Exclusions
C.2 DEFINITIONS
C.2.1 Acceptance C.2.2 Acts of God C.2.3 Additional Services C.2.4 Advanced Meters C.2.5 Advanced Metering Systems C.2.6 Approval C.2.7 Architectural and Structural C.2.8 Basic Services C.2.9 Building Automation System (BAS) C.2.10 GSALink C.2.11 Building Operating Plan C.2.12 Commissioning C.2.13 Ongoing Commissioning
C.2.14 National Computerized Maintenance Management System (NCMMS) C.2.15 Consumable Parts C.2.16 Contracting Officer (CO) C.2.17 Contracting Officer Representative (COR) or Designee C.2.18 Contractor C.2.19 Contractor’s Other Than Normal Working/Duty Hours C.2.20 Controls and Control System C.2.21 Defective Service C.2.22 Emergency C.2.23 Emergency Callback C.2.24 Environmentally Sustainable C.2.25 Existing Deficiency List Report C.2.26 Exterior C.2.27 Federal Holidays C.2.28 Federal Executive Holidays, Unanticipated C.2.29 Fire Protection and Life Systems C.2.30 Guiding Principles for Sustainable Existing Buildings C.2.31 GSA Green Purchasing Program (GPP) C.2.32 Indefinite Quantity
C.2.33 Miscellaneous Repair C.2.34 Miscellaneous Work C.2.35 Modification of Contract C.2.36 Negligence C.2.37 Non-reimbursable Repairs C.2.38 Normal Working Hours C.2.39 Occupant Emergency Plan (OEP) C.2.40 Open Systems C.2.41 Operations C.2.42 Performance Based Service Contracting C.2.43 Performance Work Statement (PWS) C.2.44 Predictive Maintenance C.2.45 Preventive Maintenance (Scheduled and Unscheduled) C.2.46 Product Preference C.2.47 Quality Assurance Surveillance Plan (QASP) C.2.48 Quality Control Plan C.2.49 Repair C.2.50 Reimbursable Repair C.2.51 Sequence of Operations C.2.52 Work Request / Work Order C.2.53 Standard Services C.2.54 Stewardship C.2.55 Supervisor, On-Site C.2.56 Tour C.2.57 Vertical Transportation Systems C.2.58 Watch
C.3 REFERENCES
C.4 EXISTING DEFICIENCY INSPECTION/INITIAL DEFICIENCY LIST
C.4.1 Initial Inspections C.4.2 Initial Deficiency List
C.5 START-UP PHASE/TRANSITION PHASE
C.5.1 Transition Phase Startup C.5.2 Startup Phase Schedule - Reserved C.5.3 Adjustments and Corrections
C.6 PHASEOUT TRANSITION PERIOD
C.7 DEFICIENCY LIST COMPLETION AND WITHHOLDING OF FINAL PAYMENT
C.8 GENERAL AND ADMINISTRATIVE REQUIREMENTS
C.8.1 Minimum Staffing C.8.2 Communication Equipment C.8.3 Onsite Records C.8.4 Work Request / Work Order and Administrative Support C.8.5 Use of NCMMS C.8.6 Quality Control Program C.8.7 Government Quality Assurance Surveillance Program
C.8.7.1 Contract Performance C.8.7.2 Methods C.8.7.3 Records and Files C.8.7.4 Cooperation – Inspections C.8.7.5 Contractor Performance System (CPARS)
C.9 BUILDING OPERATING PLAN
C.9.1 Building Operating Plan C.9.2 Components of the Building Operating Plan
C.10 EQUIPMENT INVENTORY
C.11 MONTHLY PROGRESS REPORTS
C.12 PERFORMANCE REVIEW MEETINGS
C.13 EQUIPMENT CONDITION ASSESSMENTS
C.14 OCCUPANT FEEDBACK PROGRAM
C.15 REFERENCE LIBRARY
C.16 REVIEW OF DESIGN DOCUMENTS
C.17 BUILDING MANAGEMENT AND SUPPORT SERVICES (MISCELLANEOUS AND
UTILITY ESCORT HOURS)
C.18 INSPECTIONS ASSISTANCE FOR SPACE BUILD OUTS
C.19 EMERGENCY SHUTDOWN INSTRUCTIONS AND TOUR CHECKLISTS
C.20 LABELING OF ELECTRICAL CIRCUITS
C.21 OPERATIONAL REQUIREMENTS
C.21.1 General C.21.2 Extended Operating Hours C.21.3 Continuity of Operations (COOP) C.21.4 Emergency Operations Plan C.21.5 Tenant Environment C.21.6 Energy and Water Efficiency
C.22 SYSTEM PERFORMANCE STANDARDS OR PROCEDURES
C.23 WORK REQUEST / WORK ORDERS
C.23.1 General C.23.2 Emergency Work Request / Work Order C.23.3 Emergency Call Back (after hours) C.23.4 Urgent Work Request / Work Order Response C.23.5 Routine Work Request / Work Order Response
C.24 TOURS
C.24.1 General C.24.2 Operating Logs and Tour Check Sheets C.24.3 Tour Frequencies C.24.4 Condensate Drip Pans C.24.5 Monitoring of Central Plant Equipment C.24.6 Leak Testing
C.24.7 Equipment Failure Reports
C.25 DEMAND RESPONSE PROGRAMS
C.26 CURTAILMENT PLAN - RESERVED
C.27 BAS ALARM RESPONSE
C.28 ADVANCED METERING PROGRAM
C.28.1 Verification and Calibration
C.29 PROTECTION AND DAMAGE
C.30 NEGLIGENCE
C.31 KEY CONTROL AND LOCKSMITH SERVICES
C.32 DISRUPTIVE OR HAZARDOUS TOOLS
C.33 SCHEDULED DISRUPTION TO UTILITIES, LIGHTING, FIRE PROTECTION & LIFE
SAFETY SYSTEMS, OR SPACE CONDITIONING
C.34 PLUMBING AND RESTROOMS
C.35 MAINTENANCE PROGRAM
C.35.1 General C.35.2 Maintenance Standard C.35.3 Application of Diagnostic Software C.35.4 BAS Control Systems
C.35.4.1 BAS Operating Standards
C.35.4.1.1 GSA-hosted Systems Requirements
C.35.4.1.2 Excepted Systems Requirements (not hosted on GSA’s system infrastructure)
C.35.4.2 Reporting
C.35.4.3 Staffing
C.35.5 Smart Building Technology - Reserved
C.35.6 Ongoing Commissioning/Re-Tuning - Reserved
C.35.7 Switchgear and Electrical Distribution Equipment
C.36 WATER TREATMENT
C.36.1 General C.36.2 Tolerances
C.36.3 Initial Report and Development of Program C.36.4 Cooling Tower Water Management Plan C.36.5 Corrosion Monitoring C.36.6 Monthly Testing
