About this file

This solicitation package is for the replacement of the fire alarm and installation of a fire suppression system at the Sumas Land Port of Entry located in Sumas, Washington. Interested vendors must create a GSA Google email account to access controlled unclassified information documents related to the project. The objective is to design and install a code-compliant fire alarm control panel, conductors, devices, and notification appliances to replace the existing Simplex Grinnell system. The scope also includes replacing the existing partially-installed dry fire suppression system cross main and installing sprinklers in the attic fan room. A pre-proposal site visit will take place on August 4, 2021. Responses are due by August 25, 2021 and should be emailed to the points of contact listed. All inquiries must be submitted by August 11. The solicitation is a total small business set-aside, and NAICS code 238210 applies.

View the file

Other files for this federal contract opportunity

Other files attached to Sumas Fire Alarm and Fire Suppression Modernization, newest first.
File Type Posted
2 Solicitation 47PL0121R0035 Revised by Amd 04.pdf PDF
Solicitation Amendment 47PL0121R0035-A0004.pdf PDF
Calculation of Self Performed Work.pdf PDF
Solicitation Amendment 47PL0121R0035-A0003.pdf PDF
Solicitation Amendment 47PL0121R0035-A0002.pdf PDF
2 Solicitation 47PL0121R0035.pdf PDF
Solicitation Amendment 47PL0121R0035-A0001.pdf PDF
1 SF1442 47PL0121R0035.pdf PDF
4 Agreement 47PL0121R0035.pdf PDF
Exhibit 2 Project Experience Form.docx DOCX document
A3 GSA Region 10 - Policy for Fire Watches.pdf PDF
2 Solicitation 47PL0121R0035.pdf PDF
5 Statement of Work.pdf PDF
Exhibit 1 Price Services Schedule.docx DOCX document
A4 GSA Vendor Fitness Determination Training Manual_Final.pdf PDF
1 SF1442 47PL0121R0035.pdf PDF
3 Reps and Certs 47PL0121R0035.pdf PDF
6 Wage Determination WA20210019 2021 01 01.pdf PDF
PPI Log 47PL0121R0035.xlsx XLSX spreadsheet
Exhibit 1-a Sample Cost Breakdown Format.xlsx XLSX spreadsheet
Exhibit 3 Sample Key Personnel Resume Format.docx DOCX document
A1 GSA R10 - FA Design Installation Testing Policy.pdf PDF
A2 GSA Region 10 - Fire Watch Log.pdf PDF
A5 GACA - GSA Affiliated Customer Accounts May 2014.docx DOCX document
Exhibit 4 Past Performance Questionnaire.docx DOCX document
Exhibit 0 Read Me First - CUI Document.docx DOCX document
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

Amend No. Item # Date

Submitted

Question

Type

(Technical or

Admin)

Question Response

Date Response

Responded

By

A0003 01 7/21/2021 Admin

See statement of work page 14 of 21 Paragraph 2.18 Period of performance 205 calendar days From NTP . Please confirm NTP will come after the design period so field construction will be for 205 days after design is completed.

7/22/2021

2.18 CONSTRUCTION PERIOD OF PERFORMANCE

Period of performance will be 205 calendar days after construction NTP.

(Design completion then Construct.)

GSA/PM

Melissa Hibray

A0003 02 7/21/2021 Admin

See statement of work page 16 0f 21 ,paragraph 3.1 line C please confirm all site work to be off hours from 1800 to 0600 hours Monday through Friday.

7/22/2021 All site work will take place after hours Monday-Friday (1800-0600)

GSA/PM

Melissa Hibray

A0004 03 7/26/2021 Admin

Re: Solicitation page 13, Factor 1 Relevant Experience Submission

Requirements:

Solicitation states, “Limit the submittal for each fire alarm, fire suppression and electrical project example to two (2) pages each using the Project Experience Form attached (Exhibit 2). **NOTE: Any pages in excess of the one (1) page per project example limit (excluding back page instructions) will not be considered for evaluation purposes.”

Question: this statement states we are allow two pages, then states we are only allowed one page per project.

The Exhibit 2 provided does not have a back page of instructions.

Is offeror allowed two pages per project or only one page per project?

7/28/2021

Solicitation Para II.D. Factor 1, 2) a. will be changed as below.

Limit the submittal for each fire alarm, fire suppression and electrical project example to One (1) page each using the Project Experience

Form attached (Exhibit 2). **NOTE: Any pages in excess of the one (1) page per project example limit will not be considered for evaluation purposes.

CO

Thupten Tsering

A0004 04 7/26/2021 Admin

Re: Solicitation page 11, Factor 1 Relevant Experience

Question: For evaluation purposes, can the Offeror use relevant projects from key subcontractors to demonstrate “Proposed Builder” experience?

7/28/2021

Yes, the prime contractor can use their subcontractors' relevant proejct experience.

Factor 1 will be amended to require Name of Firm that performed the proejct (Prime / Proposed Subcontractor)

However, there is a subcontracting limitation for prime contractor which require performing at least 25 percent of the cost of the contract, not including the cost of materials, with its own employees. as stated in the

Solicitaiton Para II.E. (2).