C.37 OIL ANALYSIS AND OIL CHANGES
C.37.1 Periodic Oil Analysis C.37.2 Oil and Refrigerant Additives C.37.3 Oil Changes
C.37.4 Generator Oil Testing
C.37.5 Diesel Fuels Level Checks and Testing
C.38 LAMPS AND BALLASTS
C.39 ARCHITECTURAL AND STRUCTURAL SYSTEMS MAINTENANCE
C.39.1 General
C.39.2 Maintenance Repair C.39.3 Repair and Replacement Work C.39.4 Painting C.39.5 Interior Signage and Directories C.39.6 Finishes Maintenance C.39.7 Historic Building Preservation C.39.8 Vertical Transportation and Associated Equipment C.39.9 Flag Procedures
C.40 REPAIRS
C.40.1 General C.40.2 Non-reimbursable Repairs C.40.3 Reimbursable Repairs C.40.4 Miscellaneous Work C.40.5 Repair Shared Liability Example C.40.6 Approval of Work C.40.7 Invoicing C.40.8 Ordering Repairs from Outside Source C.40.9 Force Majeure (Uncontrollable events) C.40.10 Warranties C.40.11 Quality of Materials and Replacement Parts
C.41 SAFETY & ENVIRONMENTAL MANAGEMENT
C.41.1 General C.41.2 Scheduling and Recordkeeping C.41.3 Refrigerant
C.41.3.1 Control and Certification C.41.3.2 Certified Handlers
C.41.4 Air Emissions C.41.4.1 Local Air Quality Management Operating Permits
C.41.5 Fuel Storage Tank Management
C.41.5.1. Underground Storage Tank Management
C.41.5.2 Above Ground Storage Tank Management
C.41.6 Solid Waste Audit - Reserved
C.41.7 Polychlorinated Biphenyl (PCB) Control - Reserved
C.41.8 Facility Hazards
C.41.9 Workplace Safety
C.41.10 Electrical Safety
C.41.11 Fall Protection
C.41.12 Powered Platforms
C.41.13 Lock Out/Tag Out
C.41.14 Confined Spaces
C.41.15 Asbestos Management
C.41.16 Hazardous Materials
C.41.16.1 Safety Data Sheet (SDS)
C.41.16.2 Disposition of Waste
C.41.16.2.1 Non-Hazardous Solid Waste
C.41.16.2.2 Universal Waste
C.41.16.2.3 PCB Wastes and Ballasts
C.41.16.2.4 Hazardous Waste
C.41.16.2.5 Recycling Hazardous Waste and Electronic Waste
C.41.16.2.6 Miscellaneous Hazardous Substance Disposal
C.41.16.2.7 Used Oil
C.41.16.3 Environmental Reporting
C.41.16.4 Sustainable Products and Reporting
C.41.16.4.1 Key Sustainable Product (KSP)
C.41.16.4.2 Proof of Compliance
C.41.16.4.3 Recycled Content Product Purchase Annual Reporting
C.41.16.4.4 Bio-Based Products
C.41.16.4.5 Green Cleaning Plan
C.41.17 Boiler/Pressure Vessel Operation and Inspection Standards
C.41.17.1 Boiler Operation and Inspection
C.41.17.2 Inspection and Test
C.41.18. Potable Water Systems
C.41.18.1 Use of Lead-Free Plumbing Materials
C.41.18.2 Potable Water System Disinfection
C.41.18.3 Backflow Prevention Devices
C.41.19 Labeling and Signage
C.41.20 Roof Anchorage Points
C.42 FIRE PROTECTION AND LIFE SAFETY EQUIPMENT AND SYSTEMS
C.42.1 General
C.42.2 Fire Alarm System Services
C.42.3 Water Based Fire Suppression System
C.42.4 Fire-rated Door Assemblies
C.42.5 Fire Damper and Combination Fire/Smoke Dampers
C.42.6 Smoke Doors Assemblies
C.42.7 Smoke Dampers
C.42.8 Portable Fire Extinguishers
C.42.9 Non-Water-Based Fire Extinguishing Systems
C.42.10 Smoke Control Systems
C.42.11 Emergency and Standby Power Systems
C.42.12 Emergency Lighting Systems and Exit Signage
C.43 MAINTENANCE AND REPAIR OF VERTICAL TRANSPORTATION SYSTEMS -
RESERVED
C.44 SUBMITTALS CHART (CONTRACTOR DELIVERABLES)
C.45 FEDERAL REQUIREMENTS
D. PACKAGING & MARKING
D.1 PAYMENT OF POSTAGE AND FEES
D.2 MARKING
E. INSPECTION & ACCEPTANCE
E.1 CLAUSES INCORPORATED BY REFERENCE
E.2 INSPECTION AND ACCEPTANCE
F. DELIVERIES OR PERFORMANCE
F.1 PLACE OF PERFORMANCE
F.2 TERM OF THE CONTRACT
F.3 DEFINITION FOR DAY
F.4 ORDERING PROCEDURES
F.5 TASK ORDERS OVER $2,500.00 ORDERING PROCESS
F.6 MICRO-PURCHASES UNDER $2,500.00 ORDERING PROCESS
F.7 MINOR ANCILLARY REPAIR & ALTERATION ORDERING PROCEDURES
F.8 FAR PART 51 SPECIAL ORDERING PROCEDURES
F.9 MODIFICATIONS
F.10 EXERCISING OF THE OPTION AND IDIQ ANNUAL REVIEW
F.11 CONTRACTOR PERFORMANCE EVALUATION
F.12 MINIMUM/MAXIMUM CONTRACT AMOUNTS
F.13 FEDERAL HOLIDAYS
G. CONTRACT ADMINISTRATION DATA
G.1 ACCOUNTING AND APPROPRIATION DATA
G.2 THE ROLE OF GOVERNMENT PERSONNEL AND RESPONSIBILITY FOR
CONTRACT ADMINISTRATION
G.2.1 IDIQ CONTRACTING OFFICER (CO)
G.2.2 IDIQ CONTRACT SPECIALIST (CS)
G.2.3 IDIQ CONTRACTING OFFICER’S REPRESENTATIVE (COR)
G.2.4 TASK ORDER ORDERING OFFICIALS
G.3 INVOICES
G.4 SUSPENSION OF WORK
G.5 EXCUSABLE DELAY
G.6 CANCELLATION OF CONTRACT
H. SPECIAL CONTRACT REQUIREMENTS
H.1. SECURITY
H.1.1 Security Requirements and Personal Identity Verification Procedures (Non-
Classified Contract)
H.1.2 GSAR 552.237-70 Qualification of Offerors (MAY 1989)
H.1.3 GSAR 552.237-71 Qualifications of Employees (MAY 1989)
H.1.4 Suitability Determinations
H.1.5 Compliance with Security Requirements
H.1.6 Safeguarding Sensitive Data and Information Technology Resources
H.2. IDENTIFICATION CREDENTIAL
H.3. ESCORT REQUIREMENTS
H.4. STANDARDS OF CONDUCT
H.5. REMOVAL FROM CONTRACT WORK
H.6. SENSITIVE BUT UNCLASSIFIED (SBU) BUILDING INFORMATION
H.7. RECORDING PRESENCE
H.8. GOVERNMENT FORMS
H.9. OTHER CONTRACTORS
H.10. ORDINANCES, TAXES, PERMITS AND LICENSES
H.11. DISCREPANCY IN THE SPECIFICATIONS
H.12. AFFIRMATIVE PROCUREMENT PROGRAM (APP)
H.12.1 Standards
H.12.1 Reporting
H.12.1 Recycle Content Certification
H.13. ASBESTOS AWARENESS TRAINING
H.14. UNIFORMS
H.15. PERSONNEL QUALIFICATIONS
H.15.1 Personnel Training
H.15.1.1 Re-Tuning Training
H.15.2 Qualifications of Project Manager and Onsite Supervisory Personnel H.15.2.1 Qualifications of Project Manager
H.15.2.2 Qualifications of Onsite Supervisor
H.15.3 Qualifications of Technicians
H.15.3.1 Qualifications of Fire Alarm System Technicians
H.15.3.2 Qualifications of Water-Based Fire Suppression System Technicians
H.15.3.3 Qualifications of Dry Chemical and Wet Chemical Extinguishing
System Technicians
H.15.3.4 Qualifications of Clean Agent Fire Extinguisher System Technicians
H.15.3.5 Qualifications of Halogenated Extinguishing System Technicians
H.15.3.6 Qualifications of Carbon Dioxide Extinguishing System Technicians
H.15.3.7 Qualifications of Ventilation System Fire Extinguishing System
Technicians
H.15.3.8 Qualifications of Smoke Control Technicians
H.15.3.9 Qualification of Fire Damper, Smoke Damper, and Combination
Fire/Smoke Damper Technicians
H.15.3.10 Qualifications of Fire-rated and Smoke Door Assemblies Technicians
H.15.3.11 Qualifications of Portable Fire Extinguisher Technicians
H.15.3.12 Qualification of Emergency and Standby Power System Technicians
H.15.3.13 Qualifications of Emergency Lighting Equipment and Exit Signage
Technicians
H.15.3.14 Qualifications of HVAC Technicians
H.15.3.15 Qualifications of AMS, BAS Technicians
H.15.3.16 Qualifications of Electrical Technicians H.15.4 Submission of Resumes for New Employees H.15.5 State Licensing H.15.6 Compliance with Federal, State, and Local Codes
H.16. GOVERNMENT-FURNISHED MATERIALS
H.16.1 Requirements for Network Connection
H.17. CONTRACTOR FURNISHED MATERIALS
H.18. ADDITIONAL SERVICES [INDEFINITE QUANTITY PROVISIONS]
H.18.1 General H.18.2 Price Proposal for Additional Services Work
H.18.3 Pricing
H.18.4 Parts and Materials
H.18.5. Labor
H.18.6 Subcontracts
H.18.7 Cost Documentation
H.18.8 Competitive Bids
H.18.9 Method of Ordering and Invoicing
H.19. AWARD FEE - RESERVED
H.20. STRIKE CONTINGENCY PLAN (SCP)
H.21. OCCUPANCY EMERGENCY PLAN (OEP)
H.22. CONTRACTOR PANDEMIC PLAN
I. CONTRACT CLAUSES
I.1 FAR 52.212-4 -- CONTRACT TERMS AND CONDITIONS -- COMMERCIAL ITEMS
(JAN 2017)
I.2 FAR 52.212-5 -- CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT
STATUTES OR EXECUTIVE ORDERS -- COMMERCIAL ITEMS (JAN 2017)
I.3 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
I.4 GSAM 552.212-71 CONTRACT TERMS AND CONDITIONS APPLICABLE TO GSA
ACQUISITION OF COMMERCIAL ITEMS (JUL 2016)
I.5 FAR 52.216-18 ORDERING (OCT 1995)
I.6 FAR 52.216-19 ORDER LIMITATIONS (OCT 1995)
I.7 FAR 52.216-22 INDEFINITE QUANTITY (OCT 1995)
I.8 FAR 52.217-8 OPTION TO EXTEND SERVICES (NOV 1999)
I.9 FAR 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)
I.10 FAR 52.222-42 STATEMENT OF EQUIVALENT RATES FOR FEDERAL HIRES (MAY
1989)
I.11 FAR 52.223-7 -- NOTICE OF RADIOACTIVE MATERIALS (JAN 1997)
I.12 FAR 52.223-11 -- OZONE-DEPLETING SUBSTANCES (MAY 2001)
I.13 FAR 52.252-4 - ALTERATIONS IN CONTRACT (APR 1984)
I.14 INSURANCE REQUIREMENTS
J. LIST OF ATTACHMENTS (LIST OF DOCUMENTS, EXHIBITS AND OTHER
ATTACHMENTS)
LIST OF EXHIBITS
EXHIBIT 1 QUALITY ASSURANCE PLAN (QASP)
EXHIBIT 2A Green PURCHASING REPORT - Non Bio-based Report
EXHIBIT 2B Green PURCHASING REPORT - Bio-based Report
EXHIBIT 3 SOLID WASTE AUDIT REPORT - RESERVED
EXHIBIT 4
SUMMARY OF ENVIRONMENTALLY SUSTAINABLE PRODUCT
ATTRIBUTES and OFFERINGS
EXHIBIT 5 MONTHLY REPORT TEMPLATE
EXHIBIT 6 BUILDING OPERATING PLAN TEMPLATE
EXHIBIT 7 SMART BUILDING - RESERVED
EXHIBIT 8 WATER TREATMENT
EXHIBIT 9 OPERATIONAL PERFORMANCE TARGETS
EXHIBIT 10 ENERGY AND WATER EFFICIENCY USE PLAN
EXHIBIT 11 ENERGY AND WATER EFFICIENCY MONTHLY REPORT
EXHIBIT 12 ANNUAL ENERGY& WATER EFFICIENCY REPORT
EXHIBIT 13 QUALIFICATIONS OF ELECTRICAL TESTING TECHNICIANS (ETT)
EXHIBIT 14 MISCELLANEOUS BEST PRACTICES - RESERVED
EXHIBIT 15 JFB BUILDING INFORMATION SHEET
EXHIBIT 16 FOB BUILDING INFORMATION SHEET
EXHIBIT 17 JFB INVENTORY
EXHIBIT 18 FOB INVENTORY
EXHIBIT 19 PREVENTIVE MAINTENANCE GUIDES/5850 rev 2012
EXHIBIT 20 SOLID WASTE and RECYCLING REPORT
EXHIBIT 21 EQUIPMENT FAILURE REPORT
EXHIBIT 22 CONTRACTOR INFORMATION WORKSHEET
EXHIBIT 23 DELIVERABLE CHART
LIST OF ATTACHMENTS
ATTACHMENT 1 STANDARD FORM 1449
ATTACHMENT 2 VENDOR VALIDATION INFORMATION
ATTACHMENT 3 COLLECTIVE BARGAINING AGREEMENT
ATTACHMENT 4 WAGE DETERMINATION
ATTACHMENT 5 SCHEDULE OF PRICING: O&M SERVICES
ATTACHMENT 6 SCHEDULE OF PRICING: PROFIT AND G/A
ATTACHMENT 7 SCHEDULE OF PRICING: SWITCHGEAR SERVICES
ATTACHMENT 8 SCHEDULE OF PRICING: ADDITIONAL SERVICE LINE ITEMS
ATTACHMENT 9 SCHEDULE OF PRICING: SUBCONTRACTOR SERVICES
ATTACHMENT 10 CHECKLIST OF ITEMS TO SUBMIT
ATTACHMENT 11 TECHNICAL EVALUATION QUESTIONS