CO

Thupten Tsering

A0004 05 7/26/2021 Admin

Re: Solicitation, Proposal Submission Requirements: Factor 1-Relevant

Experience and Factor 4-Past Performance

Factor 1 (page 11) states only four projects may be submitted (2 from the

Proposed Builder and 2 from the Designer).

It states, “ any additional projects submitted over the limit specified herein shall not be considered during evaluation.”

Factor 4 (page 19) state, “No more than eight (8) DB Reference

Questionnaires (Exhibit 4) total for the Design/Build Team shall be submitted (i.e. both the Builder and the Designer together). DB

Reference Questionnaires shall be submitted for all projects identified in

FACTOR 1 for which a Relevant Experience form (Exhibit 2) was submitted. Additional surveys will not be considered.”

Question: I am confused by this as only 4 projects may be submitted in

Factor 1, but up to 8 Questionnaires may be submitted in Factor 4. Does this mean we can submit 2 questionnaires for each project, using two different customer POCs? Or is this an error?

7/28/2021

The statement "No more than eight (8) DB Reference Questionnaires

(Exhibit 4) total for the Design/Build Team shall be submitted (i.e. both the Builder and the Designer together)." in the Solicitation Factor 4, Submittal Requirement has been deleted.

Offeror shall submit DB questionnaire for all projects in Factor 1.

CO

Thupten Tsering

A0004 06 7/26/2021 Admin

Re: Factor 4- Past Performance.

On page 19, the instructions for submitting questionnaires seems conflicting.

First, it states, “The Offeror shall submit the partially completed DB

Reference Questionnaire (Exhibit 4) to the Project’s Owner for completion and submission either back to the Offeror or directly to the

GSA. Completed forms shall be signed and dated by the reference completing them and shall be submitted to the Contracting Officer identified on this Solicitation as part of the technical proposal or directly by the customer.”

Again, it states, “To be considered, the surveys must be completed by the customers (signed and dated) and emailed directly by the customer to the Contracting Officer identified at I.C or with the technical proposal, for receipt no later than the time and date proposals are due.”

Then it states, “Surveys submitted directly by Offerors…may not be considered.”

Question: Please confirm that offerors may submit completed questionnaires directly to the Contracting Officer as part of the Technical

Proposal.

7/28/2021

Yes. All completed DB Reference Questionnaire (Exhibit 4) shall be completed by their customers and submitted by an offeror as part of their technical proposal.

CO

Thupten Tsering

A0005 07 8/5/2021 Admin Can you please provide the Site Visit Sign in Sheet 8/12/2021 Provided. See attached.

CO

Thupten Tsering

A0005 08 8/6/2021 Admin Will CPARS or previously completed PPQS be accepted and considered for past performance or are new PPQ’s required?

8/12/2021

Solicitation Evaluation Factor 4 - Past Performance, Description says that Offeror may also provide copies of CPARS (ACASS, CCASS, and

CPARS) and PPIRS evaluations for relevant projects (Final ratings will be verified in PPIRS) identified in Factor 1.

Previously completed PPQs are NOT allowed and the referenced projects must be related to the project presented for the Factor 1 as indicated in the solicitation. The PPQs (Exhibit 4) in this solicitation must be completed.

CO

Thupten Tsering

1PPI Log 47PL0121R0035 as of 2021 08 12.xlsx.pdf
PPI Log
Key
topmostSubform[0]:
Page1[0]:
Code[0]: 10PQCB2
Copies[0]: 1
CheckBox9[0]: 1
Code[2]: 10PQCB2
NameandTitleOfficer[0]: Thupten Tsering, Contracting Officer
Is[0]: Off
CheckBox10[0]: Off
NameandAddress[0]:
DateSigned[1]:
Pages[0]: 4
AmendmentNo[0]: 0005
Dated10B[0]:
ModificationNo[0]:
AdministeredBy[0]: Acquisition Management Division

Construction Branch Team B 400 - 15th Street SW Auburn, WA 98001-6599 USA

FacilityCode[0]:
CheckBox13B[0]: Off
CheckBox13D[0]: Off
ReqNumber[0]: EQ10PCP-20-0014
Dated9B[0]: 7/13/2021
C13[0]:
Description[0]: A. The purpose of this amendment is to provide 1) Site Visit Sign-in Sheet and 2) Updated PPI Log as of Aug 12, 2021.

B. Additional questions will not be accepted.

C. All other terms and conditions of this Solicitation remain unchanged.

NotExtended[0]: 1
Code[1]:
AmendmentNo[1]: 47PL0121R0035
ContractIDCode[0]:
DateSigned[0]:
CheckBox11[0]: 1
Page[0]: 1
AccountingData[0]:
CopiesReturned[0]:
CheckBox13A[0]: Off
IsNot[0]: Off
EffectiveDate[0]: 8/12/2021
A13[0]:
ProjectNo[0]:
CheckBox13C[0]: Off
Extended[0]: Off
D13[0]:
IssuedBy[0]: Acquisition Management Division

Construction Branch Team B 400 - 15th Street SW Auburn, WA 98001-6599 USA NameandTitleSigner[0]:

Page2[0]:
TextField1[5]:
TextField1[4]:
TextField1[3]:
TextField1[2]:
TextField1[1]:
TextField1[0]:

File details come from the government source that posted it. Updated .