ATTACHMENT 12 SERVICE DELIVERY QUESTIONS
ATTACHMENT 13 SWITCHGEAR SUBCONTRACTOR SELECTION
ATTACHMENT 14 PAST PERFORMANCE QUESTIONNAIRE
ATTACHMENT 15 CONTRACTOR-SUPPLIED EXPERIENCE QUESTIONNAIRE
K. REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF
BIDDERS/OFFERORS
K.1 SYSTEM FOR AWARD MANAGEMENT (SAM) REGISTRATION
L. INSTRUCTIONS, CONDITIONS, AND NOTICES TO BIDDERS/OFFERORS
L.1 INSTRUCTIONS FOR PROPOSAL PREPARATION
L.2 FAR 52.216-1 TYPE OF CONTRACT (APR 1984)
L.3 FAR 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB
1998)
L.4 GSAR 552.237-70 QUALIFICATIONS OF OFFERORS (MAY 1989)
L.5 FAR 52.204-7 SYSTEM FOR AWARD MANAGEMENT (JUL 2013)
L.6 FAR 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL ITEMS (JUL 2013)
M. EVALUATION FACTORS FOR AWARD
M.1 BASIS FOR AWARD AND TECHNICAL EVALUATION PROCESS
M.2 EVALUATION FACTORS
M.2.1 List of Evaluation Factors
M.2.1.1 Evaluation Factor 1: Technical Evaluation Questions (Vol. III)
M.2.1.2 Evaluation Factor 2: Service Delivery Questions (Vol. III)
M.2.1.3 Evaluation Factor 3: Switchgear Subcontractor Questionnaire (Vol. III)
M.2.1.4 Evaluation Factor 4: Past Performance (Vol. IV)
M.2.1.5 Evaluation Factor 5: Price (Vol. II)
M.3 EVALUATION METHODOLOGY
M.3.1 Technical Factors: Evaluation Methodology
M.3.2 Past Performance: Evaluation Methodology
M.3.3 Price: Evaluation Methodology
M.3.4 Competitive Range
M.3.5 Exchanges
M.3.6 Award without Discussions
SECTION A. SOLICITATION / CONTRACT FORM
A. SOLICITATION / CONTRACT FORM
A.1 FORMS
A.1.1 Standard Form 1449 Solicitation/Contract/Order for Commercial Items – Attachment A1
A.1.2 Addendum to Standard Form 1449 – Attachment A1
A.1.3 Vendor Validation Information Form – Attachment A2
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
1. REQUISITION NUMBER PAGE 1 OF
2. CONTRACT NO. 3. AWARD/EFFECTIVE
DATE
4. ORDER NUMBER 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE
DATE
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME b. TELEPHONE NUMBER (No collect calls)
8. OFFER DUE DATE/
LOCAL TIME
9. ISSUED BY
13b. RATING
14. METHOD OF SOLICITATION
CODE
15. DELIVER TO 16. ADMINISTERED BY CODE
18a. PAYMENT WILL BE MADE BY CODE17a. CONTRACTOR/
OFFEROR
CODE
FACILITY
CODE
CODE
TELEPHONE NO.
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN
OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK
BELOW IS CHECKED
RFQ IFB RFP
SEE ADDENDUM
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED
29. AWARD OF CONTRACT: REF. OFFER
DATED . . YOUR OFFER ON SOLICITATION
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR
30b. NAME AND TITLE OF SIGNER (Type or print) 30c. DATE SIGNED
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
31b. NAME OF CONTRACTING OFFICER (Type or print) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA - FAR (48 CFR) 53.212
10. THIS ACQUISITION IS UNRESTRICTED OR
NAICS:
SIZE STANDARD:
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
SET ASIDE: % FOR:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
ARE ARE NOT ATTACHED
ARE ARE NOT ATTACHED
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
8 (A)
EDWOSB
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SMALL BUSINESS
47PL0218R0003
Mr. Min Kim / Mr. Michael Metje (253)931-7081 / 326-1653
10PQD 100
Jackson Federal Building in Seattle WA (WA0101ZZ) Federal Office Building in Seattle, WA (WA0036ZZ)
10PQD
Acquisition Management Division Services Acquisition Branch 400 15th St SW, Auburn, WA 98001
GSA Finance Division (BCFA) PO Box 17181 Ft. Worth, TX 76102-0181
ONE
561210
$38.5 Million
05/01/2018 02/07/2018
03/02/2018
4:00 PM PST
GSA/PBS
Acquisition Management Division Services Acquisition Branch 400 15th St SW, Auburn, WA 98001
BCFA
STANDARD FORM 1449 (REV. 2/2012) BACK
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
AMOUNT
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
40. PAID BY
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELPHONE NUMBER OF AUTHORZED GOVERNMENT REPRESENTATIVE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
33. SHIP NUMBER 34. VOUCHER NUMBER 35. AMOUNT VERIFIED
CORRECT FOR
PARTIAL FINAL
37. CHECK NUMBER
38. S/R ACCOUNT NO. 39. S/R VOUCHER NUMBER
36. PAYMENT
COMPLETE PARTIAL FINAL
ADDENDUM TO STANDARD FORM 1449
Block 17a DUN & BRADSTREET NUMBER (DUNS):
Block 17b REMITTANCE ADDRESS:
In the event an EFT transfer does not work please indicate where a paper check should be mailed if the address is other than that shown on the Standard Form 1449, Solicitation/Contract/Order for Commercial Items:
SUBMIT WITH VOLUME I OF PROPOSAL
VENDOR VALIDATION INFORMATION
VENDOR: ___________________________________________________________________
DUNS NUMBER: _____________________________________________________________
TAX ID NUMBER: _____________________________________________________________
CONTRACT EXECUTIVE: The following contractor representative is hereby identified as the
Contract Executive and will negotiate submitted Request for Proposal (RFP).
Name: ______________________________________________________________________
Title: ________________________________________________________________________
Telephone Number: ____________________________________________________________
Email Address: _______________________________________________________________
SIGNATORY AUTHORITY: The following Contractor Representative is providing signatory authority on behalf of this contract.
Name: ______________________________________________________________________
Title: ________________________________________________________________________
Telephone Number: ____________________________________________________________
Email Address: _______________________________________________________________
SECTION B. SERVICES, ORDERING AND PRICES
Schedule of Pricing Sheets shall be used for submitting all pricing - see Attachments 5 – 9
B.1 DESCRIPTION OF SERVICES AND PRICES
The contractor must provide all management, supervision, labor, materials, supplies and equipment
(except as otherwise provided), and shall plan, schedule, coordinate and assure effective performance of all services described herein. The Contractor must provide O&M Services in accordance with the requirements of this solicitation. It is the responsibility of the Contractor to ensure that the necessary hours to meet the performance standards specified in the solicitation are built into the monthly recurring services price. Specific Requirements for the agreed upon performance is located in the Operations and
Maintenance Performance Work Statement, Inventory Lists, and other documents listed in Section J.
B.2 O&M AND RELATED SERVICES: GENERAL REQUIREMENT
General Services Administration, Region 10 has a requirement for Operations and Maintenance services at multiple buildings within the locations listed in the Schedule of Items. This is not a new require-ment. The requirements of this IDIQ are addressed in the Performance Work Statement (PWS). These requirements could include, but are not limited to: Locksmith services; Plumbing operations & mainte-nance; Electrical services to include: High/low voltage systems and maintenance and repair of exterior electrical distribution system; Maintenance of energy management control systems (EMCS); Refrigera-tion maintenance; Maintenance of renewable energy systems; Repair of water tanks; Fire alarm system preventive maintenance and repair service; Maintenance support training and consulting services; Fire suppression system preventive maintenance and repair services; Mechanical and operations maintenance
& repair of building systems to include: HVAC, boilers, chillers, etc.; Operation and Maintenance of water distribution systems and septic systems.
The Government’s intent is to establish an Indefinite Delivery/Indefinite Quantity contract for four (4) years and seven (7) months. The minimum guarantee will be satisfied via Task Order for BASE period services. The Task Order will order services for a base period of seven (7) months, and potentially four
(4) one year option periods for a total potential performance period of four (4) year and seven (7) months. This IDIQ requires a monthly Firm Fixed Price line item for specified services as described in the Performance Work Statement (PWS). The potential for ordering Additional Services within the scope of the IDIQ is a possibility, however, not a guarantee.
Federal Business Opportunities (FedBizOpps) will be the system for advertising and posting require-ments, posting questions & answers (Q&A) and accepting quotes. The open period for proposals will be in accordance with dates listed on FedBizOpps; to include, if any, extensions or changes to the require-ments.
List reimbursable items and costs identified during negotiations. These items will be levels of service that are above commercial standard. If an agency requires above commercial level service, they will be on a reimbursable basis (Example would an agency wants to the contractor to perform maintenance on their equipment this would be a reimbursable basis). Determine what reimbursable items will become tenant agency RWA efforts and detail those expenses below.
REIMBURSABLE ITEM COST
Offerors must price option year requirements for each additional twelve-month period by assuming that the minimum hourly wages and fringe benefits established by the Administrator, Wage and Hour
Division, U.S. Department of Labor for the initial twelve-month period of performance will apply to all additional twelve-month periods. The minimum wage rates and fringe benefits applicable to the initial twelve-month period of performance are outlined on Wage Determination 2015-5535, Revision 5, dated January 10, 2018.
Pricing Information: Quote a fully burdened rate for each line item for additional services when ordered, that is in addition to the base services specified under this contract. If ordered, the
Contractor shall invoice for these items separately. These items are not funded with the base services awarded under this contract.
The additional services provision is to be used to satisfy the Government’s short-term non-recurring needs for service. Should a continuing need for additional service arise, a contract modification will be negotiated with both parties in agreement.
Additional follow-on hourly rates may be adjusted on the anniversary date using current wage determination.
Fully Burdened Rates: This Indefinite Delivery/Indefinite Quantity (IDIQ) is established under the procedures in FAR 15. All quotes submitted shall include fully burdened labor rates to accomplish the tasks and any supplies and equipment required to perform the work. In addition, fully burdened rates are required to accomplish the tasks and any supplies and equipment required to perform additional services required by the IDIQ.
Monthly services: Monthly services will be awarded directly the base contract based on a monthly rate in accordance with the maintenance requirements specified in the PWS for each line item.
Additional services and Ancillary Minor Repair and Alteration (R&A) Services: All additional services to be furnished under this IDIQ shall be ordered through the issuance of task orders based on the hourly rates specified in each contract. Minor Repair and Alteration (R&A) Services shall be or-dered as ancillary to the monthly services or additional services. The labor rates proposed under this contract for additional services and any services considered ancillary Repair and Alternation services shall be based on the labor categories included in the base monthly services. The additional services
CLINs will be evaluated based on the labor rate proposed times the number of estimated hours for a total price. Award will be evaluated based on the aggregate price for the base monthly services only. The additional services will be evaluated for price reasonableness and to estimate the total contract dollar value only. Additional discounts are encouraged.
Precedence: All task orders will be firm fixed priced and specify the performance period for the re-quired services. The task order performance period may not extend beyond the expiration date of the current IDIQ period of performance. Modifications to existing task orders will be issued using the
Standard Form 30, “Amendment of Solicitation/Modification of Contract.” All task orders are subject to the terms and conditions of the IDIQ contract. In the event of conflict between a task order and the ID-
IQ, the IDIQ will take precedence.
Authority: Only warranted Contracting Officers within the General Services Administration, North-west/Arctic Region 10, Service Contracts Branch, are allowed to modify the established IDIQ.
Subject to Availability of Funds: Issuance of this Solicitation does not warrant that funds are presently available for award of a Contract. Award of the Contract shall be subject to the availability of appropri-ated funds, and the Government shall incur no obligation under this Solicitation in advance of such time as funds are made available to the Contracting Officer for the purpose of Contract award.
Proposal Preparation Costs: The costs for preparation of Task Order proposals shall be the responsibility of the contractor and not directly reimbursable. Each Task Order awarded will include at a minimum all management, supervision, mobilization, material, equipment labor, and other applicable costs as well as overhead and profit. The contractor shall furnish all project management, planning, estimating, labor, transportation, materials, equipment, tools, supervision, design if applicable, and all other associated costs necessary to fulfill the requirements of the Task Order.
Department of Labor Wage Determination: The following Wage Determination is incorporated into this IDIQ Contract as incorporated into this solicitation:
Wage Determination No.: 2015-5535, Revision No.: 5
Date of Revision: 01/10/2018
State: Washington
Area: King County
SECTION B. SERVICES, ORDERING AND PRICES
Schedule of Pricing Sheets shall be used for submitting all pricing - see Attachments 5 – 9
B.1 DESCRIPTION OF SERVICES AND PRICES
The contractor must provide all management, supervision, labor, materials, supplies and equipment
(except as otherwise provided), and shall plan, schedule, coordinate and assure effective performance of all services described herein. The Contractor must provide O&M Services in accordance with the requirements of this solicitation. It is the responsibility of the Contractor to ensure that the necessary hours to meet the performance standards specified in the solicitation are built into the monthly recurring services price. Specific Requirements for the agreed upon performance is located in the Operations and
Maintenance Performance Work Statement, Inventory Lists, and other documents listed in Section J.
B.2 O&M AND RELATED SERVICES: GENERAL REQUIREMENT
General Services Administration, Region 10 has a requirement for Operations and Maintenance services at multiple buildings within the locations listed in the Schedule of Items. This is not a new require-ment. The requirements of this IDIQ are addressed in the Performance Work Statement (PWS). These requirements could include, but are not limited to: Locksmith services; Plumbing operations & mainte-nance; Electrical services to include: High/low voltage systems and maintenance and repair of exterior electrical distribution system; Maintenance of energy management control systems (EMCS); Refrigera-tion maintenance; Maintenance of renewable energy systems; Repair of water tanks; Fire alarm system preventive maintenance and repair service; Maintenance support training and consulting services; Fire suppression system preventive maintenance and repair services; Mechanical and operations maintenance
& repair of building systems to include: HVAC, boilers, chillers, etc.; Operation and Maintenance of water distribution systems and septic systems.
The Government’s intent is to establish an Indefinite Delivery/Indefinite Quantity contract for four (4) years and seven (7) months. The minimum guarantee will be satisfied via Task Order for BASE period services. The Task Order will order services for a base period of seven (7) months, and potentially four
(4) one year option periods for a total potential performance period of four (4) year and seven (7) months. This IDIQ requires a monthly Firm Fixed Price line item for specified services as described in the Performance Work Statement (PWS). The potential for ordering Additional Services within the scope of the IDIQ is a possibility, however, not a guarantee.
Federal Business Opportunities (FedBizOpps) will be the system for advertising and posting require-ments, posting questions & answers (Q&A) and accepting quotes. The open period for proposals will be in accordance with dates listed on FedBizOpps; to include, if any, extensions or changes to the require-ments.
List reimbursable items and costs identified during negotiations. These items will be levels of service that are above commercial standard. If an agency requires above commercial level service, they will be on a reimbursable basis (Example would an agency wants to the contractor to perform maintenance on their equipment this would be a reimbursable basis). Determine what reimbursable items will become tenant agency RWA efforts and detail those expenses below.
REIMBURSABLE ITEM COST
N/A $0.00
Offerors must price option year requirements for each additional twelve-month period by assuming that the minimum hourly wages and fringe benefits established by the Administrator, Wage and Hour
Division, U.S. Department of Labor for the initial twelve-month period of performance will apply to all additional twelve-month periods. The minimum wage rates and fringe benefits applicable to the initial twelve-month period of performance are outlined on Wage Determination 2015-5535, Revision 5, dated January 10, 2018.
Pricing Information: Quote a fully burdened rate for each line item for additional services when ordered, that is in addition to the base services specified under this contract. If ordered, the
Contractor shall invoice for these items separately. These items are not funded with the base services awarded under this contract.
The additional services provision is to be used to satisfy the Government’s short-term non-recurring needs for service. Should a continuing need for additional service arise, a contract modification will be negotiated with both parties in agreement.
Additional follow-on hourly rates may be adjusted on the anniversary date using current wage determination.
Fully Burdened Rates: This Indefinite Delivery/Indefinite Quantity (IDIQ) is established under the procedures in FAR 15. All quotes submitted shall include fully burdened labor rates to accomplish the tasks and any supplies and equipment required to perform the work. In addition, fully burdened rates are required to accomplish the tasks and any supplies and equipment required to perform additional services required by the IDIQ.
Monthly services: Monthly services will be awarded via Task Order against the base contract based on a monthly rate in accordance with the maintenance requirements specified in the PWS for each line item.
Additional services and Ancillary Minor Repair and Alteration (R&A) Services: All additional services to be furnished under this IDIQ shall be ordered through the issuance of task orders based on the hourly rates specified in each contract. Minor Repair and Alteration (R&A) Services shall be or-dered as ancillary to the monthly services or additional services. The labor rates proposed under this contract for additional services and any services considered ancillary Repair and Alternation services shall be based on the labor categories included in the base monthly services. The additional services
CLINs will be evaluated based on the labor rate proposed times the number of estimated hours for a total price. Award will be evaluated based on the aggregate price for the base monthly services only. The additional services will be evaluated for price reasonableness and to estimate the total contract dollar value only. Additional discounts are encouraged.
Precedence: All task orders will be firm fixed priced and specify the performance period for the re-quired services. The task order performance period may not extend beyond the expiration date of the current IDIQ period of performance. Modifications to existing task orders will be issued using the
Standard Form 30 (SF30), “Amendment of Solicitation/Modification of Contract.” All task orders are subject to the terms and conditions of the IDIQ contract. In the event of conflict between a task order and the IDIQ, the IDIQ will take precedence.
Authority: Only warranted Contracting Officers within the General Services Administration, North-west/Arctic Region 10, Service Contracts Branch, are allowed to modify the established IDIQ.
Subject to Availability of Funds: Issuance of this Solicitation does not warrant that funds are presently available for award of a Contract. Award of the Contract shall be subject to the availability of appropri-ated funds, and the Government shall incur no obligation under this Solicitation in advance of such time as funds are made available to the Contracting Officer for the purpose of Contract award.
Proposal Preparation Costs: The costs for preparation of Task Order proposals shall be the responsibility of the contractor and not directly reimbursable. Each Task Order awarded will include at a minimum all management, supervision, mobilization, material, equipment labor, and other applicable costs as well as overhead and profit. The contractor shall furnish all project management, planning, estimating, labor, transportation, materials, equipment, tools, supervision, design if applicable, and all other associated costs necessary to fulfill the requirements of the Task Order.
Department of Labor Wage Determination: The following Wage Determination is incorporated into this IDIQ Contract as incorporated into this solicitation:
Wage Determination No.: 2015-5535, Revision No.: 5
Date of Revision: 01/10/2018
State: Washington
Area: King County
February 2018
SECTION C. DESCRIPTION/ SPECIFICATION/ PERFORMANCE WORK STATEMENT
INTRODUCTION
C.2.2 Acts of God C.2.3 Additional Services C.2.4 Advanced Meters C.2.5 Advanced Metering Systems C.2.6 Approval C.2.7 Architectural and Structural C.2.8 Basic Services C.2.9 Building Automation System (BAS) C.2.10 GSALink C.2.11 Building Operating Plan C.2.12 Commissioning C.2.13 Ongoing Commissioning C.2.14 National Computerized Maintenance Management System (NCMMS) C.2.15 Consumable Parts C.2.16 Contracting Officer (CO) C.2.17 Contracting Officer Representative (COR) or Designee C.2.18 Contractor C.2.19 Contractor’s Other Than Normal Working/Duty Hours C.2.20 Controls and Control System C.2.21 Defective Service C.2.22 Emergency C.2.23 Emergency Callback C.2.24 Environmentally Sustainable C.2.25 Existing Deficiency List Report C.2.26 Exterior C.2.27 Federal Holidays C.2.28 Federal Executive Holidays, Unanticipated C.2.29 Fire Protection and Life Systems C.2.30 Guiding Principles for Sustainable Existing Buildings C.2.31 GSA Green Purchasing Program (GPP) C.2.32 Indefinite Quantity
C.2.33 Miscellaneous Repair C.2.34 Miscellaneous Work C.2.35 Modification of Contract C.2.36 Negligence C.2.37 Non-reimbursable Repairs C.2.38 Normal Working Hours C.2.39 Occupant Emergency Plan (OEP) C.2.40 Open Systems C.2.41 Operations C.2.42 Performance Based Service Contracting C.2.43 Performance Work Statement (PWS) C.2.44 Predictive Maintenance C.2.45 Preventive Maintenance (Scheduled and Unscheduled) C.2.46 Product Preference C.2.47 Quality Assurance Surveillance Plan (QASP) C.2.48 Quality Control Plan C.2.49 Repair C.2.50 Reimbursable Repair C.2.51 Sequence of Operations C.2.52 Work Request / Work Order C.2.53 Standard Services C.2.54 Stewardship C.2.55 Supervisor, On-Site C.2.56 Tour
C.4.1 Initial Inspections
C.5 START-UP PHASE/TRANSITION PHASE
C.5.2 Startup Phase Schedule - Reserved C.5.3 Adjustments and Corrections
C.6 PHASEOUT TRANSITION PERIOD
C.7 DEFICIENCY LIST COMPLETION AND WITHHOLDING OF FINAL PAYMENT
C.8 GENERAL AND ADMINISTRATIVE REQUIREMENTS
C.8.1 Minimum Staffing C.8.2 Communication Equipment C.8.3 Onsite Records C.8.4 Work Request / Work Order and Administrative Support C.8.5 Use of NCMMS C.8.6 Quality Control Program C.8.7 Government Quality Assurance Surveillance Program
C.8.7.1 Contract Performance C.8.7.2 Methods
C.8.7.3 Records and Files C.8.7.4 Cooperation – Inspections C.8.7.5 Contractor Performance System (CPARS)
C.9 BUILDING OPERATING PLAN
C.9.1 Building Operating Plan C.9.2 Components of the Building Operating Plan
C.10 EQUIPMENT INVENTORY
C.11 MONTHLY PROGRESS REPORTS
C.12 PERFORMANCE REVIEW MEETINGS
C.13 EQUIPMENT CONDITION ASSESSMENTS
C.14 OCCUPANT FEEDBACK PROGRAM
C.15 REFERENCE LIBRARY
C.16 REVIEW OF DESIGN DOCUMENTS
C.17 BUILDING MANAGEMENT AND SUPPORT SERVICES (MISCELLANEOUS AND UTILITY
ESCORT HOURS)
C.18 INSPECTIONS ASSISTANCE FOR SPACE BUILD OUTS
C.19 EMERGENCY SHUTDOWN INSTRUCTIONS AND TOUR CHECKLISTS
C.20 LABELING OF ELECTRICAL CIRCUITS
C.21 OPERATIONAL REQUIREMENTS
C.21.1 General C.21.2 Extended Operating Hours C.21.3 Continuity of Operations (COOP) C.21.4 Emergency Operations Plan C.21.5 Tenant Environment C.21.6 Energy and Water Efficiency
C.22 SYSTEM PERFORMANCE STANDARDS OR PROCEDURES
C.23 WORK REQUEST / WORK ORDERS
C.23.1 General C.23.2 Emergency Work Request / Work Order C.23.3 Emergency Call Back (after hours) C.23.4 Urgent Work Request / Work Order Response C.23.5 Routine Work Request / Work Order Response
C.24 TOURS
C.24.1 General C.24.2 Operating Logs and Tour Check Sheets C.24.3 Tour Frequencies
C.24.4 Condensate Drip Pans C.24.5 Monitoring of Central Plant Equipment C.24.6 Leak Testing
C.24.7 Equipment Failure Reports
C.25 DEMAND RESPONSE PROGRAMS
C.26 CURTAILMENT PLAN - RESERVED
C.27 BAS ALARM RESPONSE
C.28 ADVANCED METERING PROGRAM
C.28.1 Verification and Calibration
C.29 PROTECTION AND DAMAGE
C.30 NEGLIGENCE
C.31 KEY CONTROL AND LOCKSMITH SERVICES
C.32 DISRUPTIVE OR HAZARDOUS TOOLS
C.33 SCHEDULED DISRUPTION TO UTILITIES, LIGHTING, FIRE PROTECTION & LIFE
SAFETY SYSTEMS, OR SPACE CONDITIONING
C.34 PLUMBING AND RESTROOMS
C.35 MAINTENANCE PROGRAM
C.35.1 General C.35.2 Maintenance Standard C.35.3 Application of Diagnostic Software C.35.4 BAS Control Systems
C.35.4.1 BAS Operating Standards
C.35.4.1.1 GSA-hosted Systems Requirements
C.35.4.1.2 Excepted Systems Requirements (not hosted on GSA’s system infrastructure)
C.35.4.2 Reporting
C.35.4.3 Staffing
C.35.5 Smart Building Technology - Reserved
C.35.6 Ongoing Commissioning/Re-Tuning - Reserved
C.35.7 Switchgear and Electrical Distribution Equipment
C.36 WATER TREATMENT
C.36.1 General C.36.2 Tolerances
C.36.3 Initial Report and Development of Program C.36.4 Cooling Tower Water Management Plan C.36.5 Corrosion Monitoring C.36.6 Monthly Testing
C.37 OIL ANALYSIS AND OIL CHANGES
C.37.1 Periodic Oil Analysis
C.37.2 Oil and Refrigerant Additives C.37.3 Oil Changes
C.37.4 Generator Oil Testing
C.37.5 Diesel Fuels Level Checks and Testing
C.38 LAMPS AND BALLASTS
C.39 ARCHITECTURAL AND STRUCTURAL SYSTEMS MAINTENANCE
C.39.1 General C.39.2 Maintenance Repair C.39.3 Repair and Replacement Work C.39.4 Painting C.39.5 Interior Signage and Directories C.39.6 Finishes Maintenance C.39.7 Historic Building Preservation C.39.8 Vertical Transportation and Associated Equipment C.39.9 Flag Procedures
C.40 REPAIRS
C.40.1 General C.40.2 Non-reimbursable Repairs C.40.3 Reimbursable Repairs C.40.4 Miscellaneous Work C.40.5 Repair Shared Liability Example C.40.6 Approval of Work C.40.7 Invoicing C.40.8 Ordering Repairs from Outside Source C.40.9 Force Majeure (Uncontrollable events) C.40.10 Warranties C.40.11 Quality of Materials and Replacement Parts
C.41 SAFETY & ENVIRONMENTAL MANAGEMENT
C.41.1 General C.41.2 Scheduling and Recordkeeping C.41.3 Refrigerant
C.41.3.1 Control and Certification C.41.3.2 Certified Handlers
C.41.4 Air Emissions C.41.4.1 Local Air Quality Management Operating Permits
C.41.5 Fuel Storage Tank Management
C.41.5.1. Underground Storage Tank Management
C.41.5.2 Above Ground Storage Tank Management
C.41.6 Solid Waste Audit - Reserved
C.41.7 Polychlorinated Biphenyl (PCB) Control - Reserved
C.41.8 Facility Hazards
C.41.9 Workplace Safety
C.41.10 Electrical Safety
C.41.11 Fall Protection
C.41.12 Powered Platforms
C.41.13 Lock Out/Tag Out
C.41.14 Confined Spaces
C.41.15 Asbestos Management
C.41.16 Hazardous Materials
C.41.16.1 Safety Data Sheet (SDS)
C.41.16.2 Disposition of Waste
C.41.16.2.1 Non-Hazardous Solid Waste
C.41.16.2.2 Universal Waste
C.41.16.2.3 PCB Wastes and Ballasts
C.41.16.2.4 Hazardous Waste
C.41.16.2.5 Recycling Hazardous Waste and Electronic Waste
C.41.16.2.6 Miscellaneous Hazardous Substance Disposal
C.41.16.2.7 Used Oil
C.41.16.3 Environmental Reporting
C.41.16.4 Sustainable Products and Reporting
C.41.16.4.1 Key Sustainable Product (KSP)
C.41.16.4.2 Proof of Compliance
C.41.16.4.3 Recycled Content Product Purchase Annual Reporting
C.41.16.4.4 Bio-Based Products
C.41.16.4.5 Green Cleaning Plan
C.41.17 Boiler/Pressure Vessel Operation and Inspection Standards
C.41.17.1 Boiler Operation and Inspection
C.41.17.2 Inspection and Test
C.41.18. Potable Water Systems
C.41.18.1 Use of Lead-Free Plumbing Materials
C.41.18.2 Potable Water System Disinfection
C.41.18.3 Backflow Prevention Devices
C.41.19 Labeling and Signage
C.41.20 Roof Anchorage Points
C.42 FIRE PROTECTION AND LIFE SAFETY EQUIPMENT AND SYSTEMS
C.42.1 General
C.42.2 Fire Alarm System Services
C.42.3 Water Based Fire Suppression System
C.42.4 Fire-rated Door Assemblies
C.42.5 Fire Damper and Combination Fire/Smoke Dampers
C.42.6 Smoke Doors Assemblies
C.42.7 Smoke Dampers
C.42.8 Portable Fire Extinguishers
C.42.9 Non-Water-Based Fire Extinguishing Systems
C.42.10 Smoke Control Systems
C.42.11 Emergency and Standby Power Systems
C.42.12 Emergency Lighting Systems and Exit Signage
C.43 MAINTENANCE AND REPAIR OF VERTICAL TRANSPORTATION SYSTEMS - RESERVED
C.44 SUBMITTALS CHART (CONTRACTOR DELIVERABLES)
C.45 FEDERAL REQUIREMENTS
Introduction
This is a Performance Based Service Contract and the success of the Contract depends on the satisfaction of the requirements, but also the satisfaction of our shared customer. Rather than a mere list of activities, this is a written expression of the GSA’s expectation of the service to be performed by the
Operations and Maintenance Contractor (known from here on as Contractor). A higher level of effective communication between the Government and Contractor is essential for partnering and for the performance based service contract to succeed. The success of this Contract is shared between the
Government and the Contractor.
More emphasis is placed on the Contractor’s self-management of quality, not the usual external inspection by Government Inspectors, although that is a part of this Contract as well. All parties should act proactively to reduce service cost, therein providing an incentive for the Contractor.
The Contractor, through innovation, technology, or other means, shall perform the required maintenance of these facilities by following the Guiding Principles for Sustainable Existing Buildings.
While working with the Government, the Contractor is motivated to obtain GSA’s goals through improved methods of performance to assist GSA in reducing operating cost. The effectiveness of this partnership will be demonstrated in GSA attaining its goals.
The Contractor shall be responsible to provide management, supervision, labor, materials, equipment, and supplies and is responsible for the efficient, effective,…